Home / Browse projects / Pune, Maharashtra / Aayush Park - III

Registration lapsed No litigation declared Residential / Group Housing project

Aayush Park - III

By Earnest and Shah Ventures

RG-MH-03454 · RERA P52100020055 · Last updated on MahaRERA portal: 5 Nov 2024

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 22 months past the filed date

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Dec 2024Possession promised22 months past this date
26 of 33Construction stages doneacross 3 buildings; furthest along: Stilt Floor, 0%
0Complaints at MahaRERAon this registration
Jump to the 124 documents Report an error

Aayush Park - III is a Residential / Group Housing project by Earnest and Shah Ventures in Pune, Maharashtra, registered with MahaRERA as P52100020055 on 25 Mar 2019. Possession was promised by 30 Dec 2024 and is now 22 months past that date.

At a glance

Project

  • NameAayush Park - III
  • TypeResidential / Group Housing
  • Location
    • Talegaon Katvi Road
    • Katvi
    • Katavi
    • Mawal
    • Pune
    • 410507
  • Pincode410507
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100020055
  • ReraGenie IDRG-MH-03454

Builder

  • NameEarnest and Shah Ventures
  • Entity typePartnership
  • PartnersVinaykumar Mahavirprasad Chudiwal, Mahantesh Babulal Palresha, Akansh Shailesh Shah, Shailesh Rupalal Shah, Shreyas Ravikumar Kasliwal
  • Other registrations3 more →
  • Completed2 of 4
  • No longer live2 lapsed, de-registered or revoked
  • Declared earlier projects1 →

Key dates

22 months past promisethis monthRegisteredMar 2019PromisedDec 2024

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on25 Mar 2019
  • Promised completion30 Dec 2024
  • Revised completionNone
  • Buildings3 building records
  • Documents filed124 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
ANA190000
BNA170000
CNA130000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building3

As on 5 Nov 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

26 of 33 construction stages are filed complete across 3 buildings. The stage furthest along is Stilt Floor, at 0%.

A82%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
B73%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
C82%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 5 Nov 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes100%
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes100%
Street LightingYes100%
Community BuildingsYes100%
Treatment And Disposal Of Sewage And Sullage WaterYes100%
Solid Waste Management And DisposalYes100%
Water conservation /Rain water harvestingYes100%
Energy managemcntYes100%
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceYes100%
Open ParkingYes100%

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area13,800 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI24481.0
Proposed, not sanctioned21,931 sq m
Buildings approved4
Buildings sanctioned3

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchShirole Bhavan, PMT Building, JM Road, Pune - 411004

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectA Design Studio
EngineerNitinkumar Mohanlal Jain
Chartered AccountantCA Kunal Jhamvar
PartnerRole in project
Earnest and Shah Ventures-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 30 Sep 2019
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 13 Feb 2019
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 13 Feb 2019
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 13 Feb 2019Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 1 Aug 2023

Documents filed124

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 124 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5.pdf5 Nov 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: 5 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23).pdf27 Oct 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Ar Certifcate.pdf18 Aug 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Eng Certificate.pdf18 Aug 2023
Certificates of CA (Form 3)File: CA Certificate.pdf18 Aug 2023
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: A Building Occupancy Certificate.pdf1 Aug 2023
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: B Building Occupancy Certificate.pdf4 Jul 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Ar Certifcate.pdf8 May 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineers Certificate.pdf8 May 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2A.pdf8 May 2023
Certificates of CA (Form 3)File: CA Certificate.pdf8 May 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1.pdf3 Feb 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate - Dec 2022.pdf1 Feb 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form2 - Dec 2022.pdf1 Feb 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Form 2A Dec 2019.pdf1 Feb 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Form 2A March 2020.pdf1 Feb 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Quality Certificate form 2A.pdf1 Feb 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Form 2 -Mar 19.pdf1 Feb 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: RERA Form 2A Dec 2020.pdf1 Feb 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2A Certificate.pdf1 Feb 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2A.pdf1 Feb 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2 -June 22.pdf1 Feb 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2A -Sep 22.pdf1 Feb 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2A -Dec 22.pdf1 Feb 2023
Certificates of CA (Form 3)File: RERA CA cerificate - BW.pdf1 Feb 2023
Certificates of CA (Form 3)File: CA Certificate Form3.pdf1 Feb 2023
Certificates of CA (Form 3)File: RERA CA Certificate - Form 3 - Mar 2020.pdf1 Feb 2023
Certificates of CA (Form 3)File: Form 3.pdf1 Feb 2023
Certificates of CA (Form 3)File: RERA Form 3 Dec 2020.pdf1 Feb 2023
Certificates of CA (Form 3)File: Form 3 CA Certificate.pdf1 Feb 2023
Certificates of CA (Form 3)File: Form 3 CA RERA Certificate.pdf1 Feb 2023
Certificates of CA (Form 3)File: Form 3 - Dec 2022.pdf1 Feb 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineers Certificate Phase-III.pdf31 Jan 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf31 Jan 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineers Certificate March 2020.pdf31 Jan 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineers Certificate Form 2.pdf31 Jan 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineers Certificate Form-2.pdf31 Jan 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineers Certificate Form-2.pdf31 Jan 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf31 Jan 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engg Certificate.pdf31 Jan 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Engineers Certificate Form 2.pdf31 Jan 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: RERA Form 5 2018-19.pdf31 Jan 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architecture_Cretificate.pdf30 Jan 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Ar Certificate.pdf30 Jan 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate March 2020.pdf30 Jan 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate March 2020.pdf30 Jan 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architects Certificate.pdf30 Jan 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate Mar 21.pdf30 Jan 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate.pdf30 Jan 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2A.pdf19 Jan 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2A.pdf19 Jan 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form2A quality Certificate.pdf19 Jan 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2A.pdf19 Jan 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5.pdf17 Dec 2022
Disclosure of sold/ booked inventoryFile: DISCLOSURE OF SOLD-BOOKED INVENTORY A-BLD.pdf31 Oct 2022
Disclosure of sold/ booked inventoryFile: DISCLOSURE OF SOLD-BOOKED INVENTORY B-BLD.pdf31 Oct 2022
Disclosure of sold/ booked inventoryFile: DISCLOSURE OF SOLD-BOOKED INVENTORY C-BLD.pdf31 Oct 2022
Status of Formation of Legal Entity (Society/Co Op etc.)File: AP III Society Registration For Certificate.pdf31 Oct 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate.pdf21 Oct 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineers Cert.pdf21 Oct 2022
Certificates of CA (Form 3)File: CA Certificate.pdf21 Oct 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate.pdf3 Aug 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: RERA Engineers Certificate June22.pdf3 Aug 2022
Certificates of CA (Form 3)File: Form 3.pdf3 Aug 2022
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: C Building Occupancy Certificate.pdf4 May 2022
Certificates of CA (Form 3)File: Form 3.pdf3 Feb 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate.pdf1 Feb 2022
Certificates of CA (Form 3)File: CA Certificate Sept 21.pdf9 Nov 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: RERA Architect Certificate Sept 21.pdf2 Nov 2021
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineers Certificate Sept 21.pdf2 Nov 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Form 2A.pdf2 Nov 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Aayush Park 3 Form 5-compressed.pdf30 Sep 2021
Declaration about Commencement CertificateFile: DECLARATION ABOUT COMMENCEMNT CERTIFICATE.pdf13 Sep 2021
Declaration about Commencement CertificateFile: DISCLOSURE OF SOLD-BOOKED INVENTORY B-BLD.pdf30 Aug 2021
Disclosure of sold/ booked inventoryFile: DISCLOSURE OF SOLD-BOOKED INVENTORY A-BLD.pdf30 Aug 2021
Disclosure of sold/ booked inventoryFile: DISCLOSURE OF SOLD-BOOKED INVENTORY B-BLD.pdf30 Aug 2021
Disclosure of sold/ booked inventoryFile: DISCLOSURE OF SOLD-BOOKED INVENTORY C-BLD.pdf30 Aug 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form2A quality Certificate.pdf6 Aug 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architech Certificate June 21.pdf5 Aug 2021
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineers Certificate Jun-21.pdf5 Aug 2021

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 delivered late
ProjectLocationFlatsStatusPromisedDelivered
Aayush Park - IIVarale Gaon Talegaon Dabhade Pune - 410507337CompletedOct 2018Late, Dec 2018

How this compares with Pune

26%of Pune projects moved their completion datethis one has not
26%of Pune registrations have lapsed or been cancelledthis one is among them

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Aayush Park - III on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Katvi13,700+ in Pune

2 kmAayush Park - IIICompleted 38Lapsed / revoked 35Other 39Dot size: filed unitsN

Filed coordinates, straight-line distance. 112 registered projects within 2 km.

Builder: Earnest and Shah Ventures

Earnest and Shah Ventures has 4 registrations on MahaRERA, including Aayush Park II and Aayush Business Square. Its filings disclose 1 earlier MahaRERA project: declares 0 of 1 past projects completed on time. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What does it mean that Aayush Park - III shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if Aayush Park - III is delayed beyond 30 Dec 2024?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Aayush Park - III?

The registered promoter entity is Earnest and Shah Ventures, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Aayush Park - III?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Aayush Park - III?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Aayush Park - III?

The professionals named in the filing: Architect: A Design Studio; Engineer: Nitinkumar Mohanlal Jain; Chartered Accountant: CA Kunal Jhamvar. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Aayush Park - III?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Aayush Park - III. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Aayush Park - III to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.