Total Environment Building Systems Private limited.: RERA track record
CIN U45202KA1996PTC020790 · GSTIN 29AABCT9452F1Z2 · Company · attribution by exact filing name, entity resolution in progress
Total Environment Building Systems Private limited. has 5 registrations on RERA Karnataka, including AFTER THE RAIN COMMERCIAL and Lost in the Greens. Its filings declare 3 earlier projects, none of them declared completed. Litigation is declared on 3 of its registrations.
Projects by this developer
Showing all 5 projects.
Largest first, by the unit count in the filing.
| Project | Location | Units | Booked | Registered | Status |
|---|---|---|---|---|---|
| After the Rain - Phase II APRM/KA/RERA/1251/309/PR/180519/001763 | Bengaluru Urban | 95 | - | 19 May 2018 | Registration approved |
| AFTER THE RAIN COMMERCIALPRM/KA/RERA/1251/309/PR/110522/004867 | Bengaluru Urban, 562157 | 38 | 100% | 11 May 2022 | Registration approved |
| AFTER THE RAIN-PHASE IIBPRM/KA/RERA/1251/309/PR/191015/002923 | Bengaluru Urban | 37 | 97% | 15 Oct 2019 | Registration approved |
| AFTER THE RAIN-PHASE IICPRM/KA/RERA/1251/309/PR/300322/004795 | Bengaluru Urban, 562157 | 26 | 100% | 30 Mar 2022 | Registration approved |
| Lost in the GreensPRM/KA/RERA/1251/309/PR/171014/000665 | Bengaluru Urban | 10 | - | 14 Oct 2017 | Registration approved |
What this promoter declares as its own experience
Total Environment Building Systems Private limited. declares experience on 3 earlier projects. The experience table on RERA Karnataka carries no registration numbers, so none of them can be matched to a registration.
From the promoter experience table each promoter files with RERA Karnataka, as typed. A declaration naming another promoter's project is a claim of involvement, and involvement takes several shapes: a parent and its project company, one firm re-registering under a second name, or a joint venture between two separate developers. We publish the claim as filed and do not treat it as proof that the entities are one builder.
Past projects, as disclosed in RERA filings
| Project | Promised completion | Actual completion | Delivery |
|---|---|---|---|
| After the Rain Phase I | 30 Jun 2020 | Not completed yet | Ongoing |
| TMFT Phase 2 | 30 Sep 2024 | Not completed yet | Ongoing |
| AFTER THE RAIN-PHASE IIC | 1 Apr 2028 | Not completed yet | Ongoing |
Frequently asked questions
How do I verify Total Environment Building Systems Private limited. as a legal entity before signing?
Your agreement for sale must name the exact entity registered for the project, not a group brand. Cross-check its CIN U45202KA1996PTC020790 and GSTIN 29AABCT9452F1Z2 on the MCA and GST portals before signing anything. Large builders commonly register one company or LLP per project, which is normal; the entity on the registration certificate is the one legally accountable to you.
How should I use this delivery record when booking with Total Environment Building Systems Private limited.?
Check the specific project: promised date, current progress, and sales pace. If possession then slips past your agreement date, section 18 entitles you to interest for every month of delay at the rate the state's RERA rules prescribe, or an exit with a full refund with interest.
Does the declared litigation make Total Environment Building Systems Private limited. unsafe to buy from?
Not by itself. Litigation on a registration ranges from a boundary dispute to an allottee case about delay; what matters is the case type, which court or forum, and whether it touches the land title of the project you are buying. The case list is in each project's filed documents. Treat litigation as a question to resolve in writing before booking, not as a verdict either way.
Spotted a project attributed to the wrong developer, or something else wrong on this page? Projects are grouped by the promoter name as filed, so a firm that registers under two spellings can split across two pages. Tell us and we will check it against the filings.