ReraGenieLog inGet a buyer report

Home / Browse projects / Pune, Maharashtra / ACE AASTHA BUILDING C

Registration lapsed No litigation declared Residential / Group Housing project

ACE AASTHA BUILDING C

By SAKSHI DEVELOPERS

RG-MH-15271 · RERA P52100024476 · Last updated on MahaRERA portal: 20 Oct 2025

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 13 months past the filed date
  • 11 complaints at MahaRERA
  • Completion date moved by 11 months
  • 1 extension taken

Clear

  • No litigation declared
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Sep 2025Possession promised13 months past this date
9 of 11Construction stages donefurthest along: Installation of Lifts, 65%
17 of 110Units unsoldnot recorded sold or booked
11Complaints at MahaRERAon this registration
Jump to the 96 documents Report an error

ACE AASTHA BUILDING C is a Residential / Group Housing project by SAKSHI DEVELOPERS in Pune, Maharashtra, registered with MahaRERA as P52100024476 on 18 Feb 2020. Possession was promised by 30 Sep 2025 and is now 13 months past that date. The completion date has moved by 11 months from the original filing. 93 of the 110 units on this registration are recorded sold or booked, and 9 of 11 construction stages are filed complete. 11 complaints are on record with the regulator.

At a glance

Project

  • NameACE AASTHA BUILDING C
  • TypeResidential / Group Housing
  • Location
    • ALANDI - CHAROLI ROAD
    • NEAR TAPKIR NAGAR
    • CHOVISAWADI
    • OPP. TANISHQ ORCHID SOCIETY
    • Pimpri Chinchawad (M Corp.)
    • Haveli
    • Pune
    • 412105
  • Pincode412105
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100024476
  • ReraGenie IDRG-MH-15271

Builder

  • NameSAKSHI DEVELOPERS
  • Entity typePartnership
  • PartnersANUP PARMANAND JHAMTANI, PARMANAND MELHUMAL JHAMTANI, RAVINDRA DHONDIBA NAMDE
  • Other registrations3 more →
  • Completed3 of 4
  • No longer live1 lapsed, de-registered or revoked

Key dates

13 months past promisethis monthRegisteredFeb 2020First promiseOct 2024Revised toSep 2025

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on18 Feb 2020
  • Promised completion30 Sep 2025
  • Revised completionRevised to 30 Sep 2025 (originally 30 Oct 2024)
  • Buildings1 building record
  • Documents filed96 files

Current status

85%93 of 110 units booked
98.4%Work done, per cost certificate

Figures as on 20 Oct 2025, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
BUILDING CNA16141100110

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 20 Oct 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

9 of 11 construction stages are filed complete. The stage furthest along is Installation of Lifts, at 65%.

BUILDING C: 88% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.65%

Progress on shared amenities15

As on 20 Oct 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes100%
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes30%
Street LightingYes100%
Community BuildingsYes0%
Treatment And Disposal Of Sewage And Sullage WaterYes90%
Solid Waste Management And DisposalYes100%
Water conservation /Rain water harvestingYes100%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceYes0%
Open ParkingYes70%

Parking filed168

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots168
Closed/Covered165
Open Space3

Land and ownership87

MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area3,188 sq m
Land owned byThe promoter, with other names on the file
Named landowners87
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on18 Jul 2025
LandownerVillageDistrict
RAHUL NAMDEPimpri Chinchawad (M Corp.)Pune
DATTARAYE KISAN TAPKIR-Pune
ABASAHEB SHANTARAM JADHAV-Pune
GAJANAN SHANTARAM JADHAV-Pune
SHANTARAM BABURAO JADHAV-Pune
BALASAHEB SHANTARAM JADHAV-Pune
PIRAJI BABU TAPKIR-Pune
BADASAHEB BABU TAPKIR-Pune
ANKUSH BABURAO TAPKIR-Pune
SUNIL DATTATRAYA TAPKIR-Pune
ASHA DATTATRAYA TAPKIR-Pune
VIDYA SANTOSH GAIKWAD-Pune
SARIKA SHAHJI PAWAR-Pune
SUREKHA UMESH CHAUDHARY-Pune
SHUBHAM SUBHASH TAPKIR-Pune
MAYA NITIN SAWANT-Pune
KOMAL ATUL MANJARE-Pune
MANGAL SUBHASH TAPKIR-Pune
SOBHA NARAYAN PAWARPimpri Chinchawad (M Corp.)Pune
MANISHA BAPUSAHEB PATILPimpri Chinchawad (M Corp.)Pune
ASHA SHARAD CHOUDHARYThane (M Corp.)Thane
SANTOSH HARICHANDRA SALUNKEGreater Mumbai (M Corp.) (Part) (802794)Mumbai Suburban
GOVIND RAMCHANDRA PATILThane (M Corp.)Thane
SURYAPRAKASH KRANMAL JAINThane (M Corp.)Thane
SARTH SURFACRE THROUGH PARTNER PRASHANT PALANDEThane (M Corp.)Thane
HANUMANT SHREEMANT GONDAWALEPimpri Chinchawad (M Corp.)Pune
SUHAS KALGONDHA PATILPimpri Chinchawad (M Corp.)Pune
TUKARAM VITTHAL TITAVEPimpri Chinchawad (M Corp.)Pune
NITIN VITTHAL TITAVEPimpri Chinchawad (M Corp.)Pune
ROHINI RAMESH RAMGIRPimpri Chinchawad (M Corp.)Pune
SMITA SANJAY PATHAKPimpri Chinchawad (M Corp.)Pune
SANDHYA TANAJI SUTARPimpri Chinchawad (M Corp.)Pune
SURESH UTTAM BHAGVATWakadPune
NAVNATH SURESH MHASKEPimpri Chinchawad (M Corp.)Pune
RAM VILAS WADNEPimpri Chinchawad (M Corp.)Pune
BALASAHEB ATMARAM BAHIRBhosariPune
SAMPAT SOLANKIJamkhed (CT)Ahmednagar
LAXMAN BAPU KARANDEPimpri Chinchawad (M Corp.)Pune
SUNANDA SUNANDA KADEPimpri Chinchawad (M Corp.)Pune
JYOTI VIJAY PACHARNEPune (M Corp.)Pune
BHAURAO DIGAMBAR LOKHANDEPimpri Chinchawad (M Corp.)Pune
URMILA MUNNALAL YADAVPimpri Chinchawad (M Corp.)Pune
PANDURANG YASHWANT PAWARJatSangli
BASVESHWAR APPASO ANKALGIJatSangli
PANDURANG TATYA AASBESangole (M Cl)Solapur
SHIVAJI SHANKAR GAWANDPimpri Chinchawad (M Corp.)Pune
SADASHIV PARASRAM JADHAVWakadPune
KAILASH PATIL-Pune
SHANKAR JIJABA NIKAM-Pune
SANTOSH TUKARAM YADAVPimpri Chinchawad (M Corp.)Pune
NANDA SANTOSH YADAVPimpri Chinchawad (M Corp.)Pune
RAHUL RAMESH NAID-Pune
PRAMOD MACHINDRANATH SHEDGEPimpri Chinchawad (M Corp.)Pune
GIRISH DINKAR MAHAJANPimpri Chinchawad (M Corp.)Pune
KALPANA GIRISH MAHAJANPimpri Chinchawad (M Corp.)Pune
VILAS SONYABAPU JAGTAPPimpri Chinchawad (M Corp.)Pune
SARTH SURFACRETE THROUGH PARTNER NARESH PATILThane (M Corp.)Thane
BALU UTTAM BHAGVATWakadPune
Dhananjay Balkrushna Lokhande-Pune
Vasundhara Shankar Borade-Pune
Hari Shankar Borade-Pune
Makrand Mhatu Bhujbal-Pune
Maruti Sadashiv Bahirwade-Pune
Dattatray Sadashiv Bahirwade-Pune
Kishore Babasaheb Chabukswar-Pune
Babu Sakharam Tapkir-Pune
Malti Piraji Tapkir-Pune
Sameer Piraji Tapkir-Pune
Tejasvi Samir Tapkir-Pune
Vijaya Pandurang Tanpure-Pune
Dawraka Balkrushna Tapkir-Pune
Kusum Balkrushna Tapkir-Pune
Dinesh Balkrushna Tapkir-Pune
Sadhana Dinesh Tapkir-Pune
Omkar Dinesh Tapkir-Pune
Natasha Dinesh Tapkir-Pune
Santosh Balkrushna Tapkir-Pune
Reshama Santosh Tapkir-Pune
Aditya Santosh Tapkir-Pune
Vedant Santosh Tapkir-Pune
Anjana Ankush Tapkir-Pune
Arati Avinash Tapkir-Pune
Shubhangi Sunil Tapkir-Pune
Soham Sunil Tapkir-Pune
Vidhya Santosh Tapkir-Pune
Savita Kisan Chaudary-Pune
Komal Subhash Tapkir-Pune

Approvals and building plan

Sanctioning authorityPimpri Chinchwad Municipal Corporation. Pune
Permissible FSI8574.82
Proposed, not sanctioned8,575 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchIndusInd Bank Ltd Gr Floor Atlanta Building Nariman Point Mumbai 400021
Estimated costRs 25.08 cr
Cost incurredRs 24.68 cr
Work done98.41%
BuildingWingEstimatedIncurred
BUILDING CNARs 21.25 crRs 21.06 cr
-NARs 3.83 crRs 3.63 cr

Certifying professionals and partners5

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectVKa Architecture
EngineerBHAUSAHEB JANGLE
EngineerNarendra B Gosavi
Chartered AccountantRAVI TALREJA AND ASSOCIATES
Chartered AccountantHaresh K Lallwani and Associates
PartnerRole in project
SAKSHI DEVELOPERS-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52100024865Oct 2024 → Sep 2025

Reason as filed by the promoterOur building timetable was slowed down and crucial activities were postponed due to a significant scarcity of construction materials caused by a strike in the supply chain. Additionally, our construction efforts at the site halted for several days due to the high rains that Pune experienced this year, which caused a delay.

Complaints filed with MahaRERA11

Case no.ComplainantRespondentFiled
CC12600323YOGESH SANTOSH BORSESAKSHI DEVELOPERS17/01/2026
CC12601151DEEPAK VINAYAK RAHINJSAKSHI DEVELOPERS02/03/2026
CC12601150DEEPAK VINAYAK RAHINJSAKSHI DEVELOPERS02/03/2026
CC12601648Mangesh Dnyaneshwar BangaleSAKSHI DEVELOPERS23/03/2026
CC12601645Rupesh GholapSAKSHI DEVELOPERS23/03/2026
CC12601955Jagannath Venunath HalnorSAKSHI DEVELOPERS02/04/2026
CC12601836Nikhil Patangrao NikamSAKSHI DEVELOPERS28/03/2026
CC12601953Komal Pandurang ManeSAKSHI DEVELOPERS02/04/2026
CC12601956Adesh Balasaheb KhaireSAKSHI DEVELOPERS02/04/2026
CC12602331Nilesh Narayan ThoratSAKSHI DEVELOPERS20/04/2026
CC12602335Narendra Bhaskar PatilSAKSHI DEVELOPERS20/04/2026

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 27 Nov 2019
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 16 Oct 2025
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 16 Oct 2025
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 13 Feb 2024Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed96

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 96 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Ace Aastha Form 1.pdf20 Oct 2025
Withdrawal Update Form 1File: Ace Aastha Form 1.pdf20 Oct 2025
Withdrawal Update Form 1File: Ace Aastha Form 1 Q2.pdf20 Oct 2025
Withdrawal Update Form 2File: Ace Aastha.pdf20 Oct 2025
Withdrawal Update Form 2File: Ace Aastha.pdf20 Oct 2025
Withdrawal Update Form 2File: Ace Aastha.pdf20 Oct 2025
Withdrawal Update Form 3File: ACE AASTHA FORM 3 Q2.pdf20 Oct 2025
Withdrawal Update Form 3File: ACE AASTHA FORM 3 Q2.pdf20 Oct 2025
Withdrawal Update Form 3File: ACE AASTHA FORM 3 Q2.pdf20 Oct 2025
Layout approvalFile: 1-16 - Marked.pdf16 Oct 2025
Building plan approvalFile: 2-16.pdf16 Oct 2025
Building plan approvalFile: 3-16.pdf16 Oct 2025
Building plan approvalFile: 4-16.pdf16 Oct 2025
Building plan approvalFile: 5-16.pdf16 Oct 2025
Form 5 (FY 2023-2024)File: Form 5 Ace Aastha.pdf1 Aug 2025
Withdrawal Update Form 1File: ACE AASTHA C WING.pdf22 Jul 2025
Withdrawal Update Form 2File: Ace Aastha Form 2.pdf22 Jul 2025
Withdrawal Update Form 3File: ACE AASTHA C WING FORM 3.pdf22 Jul 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Ace Aastha C.pdf19 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Ace Aastha Form 3 Final.pdf19 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Ace Aastha.pdf19 Apr 2025
Disclosure of sold/ booked inventoryFile: 12) ACE AASTHA BUILDING C.pdf19 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Aastha C.pdf18 Jan 2025
Disclosure of sold/ booked inventoryFile: Ace Aastha C Wing.pdf18 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ACE AASTHA WING C.pdf16 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: ACE AASTHA FORM 3 Q3 2425.pdf16 Jan 2025
Other - TechnicalFile: Ace Aastha C Wing Revised Schedule for Rera Extention.pdf8 Nov 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: fORM 5.pdf29 Oct 2024
Declaration in FORM BFile: Form B.pdf28 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ACE AASTHA WING- C (2).pdf16 Oct 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: ACE AASTHA BUILDING - C.pdf16 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineers Certificate Form - 2.pdf16 Oct 2024
Disclosure of sold/ booked inventoryFile: Ace Aastha Building -C.pdf16 Oct 2024
Disclosure of sold/ booked inventoryFile: ACE AASTHA BUILDING C.pdf18 Jul 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ACE AASHA WING-C.pdf17 Jul 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Ace Aastha Building C.pdf17 Jul 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: ACE AASTHA BUILDING -C.pdf17 Jul 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Ace Aastha C Wing.pdf29 May 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Aastha C Wing.pdf19 Apr 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ACE AASTHA C BUILDING.pdf19 Apr 2024
Disclosure of sold/ booked inventoryFile: Ace Aastha C Wing.pdf19 Apr 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 ACE AASTHA BUILDING C.pdf19 Apr 2024
Layout approvalFile: Ace AAstha C Wing Sheet 1.pdf13 Feb 2024
Building plan approvalFile: Ace AAstha C Wing Sheet 1.pdf13 Feb 2024
Building plan approvalFile: Ace Aastha C wing Sheet 2.pdf13 Feb 2024
Building plan approvalFile: Ace Aastha C Wing Sheet 3.pdf13 Feb 2024
Building plan approvalFile: Ace Aastha C Wing Sheet 4.pdf13 Feb 2024
Building plan approvalFile: Ace Aastha C wing Sheet 5.pdf13 Feb 2024
Copy of Layout Approval (in case of layout)File: Ace AAstha C Wing Sheet 1.pdf13 Feb 2024
Building Plan Approval / NA Order for plotted developmentFile: Ace AAstha C Wing Sheet 1.pdf13 Feb 2024
Building Plan Approval / NA Order for plotted developmentFile: Ace Aastha C wing Sheet 2.pdf13 Feb 2024
Building Plan Approval / NA Order for plotted developmentFile: Ace Aastha C Wing Sheet 3.pdf13 Feb 2024
Building Plan Approval / NA Order for plotted developmentFile: Ace Aastha C Wing Sheet 4.pdf13 Feb 2024
Building Plan Approval / NA Order for plotted developmentFile: Ace Aastha C wing Sheet 5.pdf13 Feb 2024
Commencement Certificates / NA Order for plotted developmentFile: CC BP 57 2023 Dt 28062023.pdf13 Feb 2024
Disclosure of sold/ booked inventoryFile: ACE AAstha.pdf3 Feb 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ACE AASTHA WING - C.pdf19 Jan 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ACE AASTHA BUILDING - C.pdf19 Jan 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: ACE AASTHA C BUILDING_compressed.pdf19 Jan 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Sakshi Developers C Wing Form 5 March 2023.pdf30 Oct 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: ACE AASTHA BUILDING C DSC_11zon.pdf7 Oct 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Astha C.pdf30 Sep 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Sakshi Dev Form 1.pdf13 Jul 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Sakshi C Form 2.pdf6 Jul 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Aastha C.pdf11 Apr 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Aastha C.pdf7 Apr 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Sakshi C Building.pdf25 Mar 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: form 2 aastha c.pdf18 Jan 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Ace Aastha C.pdf18 Jan 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 ACE AASTHA BUILDING C.pdf5 Jan 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Sakshi Dev C Building Form 5.pdf1 Nov 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Sakshi Dev C Building.pdf18 Oct 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ACE AASTHA BUILDING C.pdf12 Oct 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: ACE AASTHA BUILDING C.pdf12 Oct 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1ACE AASTHA BUILDING C.pdf20 Jul 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ACE AASTHA BUILDING C.pdf20 Jul 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: ACE AASTHA BUILDING C.pdf20 Jul 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: FORM 5 Sakshi Dev C Wing Mar 21 P52100024476_compressed.pdf2 Jun 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 02 Ace Aastha C.pdf30 Oct 2021
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Aastha C.pdf20 Oct 2021

How this compares with Pune

85%of this project is bookeddistrict median 31%
26%of Pune projects moved their completion datethis one moved by 11 months
26%of Pune registrations have lapsed or been cancelledthis one is among them

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep ACE AASTHA BUILDING C on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near OPP. TANISHQ ORCHID SOCIETY13,700+ in Pune

2 kmACE AASTHA BUILDING CCompleted 76Lapsed / revoked 36Other 94Dot size: filed unitsN

Filed coordinates, straight-line distance. 206 registered projects within 2 km.

Builder: SAKSHI DEVELOPERS

SAKSHI DEVELOPERS has 4 registrations on MahaRERA, including SAKSHI HEIGHTS and ACE AASTHA BUILDING A. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What does it mean that ACE AASTHA BUILDING C shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if ACE AASTHA BUILDING C is delayed beyond 30 Sep 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of ACE AASTHA BUILDING C?

The registered promoter entity is SAKSHI DEVELOPERS, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in ACE AASTHA BUILDING C?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against ACE AASTHA BUILDING C?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for ACE AASTHA BUILDING C?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at ACE AASTHA BUILDING C?

The professionals named in the filing: Architect: VKa Architecture; Engineer: BHAUSAHEB JANGLE; Engineer: Narendra B Gosavi; Chartered Accountant: RAVI TALREJA AND ASSOCIATES; Chartered Accountant: Haresh K Lallwani and Associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in ACE AASTHA BUILDING C?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About ACE AASTHA BUILDING C. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save ACE AASTHA BUILDING C to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.