Home / Browse projects / Bengaluru Urban, Karnataka / After The Rain Phase III

Registration approved Litigation declared Residential/Group Housing project

After The Rain Phase III

By TOTAL ENVIRONMENT BUILDING SYSTEMS PVT LTD

RG-KA-07183 · RERA PRM/KA/RERA/1251/309/PR/160825/008002 · Last updated on RERA Karnataka portal: 15 Oct 2026

Source: official RERA Karnataka filing

Red flags

  • Litigation declared, 2 cases

Clear

  • No complaints on record
  • Completion date never moved
  • Separate project account declared
Apr 2032Possession promisedno revision filed
0 of 16Construction stages donefurthest along: Earth work and other leveling..., 17%
7 of 36Units unsoldnot recorded sold or booked
0Complaints at RERA Karnatakaon this registration
Jump to the 189 documents Report an error

After The Rain Phase III is a Residential/Group Housing project by TOTAL ENVIRONMENT BUILDING SYSTEMS PVT LTD in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/309/PR/160825/008002 on 16 Aug 2025. Possession is promised by 30 Apr 2032. 29 of the 36 units on this registration are recorded sold or booked, and 0 of 16 construction stages are filed complete.

At a glance

Project

  • NameAfter The Rain Phase III
  • TypeResidential/Group Housing
  • Location
    • Bengaluru North
    • Bengaluru Urban
    • 562157
  • Pincode562157
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PRM/KA/RERA/1251/309/PR/160825/008002
  • ReraGenie IDRG-KA-07183

Builder

  • NameTOTAL ENVIRONMENT BUILDING SYSTEMS PVT LTD
  • Entity typeCompany
  • CINU45202KA1996PTC020790
  • GSTIN29AABCT9452F1Z2
  • Authorized SignatorySuresh Chandra Bandari
  • CeoKamal Sagar
  • DirectorsKamal Sagar, Shibanee Sagar
  • Project HeadKarthick Dhanasekaran
  • Other registrations4 more →
  • Declared earlier projects3 →

Key dates

this monthRegisteredAug 2025PromisedApr 2032

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on16 Aug 2025
  • Promised completion30 Apr 2032
  • Revised completionNone
  • Buildings1 building record
  • Documents filed189 files

Current status

81%29 of 36 units booked
10.7%Of the estimated cost spent so far

Figures as on 15 Oct 2026, this project's latest RERA Karnataka filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Tower---36036

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 15 Oct 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

0 of 16 construction stages are filed complete. The stage furthest along is Earth work and other leveling preparation work, at 17%.

Building: 1% average across the applicable activities

ActivityProgress
Earth work and other leveling preparation work17%
Foundation footing work1%
Upto Plinth Level0%
Sub-structure flooring (Parking Floor, more than one floor below general ground level)0%
Retaining wall (All types)Not applicable
RCC or MS Framed structure0%
Masonry Construction0%
Plastering inside , outside & Ceiling0%
Joinery: Doors, Windows, Ventilators etc0%
Basic work of Water supply, Sanitary and Electrification0%
Dadoing, Skirting, Flooring, Tiles work (All types)0%
Railing and Grill fixing0%
Electrification, Water supply and Sanitary Finishing0%
Painting0%
Fire prevention and fire fighting fitting and fixture with networkNot applicable
Weather Proof work(tile,concrete)0%
Wardrobe, Showcase, Kitchen cabinet, Puja work0%
Elevation workNot applicable
Internal and External work including landscapes as per sanctioned drawings0%

Progress on shared amenities40

As on 15 Oct 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes0%
Sewage and Drainage SystemYes0%
Water conservation/rain water harvesting/recharge of ground waterNoNot applicable
Energy managementNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Solid waste management and disposalNoNot applicable
Emergency Evacuation servicesNoNot applicable
Internal Roads & FootpathsYes0%
Electricity supply transformer and substationYes0%
Storm water drainsYes0%
Use of renewable energyYes0%
Sewage Treatment Plant (STP)Yes0%
Parks & Tree plantingYes0%
Street LightingYes0%
ElectricityYes0%
Smart Home AutomationNoNot applicable
CCTV SurveillanceNoNot applicable
Club HouseYes74%
Community HallNoNot applicable
Outdoor Sports facilityNoNot applicable
Indoor Sports facilityNoNot applicable
Swimming PoolNoNot applicable
GymNoNot applicable
ParksYes0%
Power BackupNoNot applicable
Piped GasNoNot applicable
Water and SanitationNoNot applicable
Air ConditioningNoNot applicable
StaircasesYes0%
LiftsNoNot applicable
Corridor/LobbiesNoNot applicable
Fire escapesNoNot applicable
Common entrance and exit for the building/common portico/foyer/verandahNoNot applicable
BasementNoNot applicable
TerraceNoNot applicable
Outer WallNoNot applicable
Open parking areasYes0%
Provision for lodging of management staff and security staffNoNot applicable
Water conservation and renewable energyNoNot applicable
Common storage spacesNoNot applicable

Land and ownership9

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area31,312 sq m
Named landowners9
LandownerVillageDistrict
Total Environment Building Systems Private Limited--
Total Environment Building Systems Private Limited--
Total Environment Building Systems Private Limited--
Total Environment Building Systems Private Limited--
Total Environment Building Systems Private Limited--
Total Environment Building Systems Private Limited--
Total Environment Building Systems Private Limited--
Total Environment Building Systems Private Limited--
Sankriti Singh--

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 179.04 cr
Cost incurredRs 19.15 cr
Spent of the estimate10.7%
Cost lineEstimatedIncurred
Estimated Cost of Construction as certified by EngineerRs 90.16 crRs 42.52 lakh
Principal sum and interest payable to financial institutions-Non Banking financial institution (NBFC)Rs 50.00 crRs 18.73 cr
Sales and MarketingRs 19.22 cr-
Property ManagementRs 8.74 cr-
On-site expenditure-Consultants FeesRs 6.38 cr-
Payment of taxesRs 3.49 cr-
UtilitiesRs 1.05 cr-

Certifying professionals and partners3

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectVarun Biltoria
EngineerVishnu Kumar
Chartered AccountantAnkush Jain

Litigation declared2

CaseCourtStatus
WP Nos, 23101/2022, 23102/2022, 23103/2022, 23020/2022, 23097/2022, 23059/2022, 23037/2022, 23106/2022 22858/2022, 23811/2022, 23826/2022,High Court of Karnataka-
WP 15729/2024/2024High Court of Karnataka-

Complaints filed with RERA Karnataka

No complaints on record against this registration.

Documents filed189

As listed on the registration, under the names the promoter filed them with; the newest 80 of 189 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/309/PR/160825/008002 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Q2 2026-27 Form-4 Certificate issued by Chartered AccountantFile: FORM-4 AFTER THE RAIN PHASE III Q2 26-27.pdf15 Oct 2026
Q2 2026-27 Form-5 Certificate issued by ArchitectFile: FORM-5 AFTER THE RAIN PHASE III Q2 26-27.pdf15 Oct 2026
Q2 2026-27 Form-6 Certificate issued by Structural EngineerFile: FORM-6 AFTER THE RAIN PHASE III Q2 26-27.pdf15 Oct 2026
Q2 2026-27 Water supply and sewage board15 Oct 2026
Q2 2026-27 KSPCB- PCB (10 Acres to 125 Acres)15 Oct 2026
Q2 2026-27 KSPCB- MOEF (Above 50 Acres)15 Oct 2026
Q2 2026-27 KPTCL- BESCOM15 Oct 2026
Q1 2026-27 Form-4 Certificate issued by Chartered AccountantFile: Form-4 ATR III Q1 26-27.pdf15 Jul 2026
Q1 2026-27 Form-5 Certificate issued by ArchitectFile: Form-5 ATR III Q1 26-27.PDF15 Jul 2026
Q1 2026-27 Form-6 Certificate issued by Structural EngineerFile: Form-6 ATR III Q1 26-27.pdf15 Jul 2026
Q1 2026-27 Water supply and sewage board15 Jul 2026
Q1 2026-27 KSPCB- PCB (10 Acres to 125 Acres)15 Jul 2026
Q1 2026-27 KSPCB- MOEF (Above 50 Acres)15 Jul 2026
Q1 2026-27 KPTCL- BESCOM15 Jul 2026
Q4 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Form-4 Q4 25-26 ATR Phase 3.pdf15 Apr 2026
Q4 2025-26 Form-5 Certificate issued by ArchitectFile: Form-5 Q4 25-26 AtR Ph-3.PDF15 Apr 2026
Q4 2025-26 Form-6 Certificate issued by Structural EngineerFile: FORM-6 AFTER THE RAIN PHASE III 31-03-2026 (1).pdf15 Apr 2026
Q3 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Form-4 Q3-25-26.pdf27 Jan 2026
Q3 2025-26 Form-5 Certificate issued by ArchitectFile: Form-5_Architect_Certificate_ Ph-III_Q3_25-26 (1).pdf27 Jan 2026
Q3 2025-26 Form-6 Certificate issued by Structural EngineerFile: Form-6 After The Rain - Phase III 31-12-2025.pdf27 Jan 2026
Declaration Affidavit with BESCOM NOC'sFile: Declaration Affidavit with BESCOM NOC's.pdf16 Aug 2025
Approved Building Plan Block 31-36File: 1 Approved Building Plan Block 31-36.pdf12 Aug 2025
ATR Building License Phase 3 Block wise B31-B36File: 2 ATR Building License Phase 3 Block wise B31-B36.pdf12 Aug 2025
ATR Phase III SEIAA NOC declaration and Fee paid receiptFile: 3 ATR Phase III SEIAA NOC declaration and Fee paid receipt.pdf12 Aug 2025
ATR Phase 3 KSPCB declarationFile: 4 ATR Phase 3 KSPCB declaration.pdf12 Aug 2025
Clarification on Clubhouse of the projectFile: 5 Clarification on Clubhouse of the project.PDF12 Aug 2025
Proforma Agreement for Sale ATR Phase III V3File: 6 Proforma Agreement for Sale ATR Phase III V3.pdf12 Aug 2025
Clarification on BESCOM NOC with supporting docsFile: 7 Clarification on BESCOM NOC with supporting docs.pdf12 Aug 2025
All ECs till DateFile: 1 All ECs till Date.pdf3 Jun 2025
Kharab Land AffidavitFile: 2 Kharab Land Affidavit.pdf3 Jun 2025
Block 23 sheet 25 of 40File: 1 Block 23 sheet 25 of 40.pdf3 Jun 2025
Block 26 sheet 26 of 40File: 2 Block 26 sheet 26 of 40.pdf3 Jun 2025
Block 26 sheet 37 of 40File: 3 Block 26 sheet 37 of 40.pdf3 Jun 2025
Block 31 sheet 32 of 40File: 4 Block 31 sheet 32 of 40.pdf3 Jun 2025
Block 31 sheet 33 of 40File: 5 Block 31 sheet 33 of 40.pdf3 Jun 2025
Block 32 sheet 34 of 40File: 6 Block 32 sheet 34 of 40.pdf3 Jun 2025
Block 33 sheet 35 of 40File: 7 Block 33 sheet 35 of 40.pdf3 Jun 2025
Block 34 sheet 36 of 40File: 8 Block 34 sheet 36 of 40.pdf3 Jun 2025
Block 34 sheet 37 of 40File: 9 Block 34 sheet 37 of 40.pdf3 Jun 2025
Block 35 sheet 38 of 40File: 10 Block 35 sheet 38 of 40.pdf3 Jun 2025
Block 36 sheet 39 of 40File: 11 Block 36 sheet 39 of 40.pdf3 Jun 2025
Block 36 sheet 40 of 40File: 12 Block 36 sheet 40 of 40.pdf3 Jun 2025
SEIAA NOC fee paid receipt and declaration affidavitFile: 14 SEIAA NOC fee paid receipt and declaration affidavit.pdf3 Jun 2025
KSPCB NOC affidavitFile: 13 KSPCB NOC affidavit.pdf3 Jun 2025
Project Plan Demarcation DetailsFile: 15 Project Plan Demarcation Details.PDF3 Jun 2025
ATR BP5 Site PlanFile: 16 ATR BP site Plan 2025.pdf3 Jun 2025
RDPR OC Circular 05-08-2024 ( to obtain sanction from Panchyath)File: 17 RDPR OC Circular 05-08-2024 ( to obtain sanction from Panchyath).pdf3 Jun 2025
Common Area and Amenities detailsFile: 1 Common Area and Amenities details.pdf3 Jun 2025
BBMP Engineer's Licence attestedFile: 2 BBMP Engineer's Licence attested.pdf3 Jun 2025
Proforma Allotment Letter After the Rain Phase IIIFile: 3 Proforma Allotment Letter After the Rain Phase III.pdf3 Jun 2025
BESCOM Power Enhancement approvalFile: 4 BESCOM Power Enhancement approval.pdf3 Jun 2025
5 Water NOC3 Jun 2025
Agreement for Sale ATR Phase III - RERA UpdatedFile: 6 Agreement for Sale ATR Phase III - RERA Updated.pdf3 Jun 2025
RTC, survey 354/1B-
Mutation, survey 354/1B-
Encumbrance Certificate, survey 354/1B-
Conversion/Alienation Order, survey 354/1B-
Sale/Title/Gift Deed, survey 354/1B-
Khatha, survey 354/1B-
RTC, survey 354/2-
Mutation, survey 354/2-
Encumbrance Certificate, survey 354/2-
Conversion/Alienation Order, survey 354/2-
Sale/Title/Gift Deed, survey 354/2-
Khatha, survey 354/2-
RTC, survey 231/3-
Mutation, survey 231/3-
Encumbrance Certificate, survey 231/3-
Conversion/Alienation Order, survey 231/3-
Sale/Title/Gift Deed, survey 231/3-
Khatha, survey 231/3-
RTC, survey 244/1-
Mutation, survey 244/1-
Encumbrance Certificate, survey 244/1-
Conversion/Alienation Order, survey 244/1-
Sale/Title/Gift Deed, survey 244/1-
Khatha, survey 244/1-
RTC, survey 244/2-
Mutation, survey 244/2-
Encumbrance Certificate, survey 244/2-

How this compares with Bengaluru Urban

81%of this project is bookeddistrict median 51%
34%of Bengaluru Urban projects moved their completion datethis one has not
1%of Bengaluru Urban registrations are shown as withdrawn or revokedthis one is not

Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.

Keep After The Rain Phase III on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bengaluru Urban4,100+ in Bengaluru Urban

2 kmAfter The Rain Phase IIIOther 9Dot size: filed unitsN

Filed coordinates, straight-line distance. 9 registered projects within 2 km.

Builder: TOTAL ENVIRONMENT BUILDING SYSTEMS PVT LTD

TOTAL ENVIRONMENT BUILDING SYSTEMS PVT LTD has 5 registrations on RERA Karnataka, including After The Rain Phase III and After the Rain- Phase 1. Its filings declare 3 earlier projects, none of them declared completed. Litigation is declared on 3 of its registrations. Read the full track record. See more projects on the Bengaluru Urban district page.

Frequently asked questions

What are my rights if After The Rain Phase III is delayed beyond 30 Apr 2032?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of After The Rain Phase III?

The registered promoter entity is TOTAL ENVIRONMENT BUILDING SYSTEMS PVT LTD, a company as per the filing. Its CIN U45202KA1996PTC020790 and GSTIN 29AABCT9452F1Z2 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in After The Rain Phase III?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at After The Rain Phase III?

The professionals named in the filing: Architect: Varun Biltoria; Engineer: Vishnu Kumar; Chartered Accountant: Ankush Jain. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in After The Rain Phase III?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; how the declared litigation on this registration affects your risk; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About After The Rain Phase III. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save After The Rain Phase III to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.