Home / Browse projects / Pune, Maharashtra / AKSHAY HERITAGE

Registration lapsed No litigation declared Residential / Group Housing project

AKSHAY HERITAGE

By AKSHAY BUILDERS

RG-MH-27442 · RERA P52100033825 · Last updated on MahaRERA portal: 24 Jul 2025

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 22 months past the filed date
  • 1 complaint at MahaRERA

Clear

  • No litigation declared
  • Completion date never moved
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Dec 2024Possession promised22 months past this date
8 of 22Construction stages doneacross 2 buildings; furthest along: Slabs of Super Structure, 75%
1Complaints at MahaRERAon this registration
Jump to the 113 documents Report an error

AKSHAY HERITAGE is a Residential / Group Housing project by AKSHAY BUILDERS in Pune, Maharashtra, registered with MahaRERA as P52100033825 on 8 Mar 2022. Possession was promised by 31 Dec 2024 and is now 22 months past that date. 1 complaint is on record with the regulator.

At a glance

Project

  • NameAKSHAY HERITAGE
  • TypeResidential / Group Housing
  • Location
    • VADMUKHWADI
    • PUNE
    • Wadmukhwadi
    • Haveli
    • 412105
  • Pincode412105
  • RERA no.P52100033825
  • ReraGenie IDRG-MH-27442

Builder

  • NameAKSHAY BUILDERS
  • Entity typePartnership
  • PartnersRAJENDRA RAMANLAL LUNKAD, PARIKSHIT PRAKASH NAHAR
  • Other registrations2 more →
  • Completed1 of 3
  • No longer live1 lapsed, de-registered or revoked
  • Declared earlier projects1 →

Key dates

22 months past promisethis monthRegisteredMar 2022PromisedDec 2024

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on8 Mar 2022
  • Promised completion31 Dec 2024
  • Revised completionNone
  • Buildings2 building records
  • Documents filed113 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
A1 BUILDINGNA150000
A2 BUILDINGNA150000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building2

As on 24 Jul 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

8 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Slabs of Super Structure, at 75%.

A1 BUILDING52%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure75%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises40%
Sanitary Fittings within the flats / premises15%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks40%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
A2 BUILDING50%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure70%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises35%
Sanitary Fittings within the flats / premises15%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks35%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 24 Jul 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceYes0%
Open ParkingYes0%

Parking filed102

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots102
Closed/Covered59
Open Space43
BuildingClosed/CoveredOpen SpaceTotal
A1 BUILDING241741
A2 BUILDING352661

Land and ownership

Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area3,999 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on12 May 2026

Approvals and building plan

Sanctioning authorityPimpri chinchwad municipal corporation
Permissible FSI10803.87
Proposed, not sanctioned4,511 sq m
Buildings approved2
Buildings sanctioned2

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchLAUKIK APARTMENTS, BHANDARKAR ROAD, PUNE

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectKHIRE BHIDE & ASSOCIATES
EngineerASHISH PRAKASH DAHAKE
Chartered AccountantMUTTHA AND LAHOTI CHARTERED ACCOUNTANT
PartnerRole in project
AKSHAY BUILDERS-

Complaints filed with MahaRERA1

Case no.ComplainantRespondentFiled
CC12500485Chandrashekhar TurkarAKSHAY BUILDERS13/02/2025

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 17 Feb 2022
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 5 Sep 2023
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 8 Jan 2024
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 8 Jan 2024Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed113

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 113 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 upto 31-03-2025.pdf24 Jul 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 upto 30-06-2025.pdf24 Jul 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 upto 31-03-2025.pdf24 Jul 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 upto 31-03-2025.pdf24 Jul 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 upto 30-06-2025.pdf24 Jul 2025
Disclosure of sold/ booked inventoryFile: DISCLOSURE OF SOLD BOOKED INVENTORY A1 Building upto 31-12-2024.pdf24 Jul 2025
Disclosure of sold/ booked inventoryFile: DISCLOSURE OF SOLD BOOKED INVENTORY A2 Building upto 31-12-2024.pdf24 Jul 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: F2A AKSHAY BUILDERS - AKSHAY HERITAGE - 2024-25.pdf24 Jul 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: F3 Q4 FY 2024-25 Akshay Heritage_compressed.pdf20 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: F2 Q4 FY 2024-25 Akshay Heritage.pdf20 Apr 2025
Declaration in FORM BFile: 4 MAHARERA Form B Declaration by Promoter.pdf20 Feb 2025
Disclosure of sold/ booked inventoryFile: 3 Disclosure of Sold Unsold Invetory.pdf20 Feb 2025
Declaration about all RERA Designated Bank Accounts (Format A)File: 6 Format A for Bank Details.pdf20 Feb 2025
Disclosure of Interest in Other Real Estate OrganizationsFile: 5 Disclosure of interest in other organisations - SIGNED.pdf20 Feb 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: FORM 2A signed.pdf20 Feb 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: 2 AKSHAY BUILDERS - AKSHAY HERITAGE signed.pdf20 Feb 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: F3 Q2 FY 2024-25 Akshay Heritage_compressed.pdf22 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: F3 Q3 FY 2024-25 Akshay Heritage_compressed.pdf22 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: F2 Q3 FY 2024-25 Akshay Heritage.pdf22 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: F1 Q3 FY 2024-25 Akshay Heritage_compressed.pdf20 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: F1 Q2 FY 2024-25 Akshay Heritage.pdf29 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: F2 Q2 FY 2024-25 Akshay Heritage.pdf29 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: F1 Q1 FY 2024-25 Akshay Heritage_compressed.pdf19 Aug 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: F3 Q1 FY 2024-25 Akshay Heritage_compressed.pdf20 Jul 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 AH Q1 2024-25.pdf19 Jul 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: AKSHAY HERITAGE FORM 1.pdf23 Apr 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: AKSHAY HERITAGE FORM 2.pdf20 Apr 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: AKSHAY HERITAGE FORM III_compressed.pdf20 Apr 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: F1 Q3 FY 2023-24 Akshay Heritage.pdf20 Jan 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: F2 Q3 FY 2023-24 Akshay Heritage.pdf20 Jan 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: F3 Q3 FY 2023-24 Akshay Heritage_compressed.pdf20 Jan 2024
Building plan approvalFile: HPSC1937.pdf8 Jan 2024
Building plan approvalFile: HPSC1938.pdf8 Jan 2024
Building plan approvalFile: HPSC1939.pdf8 Jan 2024
Building plan approvalFile: HPSC1940.pdf8 Jan 2024
Building plan approvalFile: HPSC1942.pdf8 Jan 2024
Building plan approvalFile: HPSC1943.pdf8 Jan 2024
Building plan approvalFile: HPSC1944.pdf8 Jan 2024
Building plan approvalFile: HPSC1945.pdf8 Jan 2024
Building Plan Approval / NA Order for plotted developmentFile: HPSC1937.pdf8 Jan 2024
Building Plan Approval / NA Order for plotted developmentFile: HPSC1938.pdf8 Jan 2024
Building Plan Approval / NA Order for plotted developmentFile: HPSC1939.pdf8 Jan 2024
Building Plan Approval / NA Order for plotted developmentFile: HPSC1940.pdf8 Jan 2024
Building Plan Approval / NA Order for plotted developmentFile: HPSC1942.pdf8 Jan 2024
Building Plan Approval / NA Order for plotted developmentFile: HPSC1943.pdf8 Jan 2024
Building Plan Approval / NA Order for plotted developmentFile: HPSC1944.pdf8 Jan 2024
Building Plan Approval / NA Order for plotted developmentFile: HPSC1945.pdf8 Jan 2024
Commencement Certificates / NA Order for plotted developmentFile: AH Revised commecement certificate_compressed.pdf8 Jan 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: F1 Q2 FY 2023-24 Akshay Heritage.pdf20 Oct 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: F2 Q2 2023-24 Akshay Heritage.pdf20 Oct 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: F3 Q2 2023-24 Akshay Heritage.pdf20 Oct 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: 2022-23 Akshay Heritage.pdf30 Sep 2023
Layout approvalFile: AH - W - LAYOUT.PDF5 Sep 2023
Building plan approvalFile: AH - W - A1 1ST TO 13TH FLOOR.PDF5 Sep 2023
Building plan approvalFile: AH - W - A1 SECTIONS.PDF5 Sep 2023
Building plan approvalFile: AH - W - A1 TOP TERRACE - SECTIONS.PDF5 Sep 2023
Building plan approvalFile: AH - W - A2 14.PDF5 Sep 2023
Building plan approvalFile: AH - W - A2 BASEMENT TO 13TH FLOOR.PDF5 Sep 2023
Building plan approvalFile: AH - W - BASEMENT, GROUND FLOOR.PDF5 Sep 2023
Copy of Layout Approval (in case of layout)File: AH - W - LAYOUT.PDF5 Sep 2023
Building Plan Approval / NA Order for plotted developmentFile: AH - W - A1 1ST TO 13TH FLOOR.PDF5 Sep 2023
Building Plan Approval / NA Order for plotted developmentFile: AH - W - A1 SECTIONS.PDF5 Sep 2023
Building Plan Approval / NA Order for plotted developmentFile: AH - W - A1 TOP TERRACE - SECTIONS.PDF5 Sep 2023
Building Plan Approval / NA Order for plotted developmentFile: AH - W - A2 14.PDF5 Sep 2023
Building Plan Approval / NA Order for plotted developmentFile: AH - W - A2 BASEMENT TO 13TH FLOOR.PDF5 Sep 2023
Building Plan Approval / NA Order for plotted developmentFile: AH - W - BASEMENT, GROUND FLOOR.PDF5 Sep 2023
Commencement Certificates / NA Order for plotted developmentFile: AH - W - COMMENCEMENT CERTIFICATE.pdf5 Sep 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: sodapdf-compressed.pdf1 Sep 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Cert Q2 2023-24_opt.pdf1 Sep 2023
Building plan approvalFile: A1 BASMENT GROUND MEZZ.PDF17 May 2023
Layout approvalFile: LAYOUT PLAN.PDF17 May 2023
Building plan approvalFile: A1 FLOOR.PDF17 May 2023
Building plan approvalFile: A1 SECTIONS.PDF17 May 2023
Building plan approvalFile: A1 TOP TERRACE SECTIONS.PDF17 May 2023
Building plan approvalFile: A2 14 RECREL TOP TERRACE FLOOR.PDF17 May 2023
Building plan approvalFile: A2 BASEMENT TO 13TH FLOOR.PDF17 May 2023
Building plan approvalFile: BASEMENT GROUND FLOOR.PDF17 May 2023
Copy of Layout Approval (in case of layout)File: LAYOUT PLAN.PDF17 May 2023
Building Plan Approval / NA Order for plotted developmentFile: A1 BASMENT GROUND MEZZ.PDF17 May 2023
Building Plan Approval / NA Order for plotted developmentFile: A1 FLOOR.PDF17 May 2023

How this compares with Pune

26%of Pune projects moved their completion datethis one has not
26%of Pune registrations have lapsed or been cancelledthis one is among them

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep AKSHAY HERITAGE on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near PUNE13,700+ in Pune

Builder: AKSHAY BUILDERS

AKSHAY BUILDERS has 3 registrations on MahaRERA, including KUBERAKSHE and AKSHAY HERITAGE. Its filings disclose 1 earlier MahaRERA project: declares 1 of 1 past projects completed on time. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What does it mean that AKSHAY HERITAGE shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if AKSHAY HERITAGE is delayed beyond 31 Dec 2024?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of AKSHAY HERITAGE?

The registered promoter entity is AKSHAY BUILDERS, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in AKSHAY HERITAGE?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against AKSHAY HERITAGE?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for AKSHAY HERITAGE?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at AKSHAY HERITAGE?

The professionals named in the filing: Architect: KHIRE BHIDE & ASSOCIATES; Engineer: ASHISH PRAKASH DAHAKE; Chartered Accountant: MUTTHA AND LAHOTI CHARTERED ACCOUNTANT. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in AKSHAY HERITAGE?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About AKSHAY HERITAGE. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save AKSHAY HERITAGE to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.