Home / Browse projects / Wardha, Maharashtra / AKSHARDHAM PHASE - 2
AKSHARDHAM PHASE - 2
RG-MH-84612 · RERA P50400078492 · Last updated on MahaRERA portal: 13 Jul 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- No red flags in this filing
Clear
- No litigation declared
- No complaints on record
- Completion date never moved
- Separate project account declared
- Allotment letter follows the model form
Nothing adverse is on this record. The buyer report still reads the filed documents themselves, and places this filing against the promoter's 1 other registration.
See what the report covers Free either way: or have every new Wardha registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
AKSHARDHAM PHASE - 2 is a Plotted project by GOVINDAM INFRA in Wardha, Maharashtra, registered with MahaRERA as P50400078492 on 17 Dec 2024. Possession is promised by 30 Jun 2028.
At a glance
Project
- NameAKSHARDHAM PHASE - 2
- TypePlotted
- Location
- FLAT NO 204
- 2ND FLOOR
- BUILDING NO 1
- CHINTAMANI APARTMENT
- NAGTHANA
- WARDHA
- NAGTHANA
- Wardha (M Cl)
- Wardha
- 442001
- Pincode442001
- RERA no.P50400078492
- ReraGenie IDRG-MH-84612
Builder
- NameGOVINDAM INFRA
- Entity typePartnership
- PartnersSUNIL VEDPRAKASH AGRAWAL, MOHAN LAXMANRAO GULHANE, GOPAL MANGILALJI PANPALIYA, SURENDRA RAMBHAU TANK, NILESH TARACHANDJI VISHWAKARMA, SHARDA ASHOKUMAR MANDHAN, SURENDRA RAMBHAU TANK HUF
- Other registrations1 more →
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on17 Dec 2024
- Promised completion30 Jun 2028
- Revised completionNone
- BuildingsNot stated in filing
- Documents filed66 files
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Progress on shared amenities15
As on 13 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 70% |
| Water Supply | No | Not applicable |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 50% |
| Storm Water Drains | No | Not applicable |
| Landscaping & Tree Planting | Yes | 30% |
| Street Lighting | Yes | 60% |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | No | Not applicable |
| Electrical meter room, sub-station, receiving station | Yes | 0% |
| Aggregate area of recreational Open Space | Yes | 0% |
| Open Parking | No | Not applicable |
Land and ownership
MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners3
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | SWAPNIL S KHEDIKAR |
| Engineer | J P ASSOCIATES |
| Chartered Accountant | S P SANGTANI & CO |
| Partner | Role in project |
|---|---|
| GOVINDAM INFRA | - |
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 2 May 2024 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 28 Dec 2023 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 28 Dec 2023 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 16 May 2024Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot due yet
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
possession is promised for 30 Jun 2028
Documents filed66
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Form 1File: Architect Certificate.pdf | 13 Jul 2026 |
| Form 2File: Engineer Certificate.pdf | 13 Jul 2026 |
| Form 3File: CA Certificate Form 3.pdf | 13 Jul 2026 |
| Disclosure of Sold and Booked InventoryFile: Disclosure of Sold and Book Inventory.pdf | 13 Jul 2026 |
| Form 1File: Architect Certificate.pdf | 31 Mar 2026 |
| Form 2File: Engineer Certificate.pdf | 31 Mar 2026 |
| Form 3File: CA certificate.pdf | 31 Mar 2026 |
| Disclosure of Sold and Booked InventoryFile: Disclosure Of Sold and Book Inventory.pdf | 31 Mar 2026 |
| Form 1File: Architect Certificate.pdf | 31 Mar 2026 |
| Form 2File: Engineer certificate.pdf | 31 Mar 2026 |
| Form 3File: CA Certificate.pdf | 31 Mar 2026 |
| Disclosure of Sold and Booked InventoryFile: Disclosure of Sold and Book Inventory.pdf | 31 Mar 2026 |
| Form 1File: Architect certificate.pdf | 31 Mar 2026 |
| Form 2File: Engineer Certificate.pdf | 31 Mar 2026 |
| Form 3File: CA Certificate.pdf | 31 Mar 2026 |
| Disclosure of Sold and Booked InventoryFile: Disclosure of Sold and Book Inventory.pdf | 31 Mar 2026 |
| Form 1File: Architects Certificate.pdf | 12 Sep 2025 |
| Form 2File: Engineer Certificate.pdf | 12 Sep 2025 |
| Form 3File: CA Certificate.pdf | 12 Sep 2025 |
| Disclosure of Sold and Booked InventoryFile: DISCLOSURE OF SOLD AND UNSOLD INVENTORY.pdf | 12 Sep 2025 |
| OthersFile: Form 2.pdf | 12 Sep 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Arc.pdf | 13 Feb 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate.pdf | 13 Feb 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Eng.pdf | 13 Feb 2025 |
| Other - TechnicalFile: 66(1)अ completion certificate.pdf | 13 Jan 2025 |
| Details of encumbrances concerned to FinanceFile: Financial Encumbrances certificate.pdf | 9 Dec 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate.pdf | 9 Dec 2024 |
| Details of encumbrances concerned to LegalFile: Financial Encumbrances certificate.pdf | 9 Dec 2024 |
| Other - TechnicalFile: Annexure A.pdf | 9 Dec 2024 |
| Details of encumbrances concerned to FinanceFile: Legal Encumbrance Certificate.pdf | 5 Nov 2024 |
| Other - LegalFile: index.pdf | 5 Nov 2024 |
| Other - LegalFile: Ann A.pdf | 5 Nov 2024 |
| Other - LegalFile: Clarification regarding survey number.pdf | 5 Nov 2024 |
| CERSAI detailsFile: No Charge On Asset.pdf | 5 Nov 2024 |
| Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Joint Operation In Bank.pdf | 5 Nov 2024 |
| Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Bank Declaration Formate A.pdf | 5 Nov 2024 |
| Details of encumbrances concerned to LegalFile: Legal Encumbrance Certificate.pdf | 5 Nov 2024 |
| Proforma of Allotment letterFile: Ann I.pdf | 25 May 2024 |
| Declaration in FORM BFile: Form B.pdf | 25 May 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Eng.pdf | 25 May 2024 |
| Declaration about Commencement CertificateFile: Declaration About Commencement Certificate.pdf | 25 May 2024 |
| Deviation Report with respect to Allotment letterFile: Deviation Of Allotment Letter.pdf | 25 May 2024 |
| Deviation Report with respect to model copy of AgreementFile: Deviation For Agreement to sale.pdf | 25 May 2024 |
| Proforma of Agreement for saleFile: Ann III.pdf | 25 May 2024 |
| Commencement Certificates / NA Order for plotted developmentFile: NA order S.pdf | 16 May 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARC (1).pdf | 14 May 2024 |
| Copy of the legal title reportFile: Search report.pdf | 2 May 2024 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: Annexure A.pdf | 2 May 2024 |
| Other - LegalFile: purchase deed (1)_compressed.pdf | 1 May 2024 |
| Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Bank Account.pdf | 1 May 2024 |
| PAN CardFile: Pan Govindam Infra.pdf | 3 Jan 2024 |
| PAN CardFile: Niraj Khatri.pdf | 3 Jan 2024 |
| PAN CardFile: Sunil Agrawal.pdf | 3 Jan 2024 |
| PAN CardFile: Mohan Gulhane.pdf | 3 Jan 2024 |
| PAN CardFile: panpaliya.pdf | 3 Jan 2024 |
| PAN CardFile: Surendra Tank.pdf | 3 Jan 2024 |
| PAN CardFile: Nilesh vishwarkarma.pdf | 3 Jan 2024 |
| PAN CardFile: Sharda Mandhan.pdf | 3 Jan 2024 |
| PAN CardFile: Surendra Tank HUF.pdf | 3 Jan 2024 |
| Other - LegalFile: rent ag.pdf | 3 Jan 2024 |
| Other - LegalFile: partnership deed.pdf | 3 Jan 2024 |
| Other - LegalFile: Credai Certificate.pdf | 3 Jan 2024 |
| Building plan approval or NA orderFile: Map.pdf | 28 Dec 2023 |
| Layout approvalFile: Map.pdf | 28 Dec 2023 |
| Copy of Layout Approval (in case of layout)File: Map.pdf | 28 Dec 2023 |
| Building Plan Approval / NA Order for plotted developmentFile: Map.pdf | 28 Dec 2023 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Wardha
Computed across the 290+ Wardha projects on ReraGenie, from their own filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- Red flags and clear checks, the possession story, sanctions and sales, land and title, who you are dealing with
- Joined against the promoter's 1 other registration, which the RERA portal never shows together
- All 66 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep AKSHARDHAM PHASE - 2 on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near NAGTHANA290+ in Wardha
Shri Ram Vatika
Krishnagiri Developers
LITTLE EARTH UNIT 11
SANJAY P. MANMODE, GANESH P. ATKAR AND MOH
Shree Sadguru Krushnagiri Nagari
Shree Samarth Infra
DATTADHAM PART 4
HARIBHAU WASUDEORAO WAZURKAR
Mahalaxmi CIty Part-2
Krushna Builders & Developers
ISHWAR NAGAR
Mahesh Batra & 2 Others
See every Wardha project, with the district possession charts
Builder: GOVINDAM INFRA
GOVINDAM INFRA has 2 registrations on MahaRERA, including AKSHARDHAM and AKSHARDHAM PHASE - 2. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Wardha district page.
Frequently asked questions
What are my rights if AKSHARDHAM PHASE - 2 is delayed beyond 30 Jun 2028?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of AKSHARDHAM PHASE - 2?
The registered promoter entity is GOVINDAM INFRA, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in AKSHARDHAM PHASE - 2?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for AKSHARDHAM PHASE - 2?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at AKSHARDHAM PHASE - 2?
The professionals named in the filing: Architect: SWAPNIL S KHEDIKAR; Engineer: J P ASSOCIATES; Chartered Accountant: S P SANGTANI & CO. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in AKSHARDHAM PHASE - 2?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback