Home / Browse projects / Pune, Maharashtra / Adhya Radha Krishna
Adhya Radha Krishna
RG-MH-02118 · RERA P52100001891 · Last updated on MahaRERA portal: 28 Apr 2026
Source: official MahaRERA filing
Red flags
- Litigation declared, 1 case
- Completion date moved by 51 months
- 1 extension taken
Clear
- No complaints on record
- No encumbrance on the project land
- Separate project account declared
- Allotment letter follows the model form
- Recorded completed on MahaRERA
- All 1 earlier projects delivered on promise
3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
Adhya Radha Krishna is a Residential / Group Housing project by ADHYA PROPERTIES in Pune, Maharashtra, registered with MahaRERA as P52100001891 on 29 Jul 2017. The registration is recorded completed; possession was promised by 31 Mar 2027. The completion date has moved by 51 months from the original filing. 296 of the 359 units on this registration are recorded sold or booked, and 37 of 55 construction stages are filed complete.
At a glance
Project
- NameAdhya Radha Krishna
- TypeResidential / Group Housing
- Location
- -
- Pimpri Chinchawad (M Corp.)
- Haveli
- Pune
- 412105
- Pincode412105
- MapView location on Google Maps (as filed on RERA)
- RERA no.P52100001891
- ReraGenie IDRG-MH-02118
Key dates
Key facts
Registration and timeline
- StatusCompleted
- Registered on29 Jul 2017
- Promised completion31 Mar 2027
- Revised completionRevised to 31 Mar 2027 (originally 30 Dec 2022)
- Buildings5 building records
- Documents filed178 files
Current status
Figures as on 28 Apr 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| A | NA | 12 | 12 | 70 | 0 | 70 |
| B | NA | 13 | 12 | 90 | 0 | 90 |
| - | NA | 0 | 0 | 0 | 0 | 0 |
| D | NA | 15 | 12 | 77 | 0 | 77 |
| E | NA | 15 | 12 | 98 | 24 | 122 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building5
As on 28 Apr 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
37 of 55 construction stages are filed complete across 5 buildings. The stage furthest along is External plumbing and external plaster, at 90%.
A100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
B100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
-0%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
D73%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
E76%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 90% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 50% |
Progress on shared amenities15
As on 28 Apr 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | Yes | 75% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 75% |
| Storm Water Drains | Yes | 75% |
| Landscaping & Tree Planting | Yes | 50% |
| Street Lighting | No | Not applicable |
| Community Buildings | Yes | 100% |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 50% |
| Solid Waste Management And Disposal | Yes | 50% |
| Water conservation /Rain water harvesting | Yes | 50% |
| Energy managemcnt | Yes | 50% |
| Fire protection and fire safety requirements | Yes | 50% |
| Electrical meter room, sub-station, receiving station | Yes | 50% |
| Aggregate area of recreational Open Space | Yes | 0% |
| Open Parking | No | Not applicable |
Parking filed156
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Closed/Covered | Total |
|---|---|---|
| A | 41 | 41 |
| B | 56 | 56 |
| D | 23 | 23 |
| E | 36 | 36 |
Land and ownership4
MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.
| Landowner | Village | District |
|---|---|---|
| Rajesh Pokharkar | Navi Mumbai (M Corp.) | Thane |
| Ramhari Baburao Jadhav | Pimpri Chinchawad (M Corp.) | Pune |
| Balu Baburao Jadhav | Pimpri Chinchawad (M Corp.) | Pune |
| Changdev Baburao Jadhav | Pimpri Chinchawad (M Corp.) | Pune |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| - | NA | Rs 22.00 cr | Rs 18.53 cr |
| E | NA | Rs 17.26 cr | Rs 18.11 cr |
| D | NA | Rs 15.74 cr | Rs 15.43 cr |
| B | NA | Rs 11.46 cr | Rs 11.46 cr |
| A | NA | Rs 10.53 cr | Rs 10.53 cr |
Certifying professionals and partners8
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Y.W. Architects |
| Architect | MahendraThakur And Associates |
| Engineer | SHRIKANT MADHAV KEDARE |
| Engineer | Rieddhesh Engineers |
| Engineer | The Axis Structural Engineers |
| Chartered Accountant | Mehjabeen Nadeem Bamne |
| Chartered Accountant | JITEN BHANUSHALI |
| Chartered Accountant | Harsh Kumar Satyanarayan Sharma |
| Partner | Role in project |
|---|---|
| ADHYA PROPERTIES | - |
Extensions applied for1
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterThere are 5 buildings in layout. Out of 5 buildings, Building A & B are completed and handed over to Allottees. We have taken separate RERA number for Building C and Construction of building D & E as per revised sanctioned plans not yet started
Litigation declared1
| Case | Court | Status |
|---|---|---|
| Special Civil Suit 989 of /2023 | Civil Judge Senior Division | Ongoing |
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 6 Jul 2017 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 17 Mar 2025 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 17 Mar 2025 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 17 Mar 2025Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateOn the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
uploaded 30 Sep 2021
Documents filed178
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 178 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Withdrawal Update Form 1File: FORM 1.pdf | 28 Apr 2026 |
| Withdrawal Update Form 2File: Form2 ABDE- Adhya Radha Krishna For Rera.pdf | 28 Apr 2026 |
| Withdrawal Update Form 3File: FORM 3.pdf | 28 Apr 2026 |
| Withdrawal Update Form 1File: FORM 1.pdf | 12 Feb 2026 |
| Withdrawal Update Form 2File: ADK Form 2.pdf | 12 Feb 2026 |
| Withdrawal Update Form 3File: FORM 3 RADHAKRISHNA.pdf | 12 Feb 2026 |
| Form 5 (FY 2024-2025)File: Adhya Radhakrishna.pdf | 9 Dec 2025 |
| Withdrawal Update Form 1File: adhaya radhakrishna Architect Form 1.pdf | 21 Nov 2025 |
| Withdrawal Update Form 2File: A B D E Engineers Certificate Form-2 30-09-2025.pdf | 21 Nov 2025 |
| Withdrawal Update Form 3File: CA Certificate FORM 3 A B D E wings.pdf | 21 Nov 2025 |
| Form 1File: Form 1 Adhya Radha 30 06 2025.pdf | 22 Aug 2025 |
| Form 2File: Form-2 Adhya Radha 30 06 2025.pdf | 22 Aug 2025 |
| Form 3File: FORM 3 Adhya Radha 30 06 2025.pdf | 22 Aug 2025 |
| Disclosure of Sold and Booked InventoryFile: Sold Unsold A B D E 30 06 2025.pdf | 22 Aug 2025 |
| Disclosure of sold/ booked inventoryFile: Sold Unsold Aadhya Radha.pdf | 15 Apr 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Aadhya Radha.pdf | 9 Apr 2025 |
| Layout approvalFile: 01 (2)_rotated_compressed.pdf | 17 Mar 2025 |
| Building plan approvalFile: 02 (1)_rotated_compressed.pdf | 17 Mar 2025 |
| Building plan approvalFile: 05_rotated.pdf | 17 Mar 2025 |
| Building plan approvalFile: 06_rotated (1).pdf | 17 Mar 2025 |
| Building plan approvalFile: 07_rotated.pdf | 17 Mar 2025 |
| Building plan approvalFile: 08_rotated.pdf | 17 Mar 2025 |
| Building plan approvalFile: 09_rotated.pdf | 17 Mar 2025 |
| Building plan approvalFile: 10 (1)_rotated.pdf | 17 Mar 2025 |
| Building plan approvalFile: 11 (1)_rotated.pdf | 17 Mar 2025 |
| Building plan approvalFile: Adhya Radha Krishna -Highlighted Layout plan.pdf | 17 Mar 2025 |
| Copy of Layout Approval (in case of layout)File: 01 (2)_rotated_compressed.pdf | 17 Mar 2025 |
| Certificates of CA (Form 3)File: CA FORM 3 abde wings 30 09 2024.pdf | 17 Mar 2025 |
| Commencement Certificates / NA Order for plotted developmentFile: CC (6)_compressed.pdf | 17 Mar 2025 |
| Building Plan Approval (IOD)File: 02 (1)_rotated_compressed.pdf | 17 Mar 2025 |
| Building Plan Approval (IOD)File: 05_rotated.pdf | 17 Mar 2025 |
| Building Plan Approval (IOD)File: 06_rotated (1).pdf | 17 Mar 2025 |
| Building Plan Approval (IOD)File: 07_rotated.pdf | 17 Mar 2025 |
| Building Plan Approval (IOD)File: 08_rotated.pdf | 17 Mar 2025 |
| Building Plan Approval (IOD)File: 09_rotated.pdf | 17 Mar 2025 |
| Building Plan Approval (IOD)File: 10 (1)_rotated.pdf | 17 Mar 2025 |
| Building Plan Approval (IOD)File: 11 (1)_rotated.pdf | 17 Mar 2025 |
| Building Plan Approval (IOD)File: Adhya Radha Krishna -Highlighted Layout plan.pdf | 17 Mar 2025 |
| Declaration about Commencement CertificateFile: Declaration Adhya Radha Krishna final.pdf | 17 Mar 2025 |
| Declaration about Commencement CertificateFile: CC Declaration Adhya Radha Krishna.pdf | 17 Mar 2025 |
| Certificates of CA (Form 3)File: CA Certificate FORM 3 ARK A B D E wings 31 12 24.pdf | 1 Feb 2025 |
| Disclosure of sold/ booked inventoryFile: Sole Unsold 31 12 2024.pdf | 1 Feb 2025 |
| Certificates of CA (Form 3)File: CA Certificate FORM 3 ARK A B D E wings 31 12 2024.pdf | 24 Jan 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ARK A B D E Engineers Certificate Form 2 31 12 2024 4.pdf | 24 Jan 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Arch Certificare 31 12 2024 ABDE.pdf | 16 Jan 2025 |
| Disclosure of sold/ booked inventoryFile: Slod - Unsold A,B,D,E 31 12 2024.pdf | 16 Jan 2025 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A 23-24.pdf | 22 Nov 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENG CERT ABDE SEPT.pdf | 6 Nov 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: ARK FORM 5 23-24.pdf | 6 Nov 2024 |
| Disclosure of sold/ booked inventoryFile: SOLD- Unsold ABDE.pdf | 17 Oct 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCH CERT ABDE.pdf | 16 Oct 2024 |
| Commencement Certificates / NA Order for plotted developmentFile: CC VERIFICATION (3).pdf | 16 Oct 2024 |
| Layout approvalFile: LAYOUT_compressed.pdf | 15 Oct 2024 |
| Building plan approvalFile: PARKING DETAILS PLAN_compressed.pdf | 15 Oct 2024 |
| Building plan approvalFile: Building D plan 1.pdf | 15 Oct 2024 |
| Building plan approvalFile: Building D plan 2.pdf | 15 Oct 2024 |
| Building plan approvalFile: Building D plan 3.pdf | 15 Oct 2024 |
| Building plan approvalFile: Building E plan 1.pdf | 15 Oct 2024 |
| Building plan approvalFile: Building E plan 2.pdf | 15 Oct 2024 |
| Building plan approvalFile: Building E plan 3.pdf | 15 Oct 2024 |
| Copy of Layout Approval (in case of layout)File: LAYOUT_compressed.pdf | 15 Oct 2024 |
| Commencement Certificates / NA Order for plotted developmentFile: Commencement Certificate No 119(P) 120,121,122_compressed.pdf | 15 Oct 2024 |
| Building Plan Approval (IOD)File: Building D plan 1.pdf | 15 Oct 2024 |
| Building Plan Approval (IOD)File: Building E plan 3.pdf | 15 Oct 2024 |
| Building Plan Approval (IOD)File: Building E plan 2.pdf | 15 Oct 2024 |
| Building Plan Approval (IOD)File: Building E plan 1.pdf | 15 Oct 2024 |
| Building Plan Approval (IOD)File: Building D plan 3.pdf | 15 Oct 2024 |
| Building Plan Approval (IOD)File: Building D plan 2.pdf | 15 Oct 2024 |
| Building Plan Approval (IOD)File: PARKING DETAILS PLAN_compressed.pdf | 15 Oct 2024 |
| Certificates of CA (Form 3)File: CA CertificateJun 2024.pdf | 14 Aug 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ARK ENGINEER CERT JUN 24.pdf | 9 Aug 2024 |
| Disclosure of sold/ booked inventoryFile: SOLD UNSOLD A to E Wing.pdf | 20 Jul 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate Wing A-E.pdf | 16 Jul 2024 |
| Disclosure of sold/ booked inventoryFile: Sold Unsold A B D E 31 03 2024.pdf | 22 Apr 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 A B D E 31 03 2024.pdf | 20 Apr 2024 |
| Certificates of CA (Form 3)File: CA Certificate A B D E wings 31 03 2024.pdf | 20 Apr 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect certificatre 31 03 2024.pdf | 19 Apr 2024 |
| Certificates of CA (Form 3)File: 31-12-23 - FORM 3.pdf | 20 Jan 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Arch Certificate 31-12-2023.pdf | 11 Jan 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineers Certificate ARK A,B,D,E (Form-2) 31-12-2023.pdf | 11 Jan 2024 |
Promoter's earlier projects1
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Flats | Status | Promised | Delivered |
|---|---|---|---|---|---|
| ADHYA RAHI | Gat No 130 hissa 2 Dehu Taluka Haveli District Pune | 48 | Completed | Apr 2017 | Mar 2017 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Pune
Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.
Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Useful on a completed registration when you are buying resale, or checking what was promised against what was delivered.
- 3 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 4 other registrations and every project registered within 2 km, which the RERA portal never shows together
- All 178 filed documents as one ZIP, foldered, with a manifest
Keep Adhya Radha Krishna on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near -13,700+ in Pune
Filed coordinates, straight-line distance. 191 registered projects within 2 km.
TANISH PARK
TANISH DEVELOPERS
Ajinkya Towers
APAK Bussiness Innovation Pvt Ltd
SILVER GARDENIA
SILVER PROMOTERS AND DEVELOPERS
Mangalam Life Park
Mangalam Buildcorp
SingaPune Ph 3
Xrbia Mirth Properties LLP
SingaPune Ph 2
Xrbia Mirth Properties LLP
Builder: ADHYA PROPERTIES
ADHYA PROPERTIES has 5 registrations on MahaRERA, including Adhya Radha Krishna and Adhya Rohan. Its filings disclose 1 earlier MahaRERA project: declares 1 of 1 past projects completed on time. Litigation is declared on 2 of its registrations. Read the full track record. See more projects on the Pune district page.
Frequently asked questions
What are my rights if Adhya Radha Krishna is delayed beyond 31 Mar 2027?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of Adhya Radha Krishna?
The registered promoter entity is ADHYA PROPERTIES, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in Adhya Radha Krishna?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for Adhya Radha Krishna?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at Adhya Radha Krishna?
The professionals named in the filing: Architect: Y.W. Architects; Architect: MahendraThakur And Associates; Engineer: SHRIKANT MADHAV KEDARE; Engineer: Rieddhesh Engineers; Engineer: The Axis Structural Engineers; Chartered Accountant: Mehjabeen Nadeem Bamne. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Adhya Radha Krishna?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; how the declared litigation on this registration affects your risk; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback