Home / Browse projects / Pune, Maharashtra / AKSHA AMULYAM
AKSHA AMULYAM
RG-MH-24729 · RERA P52100010533 · Last updated on MahaRERA portal: 28 Apr 2023
Source: official MahaRERA filing
Red flags
- Completion date moved by 22 months
- 3 extensions taken
Clear
- No litigation declared
- No complaints on record
- Separate project account declared
- Allotment letter follows the model form
- Recorded completed on MahaRERA
2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
AKSHA AMULYAM is a Residential / Group Housing project by Concord Properties in Pune, Maharashtra, registered with MahaRERA as P52100010533 on 31 Aug 2017. The registration is recorded completed; possession was promised by 26 Feb 2022. The completion date has moved by 22 months from the original filing.
At a glance
Project
- NameAKSHA AMULYAM
- TypeResidential / Group Housing
- Location
- Pimpri Chinchawad (M Corp.)
- Haveli
- Pune
- 412105
- Pincode412105
- MapView location on Google Maps (as filed on RERA)
- RERA no.P52100010533
- ReraGenie IDRG-MH-24729
Builder
- NameConcord Properties
- Entity typePartnership
- PartnersSatishkumar Ravjibhai Patel, Babulal Punaram Choudhary, Fatima Abdul Rehman Chaudhary, Imran Abdul Rehman Chaudhary, Mahendra Suresh Thakur, Bharat Lalaram Choudhary
- Other registrations2 more →
- Completed1 of 3
- No longer live1 lapsed, de-registered or revoked
Key dates
Key facts
Registration and timeline
- StatusCompleted
- Registered on31 Aug 2017
- Promised completion26 Feb 2022
- Revised completionRevised to 26 Feb 2022 (originally 29 Apr 2020)
- Buildings4 building records
- Documents filed36 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| D BUILDING | NA | 14 | 0 | 0 | 0 | 0 |
| E BUILDING | NA | 14 | 0 | 0 | 0 | 0 |
| F BUILDING | NA | 13 | 0 | 0 | 0 | 0 |
| G BUILDING | NA | 2 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building4
As on 28 Apr 2023, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
35 of 44 construction stages are filed complete across 4 buildings. The stage furthest along is Installation of Lifts, at 95%.
D BUILDING90%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 95% |
E BUILDING90%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 95% |
F BUILDING90%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 95% |
G BUILDING81%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 95% |
Progress on shared amenities15
As on 28 Apr 2023, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 10% |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 0% |
| Storm Water Drains | Yes | 0% |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | Yes | 0% |
| Community Buildings | Yes | 0% |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 0% |
| Solid Waste Management And Disposal | Yes | 0% |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | Yes | 0% |
| Fire protection and fire safety requirements | Yes | 0% |
| Electrical meter room, sub-station, receiving station | Yes | 0% |
| Aggregate area of recreational Open Space | Yes | 0% |
| Open Parking | Yes | 0% |
Parking filed34
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Closed/Covered | Total |
|---|---|---|
| D BUILDING | 1 | 1 |
| E BUILDING | 1 | 1 |
| F BUILDING | 32 | 32 |
Land and ownership1
MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
| Landowner | Village | District |
|---|---|---|
| PRAVIN MUBHAJI VAHILE | Pimpri Chinchawad (M Corp.) | Pune |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners2
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Mahendra Thakur & Associates |
| Engineer | RamRandive |
| Partner | Role in project |
|---|---|
| Concord Properties | - |
Extensions applied for3
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterCompletion certificate is in process
Reason as filed by the promoterWrongly estimated date of completion. Our work is almost 80% completed. We predict that the reasonable extension would suffice our purpose to get project completed. The date of completion is taking more time due to labour and material issue. As industry is facing tremendous problem and we too are part and parcel who are affected by it. But we have completed most of the work.
Reason as filed by the promoterThe project has been completed up to 100%. Also we have applied for Completion certificate but not yet received. Due to Covid19 situation we couldn't get the completion certificate in given period of time. Hence request to allow the extension.
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 2 Aug 2017 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 2 Aug 2017 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 2 Aug 2017 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 2 Aug 2017Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateOn the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
uploaded 10 Jan 2022
Documents filed36
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Architect’s Certificate on Completion of Project (Form 4)File: img20230428_12353017.pdf | 28 Apr 2023 |
| Certificates of CA (Form 3)File: FORM 3 CA.pdf | 23 Feb 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: aksha amulyam 2A.pdf | 6 Feb 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Form 2A_compressed.pdf | 7 Sep 2022 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2A_compressed.pdf | 7 Sep 2022 |
| Disclosure of sold/ booked inventoryFile: AMULYAM D WING SOLD-BOOKED INVENTORY_compressed.pdf | 22 Aug 2022 |
| Disclosure of sold/ booked inventoryFile: AMULYAM E WING SOLD-BOOKED INVENTORY_compressed.pdf | 22 Aug 2022 |
| Disclosure of sold/ booked inventoryFile: AMULYAM F WING SOLD-BOOKED INVENTORY.pdf | 22 Aug 2022 |
| Disclosure of sold/ booked inventoryFile: AMULYAM G WING SOLD-BOOKED INVENTORY.pdf | 22 Aug 2022 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: AMULYAM II COMPLITION CERTIFICATE_compressed.pdf | 10 Jan 2022 |
| Status of Formation of Legal Entity (Society/Co Op etc.)File: AMULYAM P2 SOCIETY CERTIFICATE.pdf | 10 Jan 2022 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form 5 scanned.pdf | 21 Oct 2021 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Form 5 scanned.pdf | 28 Feb 2021 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Form 5 - Concorde 18-19.pdf | 25 Dec 2019 |
| Certificates of CA (Form 5)File: FORM 5.pdf | 30 Sep 2018 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1.pdf | 21 Feb 2018 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2.pdf | 21 Feb 2018 |
| Certificates of CA (Form 3)File: FORM 3.pdf | 21 Feb 2018 |
| Certificates of CA (Form 3)File: FORM 3 CONCORD.pdf | 3 Aug 2017 |
| Building plan approvalFile: PLAN-ilovepdf-compressed.pdf | 2 Aug 2017 |
| Layout approvalFile: PLAN-ilovepdf-compressed.pdf | 2 Aug 2017 |
| PAN CardFile: PAN-ilovepdf-compressed.pdf | 2 Aug 2017 |
| Copy of the legal title reportFile: CCI07072017.pdf | 2 Aug 2017 |
| Copy of the legal title reportFile: CCI07072017_0001.pdf | 2 Aug 2017 |
| Details of encumbrancesFile: anc.pdf | 2 Aug 2017 |
| Copy of Layout Approval (in case of layout)File: PLAN-ilovepdf-compressed.pdf | 2 Aug 2017 |
| Building Plan Approval (IOD)File: PLAN-ilovepdf-compressed.pdf | 2 Aug 2017 |
| Commencement Certificates / NA Order for plotted developmentFile: CCI07072017_0002.pdf | 2 Aug 2017 |
| Commencement Certificates / NA Order for plotted developmentFile: CCI07072017_0003.pdf | 2 Aug 2017 |
| Declaration in FORM BFile: form B.pdf | 2 Aug 2017 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1.pdf | 2 Aug 2017 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: AMULYAM PROPERTIES-ilovepdf-compressed.pdf | 2 Aug 2017 |
| Proforma of Allotment letterFile: ATS 1 10.pdf | 2 Aug 2017 |
| Proforma of Allotment letterFile: ATS 11 20.pdf | 2 Aug 2017 |
| Proforma of Allotment letterFile: ATS 21 24.pdf | 2 Aug 2017 |
| Proforma of Allotment letterFile: Allotement Letter.pdf | 2 Aug 2017 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Pune
Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.
Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Useful on a completed registration when you are buying resale, or checking what was promised against what was delivered.
- 2 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 2 other registrations and every project registered within 2 km, which the RERA portal never shows together
- All 36 filed documents as one ZIP, foldered, with a manifest
Keep AKSHA AMULYAM on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Pimpri Chinchawad (M Corp.)13,700+ in Pune
Filed coordinates, straight-line distance. 20 registered projects within 2 km.
TANISH PARK
TANISH DEVELOPERS
Ajinkya Towers
APAK Bussiness Innovation Pvt Ltd
SILVER GARDENIA
SILVER PROMOTERS AND DEVELOPERS
Mangalam Life Park
Mangalam Buildcorp
SingaPune Ph 3
Xrbia Mirth Properties LLP
SingaPune Ph 2
Xrbia Mirth Properties LLP
Builder: Concord Properties
Concord Properties has 3 registrations on MahaRERA, including AKSHA AMULYAM and AKSHA AMBAR. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.
Frequently asked questions
What are my rights if AKSHA AMULYAM is delayed beyond 26 Feb 2022?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of AKSHA AMULYAM?
The registered promoter entity is Concord Properties, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in AKSHA AMULYAM?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for AKSHA AMULYAM?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at AKSHA AMULYAM?
The professionals named in the filing: Architect: Mahendra Thakur & Associates; Engineer: RamRandive. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in AKSHA AMULYAM?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback