Home / Browse projects / Bengaluru Urban, Karnataka / AFTER THE RAIN-PHASE IIB

Registration approved Litigation declared Residential/Group Housing project

AFTER THE RAIN-PHASE IIB

By Total Environment Building Systems Private Limited

RG-KA-93382 · RERA PRM/KA/RERA/1251/309/PR/191015/002923 · Last updated on RERA Karnataka portal: 15 Oct 2026

Source: official RERA Karnataka filing

Red flags

  • Litigation declared, 2 cases
  • 1 complaint at RERA Karnataka
  • Completion date moved by 21 months
  • 2 extensions taken

Clear

  • Separate project account declared
Aug 2026Possession promisedmoved 21 months from the original
4 of 19Construction stages donefurthest along: Masonry construction: Bricks, 70%
1 of 37Units unsoldnot recorded sold or booked
1Complaints at RERA Karnatakaon this registration
Jump to the 76 documents Report an error

AFTER THE RAIN-PHASE IIB is a Residential/Group Housing project by Total Environment Building Systems Private Limited in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/309/PR/191015/002923 on 15 Oct 2019. Possession is promised by 1 Aug 2026. The completion date has moved by 21 months from the original filing. 36 of the 37 units on this registration are recorded sold or booked, and 4 of 19 construction stages are filed complete. 1 complaint is on record with the regulator.

At a glance

Project

  • NameAFTER THE RAIN-PHASE IIB
  • TypeResidential/Group Housing
  • Location
    • Bengaluru North
    • Bengaluru Urban
  • PincodeNot stated
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PRM/KA/RERA/1251/309/PR/191015/002923
  • ReraGenie IDRG-KA-93382

Builder

  • NameTotal Environment Building Systems Private Limited
  • Entity typeCompany
  • CINU45202KA1996PTC020790
  • Authorized SignatorySuresh chandra Bhandari
  • DirectorsMrs. Shibanee Sagar, Mr. Kamal Sagar
  • Other registrations4 more →
  • Declared earlier projects3 →

Key dates

this monthRegisteredOct 2019First promiseNov 2024Revised toAug 2026

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on15 Oct 2019
  • Promised completion1 Aug 2026
  • Revised completionRevised to 1 Aug 2026 (originally 1 Nov 2024)
  • Buildings5 building records
  • Documents filed76 files

Current status

97%36 of 37 units booked
142.8%Of the estimated cost spent so far

Figures as on 15 Oct 2026, this project's latest RERA Karnataka filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
BLOCK 23---505
BLOCK 24---808
BLOCK 25---808
BLOCK 26---606
BLOCK 27---10010

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 15 Oct 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

4 of 19 construction stages are filed complete. The stage furthest along is Masonry construction: Bricks, at 70%.

Building: 31% average across the applicable activities

ActivityProgress
Earth work and other leveling preparation work100%
Foundation footing work100%
Retaining wall (All types)0%
Plinth level Beam100%
Sub-structure flooring (Parking Floor, more than one floor below general ground level)0%
RCC or MS Framed structure100%
Masonry construction: Bricks, Concrete blocks etc70%
Plastering inside , outside & Ceiling24%
Joinery: Doors, Windows, Ventilators etc11%
Basic work of Water supply, Sanitary and Electrification5%
Dadoing, Skirting, Flooring, Tiles work (All types)16%
Railing and Grill fixing11%
Electrification, Water supply and Sanitary Finishing5%
Wardrobe, Showcase, Kitchen cabinet, Puja work5%
Fire prevention and fire fighting fitting and fixture with network0%
Weather Proof work(tile,concrete)16%
Painting11%
Elevation work11%
Internal and External work including landscapes as per santioned drawings0%

Progress on shared amenities42

As on 15 Oct 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes70%
Internal Roads & FootpathsYes60%
Sewage and Drainage SystemYes55%
Parks & Tree plantingYes0%
Street LightingYes0%
Provision for community buildings and for treatment and disposal of sewage and sullage waterNoNot applicable
Solid waste management and disposalYes55%
Water conservationNoNot applicable
Energy managementNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Education/Health/Other public amenitiesNoNot applicable
Electricity supply transformer and substationYes0%
Emergency Evacuation servicesNoNot applicable
Storm water drainsYes80%
Use of renewable energyYes0%
Water conservation/rain water harvesting/recharge of ground waterYes0%
ElectricityYes11%
Smart Home AutomationNoNot applicable
CCTV SurveillanceYes0%
Club HouseYes74%
Community HallYes100%
Outdoor Sports facilityYes100%
Indoor Sports facilityYes0%
Swimming PoolYes100%
GymYes100%
ParksYes0%
Power BackupYes0%
GasYes0%
Water and SanitationYes100%
Air Conditioning And incerntionNoNot applicable
StaircasesYes0%
LiftsNoNot applicable
Staircases and Lift lobbies, corridor,lobbies, corridorNoNot applicable
Fire escapesNoNot applicable
Common entrance and exit for the building / common portico/foyer/verandahYes0%
BasementNoNot applicable
TerraceNoNot applicable
Outer WallYes70%
Open parking areas and common storage spacesYes0%
Provision for lodging of management staff and security staffNoNot applicable
Water conservation and renewable energyYes0%
Water Tanks, Sumps And Other Electrical EquipmentYes100%

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area21,246 sq m
Named landownersNone

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 114.94 cr
Cost incurredRs 164.11 cr
Spent of the estimate142.78%
Cost lineEstimatedIncurred
Estimated Cost of Construction as certified by EngineerRs 74.40 crRs 92.29 cr
Principal sum and interest payable to financial institutions-Scheduled BanksRs 33.45 cr-
On-site expenditure-Salaries of workersRs 7.09 crRs 31.51 cr
Principal sum and interest payable to financial institutions-Non Banking financial institution (NBFC)-Rs 40.31 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectVarun Biltoria
EngineerPRAKASH CHANNAPPAGOUDAR

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

ExtensionNov 2024 → Aug 2025

No reason recorded in the filing

EX/PRM/KA/RERA/1251/309/PR/250711/002923Aug 2025 → Aug 2026

Reason as filed by the promoterCustomers want modification in interiors

Litigation declared2

CaseCourtStatus
WP Nos, 23101/2022, 23102/2022, 23103/2022, 23020/2022, 23097/2022, 23059/2022, 23037/2022, 23106/2022 22858/2022, 23811/2022, 23826/2022,High Court of Karnataka-
WP 15729/2024/2024High Court of Karnataka-

Complaints filed with RERA Karnataka1

Case no.ComplainantRespondentFiled
00617/2025-Total Environment Building Systems Private Limited09/04/2025

Documents filed76

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/309/PR/191015/002923 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Q2 2026-27 Form-4 Certificate issued by Chartered AccountantFile: FORM-4 AFTER THE RAIN PHASE IIB Q2 26-27.pdf15 Oct 2026
Q2 2026-27 Form-5 Certificate issued by ArchitectFile: FORM-5 AFTER THE RAIN PHASE IIB Q2 26-27.pdf15 Oct 2026
Q2 2026-27 Form-6 Certificate issued by Structural EngineerFile: FORM-6 AFTER THE RAIN PHASE IIB Q2 26-27.pdf15 Oct 2026
Q2 2026-27 Water supply and sewage board15 Oct 2026
Q2 2026-27 KSPCB- PCB (10 Acres to 125 Acres)15 Oct 2026
Q2 2026-27 KSPCB- MOEF (Above 50 Acres)15 Oct 2026
Q2 2026-27 KPTCL- BESCOM15 Oct 2026
Q1 2026-27 Form-4 Certificate issued by Chartered AccountantFile: Form-4 ATR IIB Q1 26-27.pdf15 Jul 2026
Q1 2026-27 Form-5 Certificate issued by ArchitectFile: Form-5 ATR IIB Q1 26-27.PDF15 Jul 2026
Q1 2026-27 Form-6 Certificate issued by Structural EngineerFile: Form-6 ATR IIB Q1 26-27.pdf15 Jul 2026
Q1 2026-27 Water supply and sewage board15 Jul 2026
Q1 2026-27 KSPCB- PCB (10 Acres to 125 Acres)15 Jul 2026
Q1 2026-27 KSPCB- MOEF (Above 50 Acres)15 Jul 2026
Q1 2026-27 KPTCL- BESCOM15 Jul 2026
Q4 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Form-4 Q4 25-26 ATR phase 2B.pdf15 Apr 2026
Q4 2025-26 Form-5 Certificate issued by ArchitectFile: Form-5 Q4 25-26 AtR Ph 2b.PDF15 Apr 2026
Q4 2025-26 Form-6 Certificate issued by Structural EngineerFile: FORM-6 AFTER THE RAIN - PHASE IIB 31-03-2026.pdf15 Apr 2026
Q3 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Form-4 Q3-25-26.pdf27 Jan 2026
Q3 2025-26 Form-5 Certificate issued by ArchitectFile: Form-5_Architect_Certificate_ Ph-2B_Q3_25-26.pdf27 Jan 2026
Q3 2025-26 Form-6 Certificate issued by Structural EngineerFile: Form-6 After the Rain - Phase IIB 31-12-2025.pdf27 Jan 2026
CertificateFile: Company Incorporation Certificate.pdf-
Architect Certificate for Work Completion Schedule till DateFile: Ex-1.PDF-
Engineer Certificate for Work Completion Schedule till DateFile: Ex-5.pdf-
CA Certificate for Funds UtilizationFile: Ex-3.pdf-
Architect Certificate for Pending Work Completion Schedule.File: Ex-2.PDF-
Engineer Certificate for Pending Work Completion Schedule.File: Ex-6.pdf-
CA Certificate for Funds required for Project CompletionFile: Ex-4.pdf-
AffidavitFile: Extension affidavit.pdf-
Latest Encumbrance CertificateFile: EC copies.pdf-
Details Of Sold/ Un-sold UnitsFile: SoldUnsoldDetails.xlsx-
Re-Modified Letter-
site plan-
approval letter with ARCH plan and BDA plan-
Proforma-Sale Deed-
ATR Phase 02b - Agreement for Sale Proforma (1)-
Sale Deed -RTC-
PHASE 01, 02a & 02b-
SITE PLAN WITH ARCH SITE PLAN-
Proforma-Allotment letter-
Project Specification_compressed-
Encumbrance certificate-
Non Violation of Sec 3(1)-
JOINT DECLARATION AFFIDAVIT-
Khatha-
Reconstituted Partnership deed 02-11-2012-
Conversion certificate_compressed-
Relinquishment deed_compressed (2)-
BESCOM-
BWSSB-
KSPCB-
SEIAA-
SITE PLAN WITH ARCH SITE PLAN-
Sections with specification_2_compressed (1)-
Change of land use-
Advocate Search report-
Balance Sheet 2018 - 2019File: Balance Sheet 17-18.pdf-
Balance Sheet 2017 - 2018File: Balance Sheet 16-17.pdf-
Balance Sheet 2016 - 2017File: Balance Sheet 15-16.pdf-
Audited Profit and Loss Statement 2018 - 2019File: Profit loss Statement 17-18.pdf-
Audited Profit and Loss Statement 2017 - 2018File: Profit loss statement 16-17.pdf-
Audited Profit and Loss Statement 2016 - 2017File: Profit loss statement 15-16.pdf-
Director's Report 2018 - 2019File: Directors report 17-18_compressed.pdf-
Director's Report 2017 - 2018File: Directors report 16-17_compressed.pdf-
Director's Report 2016 - 2017File: Directors report 15-16_compressed.pdf-
Cash Flow Statement 2018 - 2019File: Cashflow Statement 17-18.pdf-
Cash Flow Statement 2017 - 2018File: Cashflow Statement 16-17.pdf-
Auditor's Report 2018 - 2019File: Auditor Report 17-18.pdf-
Auditor's Report 2017 - 2018File: Auditor Report 16-17.pdf-
Auditor's Report 2016 - 2017File: Auditor Report 15-16_compressed.pdf-
Income Tax Return Acknowledgement 2018 - 2019File: TEBS ITR Acknowledgement AY 2018-19.pdf-
Income Tax Return Acknowledgement 2017 - 2018File: TEBS ITR Acknowledgement AY 2017-18.pdf-
Income Tax Return Acknowledgement 2016 - 2017File: TEBS ITR Acknowledgement AY 2016-17.pdf-
FORM-B AFFIDAVIT-
Prospectus/BrochureFile: Annexure 1_0.pdf-
Advertisement Copy 1File: Annexure 2 Hindu jacket page 1_171119.pdf-
Tower Excel SheetFile: PRM_KA_RERA_1251_309_PR_191015_002923.xlsx-

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 not delivered by the promised date
ProjectLocationStatusPromisedDelivered
After the Rain Phase I-OngoingJun 2020Not delivered

How this compares with Bengaluru Urban

97%of this project is bookeddistrict median 51%
34%of Bengaluru Urban projects moved their completion datethis one moved by 21 months
1%of Bengaluru Urban registrations are shown as withdrawn or revokedthis one is not

Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.

Keep AFTER THE RAIN-PHASE IIB on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bengaluru Urban4,100+ in Bengaluru Urban

2 kmAFTER THE RAIN-PHASE IIBOther 10Dot size: filed unitsN

Filed coordinates, straight-line distance. 10 registered projects within 2 km.

Builder: Total Environment Building Systems Private Limited

Total Environment Building Systems Private limited. has 5 registrations on RERA Karnataka, including AFTER THE RAIN COMMERCIAL and Lost in the Greens. Its filings declare 3 earlier projects, none of them declared completed. Litigation is declared on 3 of its registrations. Read the full track record. See more projects on the Bengaluru Urban district page.

Frequently asked questions

What are my rights if AFTER THE RAIN-PHASE IIB is delayed beyond 1 Aug 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of AFTER THE RAIN-PHASE IIB?

The registered promoter entity is Total Environment Building Systems Private Limited, a company as per the filing. Its CIN U45202KA1996PTC020790 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in AFTER THE RAIN-PHASE IIB?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against AFTER THE RAIN-PHASE IIB?

Each case number above is a complaint filed with RERA Karnataka. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

Who certifies construction progress at AFTER THE RAIN-PHASE IIB?

The professionals named in the filing: Architect: Varun Biltoria; Engineer: PRAKASH CHANNAPPAGOUDAR. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in AFTER THE RAIN-PHASE IIB?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; how the declared litigation on this registration affects your risk; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About AFTER THE RAIN-PHASE IIB. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save AFTER THE RAIN-PHASE IIB to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.