ReraGenieLog inGet a buyer report

Home / Browse projects / Gandhinagar, Gujarat / AAVALI NINE 360

Valid until 31 Dec 2025 Residential/Group Housing project

AAVALI NINE 360

By SHAH ZIL

RG-GJ-64473 · RERA PR/GJ/GANDHINAGAR/GANDHINAGAR/Others/RAA11137/030123 · Last updated on GujRERA portal: 13 Aug 2025

Source: official GujRERA filing

Red flags

  • No red flags in this filing

Clear

  • Completion date never moved
Dec 2025Possession promisedno revision filed
6 of 18Construction stages doneacross 2 buildings; furthest along: Internal walls, 99%
24 of 54Units unsoldnot recorded sold or booked
Jump to the 44 documents Report an error

AAVALI NINE 360 is a Residential/Group Housing project by SHAH ZIL in Gandhinagar, Gujarat, registered with GujRERA as PR/GJ/GANDHINAGAR/GANDHINAGAR/Others/RAA11137/030123 on 3 Jan 2023. Possession is promised by 31 Dec 2025. 30 of the 54 units on this registration are recorded sold or booked, and 6 of 18 construction stages are filed complete.

At a glance

Project

  • NameAAVALI NINE 360
  • TypeResidential/Group Housing
  • Location
    • S.R No-22/2
    • Opp. Sheeji Villa
    • Nr. Manilal Party Plot
    • Tapovan Circle
    • Motera
    • Gandhinagar
  • PincodeNot stated
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/GANDHINAGAR/GANDHINAGAR/Others/RAA11137/030123
  • ReraGenie IDRG-GJ-64473

Builder

  • NameSHAH ZIL
  • Entity typeIndividual/Propritorship

Key dates

this monthRegisteredJan 2023PromisedDec 2025

Key facts

Registration and timeline

  • StatusValid until 31 Dec 2025
  • Registered on3 Jan 2023
  • Promised completion31 Dec 2025
  • Revised completionNone
  • Buildings2 building records
  • Documents filed44 files

Current status

56%30 of 54 units booked
90.0%Of the estimated cost spent so far

Figures as on 13 Aug 2025, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Block-A---27027
Block-B---27027

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building2

As on 13 Aug 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

6 of 18 construction stages are filed complete across 2 buildings. The stage furthest along is Internal walls, at 99%.

Block-A96%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth97%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats99%
Sanitary fittings within the flats97%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks97%
External plumbing and external plaster, elevation, completion of terraces with waterproofing97%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing80%
Block-B96%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth97%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats99%
Sanitary fittings within the flats96%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks96%
External plumbing and external plaster, elevation, completion of terraces with waterproofing97%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing80%

Progress on shared amenities19

As on 13 Aug 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsYes100%
Water supplyYes100%
Sewerage (chamber, lines, septic tank, STP)Yes100%
Storm water drainsNoNot applicable
Landscaping and tree plantingYes100%
Street lightingYes100%
Community buildingsYes0%
Treatment and disposal of sewage and sullage waterNoNot applicable
Solid waste management and disposalNoNot applicable
Water conservation, rain water harvestingYes0%
Energy managementNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Fire fightingYes0%
Drinking water facilitiesYes0%
Emergency evacuationYes0%
Use of renewable energyYes0%
SecurityYes0%
Letter boxYes0%

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area1,810 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountNot declared
Estimated costRs 18.50 cr
Cost incurredRs 16.65 cr
Spent of the estimate90.0%
BuildingWingEstimatedIncurred
Block-ANARs 9.25 crRs 8.32 cr
Block-BNARs 9.25 crRs 8.32 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectArpit R Shah
EngineerPCUBE CONSULTANTS

Documents filed44

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/GANDHINAGAR/GANDHINAGAR/Others/RAA11137/030123 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Accountant's certificate (Form 3)13 Aug 2025
Architect's certificate (Form 1)11 Aug 2025
Site photograph, Block-A7 Aug 2025
Site photograph, Block-A7 Aug 2025
Site photograph, Block-B7 Aug 2025
Engineer's certificate (Form 2)1 Oct 2024
Engineer's certificate annexure1 Oct 2024
RERA registration certificate3 Jan 2023
Proforma agreement for sale-
Auditor's report (1 of 3)-
Auditor's report (2 of 3)-
Auditor's report (3 of 3)-
Income tax return (1 of 3)-
Income tax return (2 of 3)-
Income tax return (3 of 3)-
Project specific document-
Directors' report (1 of 3)-
Directors' report (2 of 3)-
Directors' report (3 of 3)-
Commencement certificate-
Approved sanctioned plan-
Approved layout plan-
Agreement-
Land location-
Encumbrance certificate-
Area development document-
Proforma allotment letter-
Brochure-
Project related document-
Declaration in Form B-
Title clearance certificate-
Title report-
Property card-
Project photograph-
Proforma sale deed-
Audited balance sheet (1 of 3)-
Audited balance sheet (2 of 3)-
Audited balance sheet (3 of 3)-
Audited profit and loss statement (1 of 3)-
Audited profit and loss statement (2 of 3)-
Audited profit and loss statement (3 of 3)-
Cash flow statement (1 of 3)-
Cash flow statement (2 of 3)-
Cash flow statement (3 of 3)-

How this compares with Gandhinagar

56%of this project is bookeddistrict median 53%
16%of Gandhinagar projects moved their completion datethis one has not

Computed across the 1,600+ Gandhinagar projects on ReraGenie, from their own filings.

Keep AAVALI NINE 360 on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Gandhinagar1,600+ in Gandhinagar

2 kmAAVALI NINE 360Other 64Dot size: filed unitsN

Filed coordinates, straight-line distance. 64 registered projects within 2 km.

Builder: SHAH ZIL

SHAH ZIL has 1 registration on GujRERA, including AAVALI NINE 360. Read the full track record. See more projects on the Gandhinagar district page.

Frequently asked questions

What are my rights if AAVALI NINE 360 is delayed beyond 31 Dec 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of AAVALI NINE 360?

The registered promoter entity is SHAH ZIL, an individual/propritorship as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in AAVALI NINE 360?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at AAVALI NINE 360?

The professionals named in the filing: Architect: Arpit R Shah; Engineer: PCUBE CONSULTANTS. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in AAVALI NINE 360?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About AAVALI NINE 360. Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save AAVALI NINE 360 to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.