Home / Browse projects / Thane, Maharashtra / Akshar Business Park- Phase III

Registration lapsed No litigation declared Commercial project

Akshar Business Park- Phase III

By Akshar Developers

RG-MH-27884 · RERA P51700024978 · Last updated on MahaRERA portal: 15 Apr 2025

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 39 months past the filed date
  • Completion date moved by 12 months
  • 2 extensions taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form

4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Thane registration emailed to you, free during the pilot beta.
Jul 2023Possession promised39 months past this date
66 of 66Construction stages doneacross 6 buildings; every applicable stage filed complete
0Complaints at MahaRERAon this registration
Jump to the 96 documents Report an error

Akshar Business Park- Phase III is a Commercial project by Akshar Developers in Thane, Maharashtra, registered with MahaRERA as P51700024978 on 17 Mar 2020. Possession was promised by 31 Jul 2023 and is now 39 months past that date. The completion date has moved by 12 months from the original filing.

At a glance

Project

  • NameAkshar Business Park- Phase III
  • TypeCommercial
  • Location
    • Sector-25
    • Near Turbhe Railway Station
    • Navi Mumbai (M Corp.)
    • Thane
    • 400703
  • Pincode400703
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51700024978
  • ReraGenie IDRG-MH-27884

Builder

  • NameAkshar Developers
  • Entity typePartnership
  • PartnersIsharwal Ratilal Thakkar, Shailesh Bachubhai Arethiya
  • Other registrations4 more →
  • Completed2 of 5
  • No longer live2 lapsed, de-registered or revoked
  • Declared earlier projects1 →

Key dates

39 months past promisethis monthRegisteredMar 2020First promiseJul 2022Revised toJul 2023

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on17 Mar 2020
  • Promised completion31 Jul 2023
  • Revised completionRevised to 31 Jul 2023 (originally 31 Jul 2022)
  • Buildings6 building records
  • Documents filed96 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Wing W- Block DNA50000
Wing X- Block DNA50000
Wing Y- Block DNA50000
Wing Z- Block DNA50000
Wing Z1- Block DNA50000
Wing Z2- Block DNA50000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building6

As on 15 Apr 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

66 of 66 construction stages are filed complete across 6 buildings.

Wing W- Block D100%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Wing X- Block D100%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Wing Y- Block D100%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Wing Z- Block D100%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Wing Z1- Block D100%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Wing Z2- Block D100%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 15 Apr 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes100%
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes100%
Street LightingYes100%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes100%
Energy managemcntYes100%
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceYes100%
Open ParkingYes100%

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area9,255 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Sanctioning authorityNavi Mumbai Municipal Corporation
Permissible FSI7506.05
Proposed, not sanctioned7,506 sq m
Buildings approved6
Buildings sanctioned6

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchCoral Crest, Plot No 3, Sector 23, Near Nerul Station, Navi Mumbai, 400706

Certifying professionals and partners

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

PartnerRole in project
Akshar Developers-

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51700013989Jul 2022 → Jul 2023

Reason as filed by the promoterDue to the current COVID 19 pandemic situation we are unable to complete the Project in all respects by 31.01.2023 as mentioned in RERA. We, thus, request you to kindly take the above on record and grant us extension till 31/07/2023 and oblige.

EXT51700012381Jul 2022 → Jan 2023

Reason as filed by the promoterWe would like to apply for Time Extension of the Project Akshar Business Park-Phase III. Due to the current COVID 19 pandemic situation we are unable to complete the Project in all respects by 31.07.2022 as mentioned in RERA. We, thus, request you to kindly take the above on record and grant us extension till 31.01.2023 and oblige.

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 29 Jan 2020
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 12 Mar 2020
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 12 Mar 2020
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 29 Jan 2020Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 27 Mar 2025

Documents filed96

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 96 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - ABP III as on Sep 2024.pdf15 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - ABP III as on Dec 2024.pdf15 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 of Akshar Business Park- Phase III as on 30th June 2024.pdf15 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - ABP III as on June 2024.pdf15 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - ABP III as on Sep 2024.pdf29 Mar 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - ABP III as on Dec 2024.pdf29 Mar 2025
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: ilovepdf_merged (51).pdf27 Mar 2025
Architect’s Certificate on Completion of Project (Form 4)File: Form 4 Dimensions ABP Akshar Developers.pdf5 Dec 2024
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: 1 Occupancy Certificate_ Completion Certificate_ Architect's certificate of completion for5 Dec 2024
Architect’s Certificate on Completion of Project (Form 4)File: organized (51).pdf30 Nov 2024
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: oc 2.pdf28 Nov 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 Akshar Business Park Phase III FY 2023-24.pdf25 Nov 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - ABP III as on Dec 2023.pdf15 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - ABP III as on March 2024.pdf15 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - ABP III as on June 2024.pdf15 Oct 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 of Akshar Business Park- Phase III as on 31st Dec 2023 (1).pdf11 Oct 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 of Akshar Business Park- Phase III as on 31st March 2024.pdf11 Oct 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 of Akshar Business Park- Phase III as on 30th June 2024.pdf11 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 2 Architect’s Certificate of Percentage of Completion of Work (Form 1).pdf20 Jul 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 17 Engineer’s Certificate on Cost Incurred on Project (Form 2).pdf20 Jul 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 17 CA Certificate on Project Cost Fund withdrawal (Form 3).pdf20 Jul 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - ABP III as on June 2020.pdf18 Jun 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - ABP III as on Sept 2020.pdf18 Jun 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - ABP III as on Dec 2020.pdf18 Jun 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - ABP III as on March 2021.pdf18 Jun 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - ABP III as on June 2021.pdf18 Jun 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - ABP III as on Sept 2021.pdf18 Jun 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - ABP III as on Dec 2021.pdf18 Jun 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - ABP III as on March 2022.pdf18 Jun 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - ABP III as on Sept 2022.pdf18 Jun 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - ABP III as on Dec 2022.pdf18 Jun 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - ABP III as on March 2023.pdf18 Jun 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - ABP III as on June 2023.pdf18 Jun 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - ABP III as on Sept 2023.pdf18 Jun 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - ABP as on 31-03-2020.pdf18 Jun 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - ABP as on 30-06-2020.pdf18 Jun 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - ABP as on 30-09-2020.pdf18 Jun 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - ABP as on 31-12-2020.pdf18 Jun 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - ABP as on 30-06-2021.pdf18 Jun 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - ABP as on 30-09-2021.pdf18 Jun 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - ABP as on 31-12-2021.pdf18 Jun 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - ABP as on 31-03-2022.pdf18 Jun 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - ABP as on 31-09-2022.pdf18 Jun 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - ABP as on 31-12-2022.pdf18 Jun 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - ABP as on 31-03-2023.pdf18 Jun 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - ABP as on 31-06-2023.pdf18 Jun 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - ABP as on 30-09-2023.pdf18 Jun 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Form 5 for FY 2019-20.pdf18 Jun 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5-Akshar Business Park Phase III_FY 2022-23.pdf18 Jun 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - ABP III as on June 2020.pdf15 Jun 2024
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: PHASE 3 akshar turbhe part OC.pdf5 Sep 2023
Declaration about Commencement CertificateFile: DECLARATION FOR COMMENCEMET CERTIFICATE 02-02-2023.pdf14 Feb 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: ENGINEER QUALITY ASSURANCE CERTIFICATE 02-02-2023.pdf14 Feb 2023
CERSAI detailsFile: CERSAI DETAILS.pdf14 Feb 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: form 5 march 22.pdf3 Feb 2023
Proforma of Agreement for saleFile: AGREEMENT- PHASE III 11-10-2022.pdf5 Dec 2022
Details of encumbrancesFile: ENCUMBRANCES CERTIFICATE.pdf11 Oct 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGINEER CERTIFICATE AKSHAR BUSINESS PARK PHASE III-31-03-2020.pdf5 Aug 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: RERA -DECORIUM PHASE 3.pdf5 Aug 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: form 5.pdf5 Aug 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: form 3_compressed.pdf4 Aug 2022
Declaration about Commencement CertificateFile: DECLARATION FOR COMMENCEMET CERTIFICATE 01-08-2022.pdf3 Aug 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: ENGINEER QUALITY ASSURANCE CERTIFICATE 01-08-2022.pdf3 Aug 2022
CERSAI detailsFile: CERSAI DETAILS.pdf3 Aug 2022
Disclosure of sold/ booked inventoryFile: ABP PHASE III SOLD-BOOKED LETTER.pdf3 Aug 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architech certificate.pdf2 Aug 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engg Certificate.pdf2 Aug 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: form 3 with annexure.pdf2 Aug 2022
Building plan approvalFile: 1 CC (1).pdf12 Mar 2020
Building plan approvalFile: 2 CC.pdf12 Mar 2020
Building plan approvalFile: 3 CC.pdf12 Mar 2020
Building plan approvalFile: 4 CC.pdf12 Mar 2020
Building plan approvalFile: 5 CC.pdf12 Mar 2020
Building plan approvalFile: 6 CC.pdf12 Mar 2020
Layout approvalFile: Layout- ABP III.pdf12 Mar 2020
Details of encumbrancesFile: Encumbrance Cerificate.pdf12 Mar 2020
Copy of Layout Approval (in case of layout)File: Layout- ABP III.pdf12 Mar 2020
Building Plan Approval / NA Order for plotted developmentFile: 1 CC (1).pdf12 Mar 2020
Building Plan Approval / NA Order for plotted developmentFile: 2 CC.pdf12 Mar 2020
Building Plan Approval / NA Order for plotted developmentFile: 3 CC.pdf12 Mar 2020

How this compares with Thane

24%of Thane projects moved their completion datethis one moved by 12 months
23%of Thane registrations have lapsed or been cancelledthis one is among them

Computed across the 7,600+ Thane projects on ReraGenie, from their own filings.

Free monthly report: Thane on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Akshar Business Park- Phase III on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Near Turbhe Railway Station7,600+ in Thane

2 kmAkshar Business Park- PhCompleted 16Lapsed / revoked 5Other 36Dot size: filed unitsN

Filed coordinates, straight-line distance. 57 registered projects within 2 km.

Builder: Akshar Developers

Akshar Developers has 5 registrations on MahaRERA, including Nirmal Arcade and Akshar Business Park- Phase I. Its filings disclose 1 earlier MahaRERA project: declares 1 of 1 past projects completed on time. Read the full track record. See more projects on the Thane district page.

Frequently asked questions

What does it mean that Akshar Business Park- Phase III shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if Akshar Business Park- Phase III is delayed beyond 31 Jul 2023?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Akshar Business Park- Phase III?

The registered promoter entity is Akshar Developers, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Akshar Business Park- Phase III?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Akshar Business Park- Phase III?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

What should I check before booking in Akshar Business Park- Phase III?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Akshar Business Park- Phase III. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Akshar Business Park- Phase III to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.