ReraGenieLog inGet a buyer report

Home / Browse projects / Pune, Maharashtra / AbhangheightsAbuilding

Completed No litigation declared Others project

AbhangheightsAbuilding

By R K Lunkad Housing Company

RG-MH-64761 · RERA P52100045587 · Last updated on MahaRERA portal: 12 Nov 2024

Source: official MahaRERA filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA

Nothing adverse is on this record. The buyer report still reads the filed documents themselves, and places this filing against the promoter's 4 other registrations.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Jun 2025Possession promisedregistration recorded completed
10 of 11Construction stages donefurthest along: Podiums (if any), 0%
0Complaints at MahaRERAon this registration
Jump to the 62 documents Report an error

AbhangheightsAbuilding is a Others project by R K Lunkad Housing Company in Pune, Maharashtra, registered with MahaRERA as P52100045587 on 24 May 2022. The registration is recorded completed; possession was promised by 30 Jun 2025.

At a glance

Project

  • NameAbhangheightsAbuilding
  • TypeOthers
  • Location
    • Charoli Pune airport road
    • Chovisawadi
    • Pimpri Chinchawad (M Corp.)
    • Haveli
    • Pune
    • 412105
  • Pincode412105
  • RERA no.P52100045587
  • ReraGenie IDRG-MH-64761

Builder

  • NameR K Lunkad Housing Company
  • Entity typePartnership
  • PartnerRavindra Ramanlal Lunkad
  • Other registrations4 more →
  • Completed4 of 5
  • Declared earlier projects5 →

Key dates

this monthRegisteredMay 2022PromisedJun 2025Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on24 May 2022
  • Promised completion30 Jun 2025
  • Revised completionNone
  • Buildings1 building record
  • Documents filed62 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Abhang Heights A buildingNA170000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 12 Nov 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

10 of 11 construction stages are filed complete. The stage furthest along is Podiums (if any), at 0%.

Abhang Heights A building: 91% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 12 Nov 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes100%
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)NoNot applicable
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingYes100%
Street LightingYes100%
Community BuildingsYes100%
Treatment And Disposal Of Sewage And Sullage WaterYes100%
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes100%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceYes100%
Open ParkingYes100%

Parking filed78

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots78
Closed/Covered75
Open Space3

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area1,845 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI19773.0
Proposed, not sanctioned15,200 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchThergoan Pune 33

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectKhire Bhide Ass
EngineerSunil Mutalik and ass
Chartered AccountantMutha and lahoti ass
PartnerRole in project
R K Lunkad Housing Company-

Litigation declared1

CaseCourtStatus
1413/2013/2013Civil Judge Senior Division PunePending For Issues

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 11 May 2022
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 2 Jun 2022
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 9 Aug 2022
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 2 Jun 2022Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 9 Oct 2024

Documents filed62

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 01 AH A BLDG Sept 24.pdf12 Nov 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 03 AH A BLDG sept 24.pdf12 Nov 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 02 AH A BLDG sept 24.pdf12 Nov 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: ABHANG HEIGHTS A BLDG FORM 05 SEPT 24.pdf18 Oct 2024
Architect’s Certificate on Completion of Project (Form 4)File: FORM 4 A AND B BLDG (2 files merged).pdf15 Oct 2024
Status of Formation of Legal Entity (Society/Co Op etc.)File: ABHANG HEIGHTS SOCIETY REGISTRATION CERTIFICATE.pdf15 Oct 2024
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: ABHANG HEIGHTS COMPLETION.pdf9 Oct 2024
Home Buyer /Allottee Grievance Redressal CellFile: 154 AH.pdf1 Aug 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 01 AH A BLDG june 2024.pdf22 Jul 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 02 AH A BLDG june 2024.pdf22 Jul 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: ABHANG HEIGHTS form 3 A BLDG june 2024 converted.pdf22 Jul 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 01 Abhang A Bldg.pdf20 Apr 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 02 Abhang Heights A Bldg.pdf20 Apr 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2 A march 24 Abhang A - Copy.pdf20 Apr 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 03 Abhang Heights A Bldg - converted.pdf20 Apr 2024
Proforma of Agreement for saleFile: Abhang heights draft agreement.pdf21 Mar 2024
Deviation Report with respect to model copy of AgreementFile: Deviation for agreement Abhang.pdf21 Mar 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 Abhang heights A bldg (1).pdf11 Jan 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ABHANG HEIGHTS FORM 02A BLDG DEC 23.pdf11 Jan 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: ABHANG HEIGHTS A BLDG.pdf11 Jan 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2 A dec 23 Abhang A.pdf6 Jan 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: AH A BLDG FORM 01 (1).pdf7 Oct 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: AH A BLDG FORM 02.pdf7 Oct 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: AH A BLDG FORM 03 (1).pdf7 Oct 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: doc02846220231003124845.pdf3 Oct 2023
Deviation Report with respect to model copy of AgreementFile: Draft Agreement Deviation Report Abhang Heights (1).pdf25 Aug 2023
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Format A Abhang Heights A Bldg.pdf10 Jul 2023
Disclosure of sold/ booked inventoryFile: New Microsoft Excel Worksheet (1).pdf7 Jul 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 AH A BLDG jUNE 23.pdf10 Jun 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 A HA BLDG June 23.pdf10 Jun 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: ABHANG HEIGHTS A BLDG 15 may 23.pdf19 May 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: Abhang heights Disclosure of interest.pdf3 Mar 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 B FEB 23.pdf8 Feb 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 A FEB 23.pdf8 Feb 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 A FEB 23.pdf8 Feb 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 A FEB 23.pdf8 Feb 2023
Details of encumbrances concerned to FinanceFile: 154 Abhang height CONERNED TO LEGAL Encoumberance.pdf31 Jan 2023
Details of encumbrances concerned to LegalFile: 154 Abhang height CONERNED TO LEGAL Encoumberance.pdf31 Jan 2023
Declaration about Commencement CertificateFile: Abhang heights declaration about commencement certificate.pdf18 Jan 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2 A 22 annual (1).pdf12 Jan 2023
Building plan approvalFile: typical plan_compressed.pdf9 Aug 2022
Building plan approvalFile: first floor plans_compressed.pdf9 Aug 2022
Building Plan Approval / NA Order for plotted developmentFile: typical plan_compressed.pdf9 Aug 2022
Building Plan Approval / NA Order for plotted developmentFile: first floor plans_compressed.pdf9 Aug 2022
Layout approvalFile: Layout_compressed (1).pdf2 Jun 2022
Building plan approvalFile: All floor plans A wing_compressed.pdf2 Jun 2022
Copy of Layout Approval (in case of layout)File: Layout_compressed (1).pdf2 Jun 2022
Building Plan Approval / NA Order for plotted developmentFile: All floor plans A wing_compressed.pdf2 Jun 2022
Commencement Certificates / NA Order for plotted developmentFile: Commencement MAY 22_compressed.pdf2 Jun 2022
Layout approvalFile: A plan _compressed.pdf11 May 2022
Building plan approvalFile: Floor plan _compressed.pdf11 May 2022
PAN CardFile: 1 PAN Card.pdf11 May 2022
Copy of the legal title reportFile: LEGAL TITLE REPORT.pdf11 May 2022
Details of encumbrancesFile: Non Encumbrance Certificate.pdf11 May 2022
Copy of Layout Approval (in case of layout)File: A plan _compressed.pdf11 May 2022
Building Plan Approval / NA Order for plotted developmentFile: Floor plan _compressed.pdf11 May 2022
Commencement Certificates / NA Order for plotted developmentFile: commencement A Abhang _compressed.pdf11 May 2022
Declaration about Commencement CertificateFile: COMMENCEMENT DECLARATION.pdf11 May 2022
Declaration in FORM BFile: ABHANG HEIGHTS A WING FORM B_compressed.pdf11 May 2022
CERSAI detailsFile: CERSAI -Abhang heights A Bldg.pdf11 May 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 A Building_compressed.pdf11 May 2022
Proforma of Allotment letterFile: A wing abhang heights draft agreement.pdf11 May 2022

How this compares with Pune

26%of Pune projects moved their completion datethis one has not
26%of Pune registrations have lapsed or been cancelledthis one is completed

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep AbhangheightsAbuilding on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Chovisawadi13,700+ in Pune

Builder: R K Lunkad Housing Company

R K Lunkad Housing Company has 5 registrations on MahaRERA, including Alankar E building and ALANKAR F BUILDING. Its filings disclose 5 earlier MahaRERA projects: declares 5 of 5 past projects completed on time. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if AbhangheightsAbuilding is delayed beyond 30 Jun 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of AbhangheightsAbuilding?

The registered promoter entity is R K Lunkad Housing Company, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in AbhangheightsAbuilding?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for AbhangheightsAbuilding?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at AbhangheightsAbuilding?

The professionals named in the filing: Architect: Khire Bhide Ass; Engineer: Sunil Mutalik and ass; Chartered Accountant: Mutha and lahoti ass. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in AbhangheightsAbuilding?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About AbhangheightsAbuilding. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save AbhangheightsAbuilding to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.