Home / Browse projects / Nagpur, Maharashtra / Aashray Township
Aashray Township
By Veeplus Arcades Private Limited
RG-MH-02695 · RERA P50500027062 · Last updated on MahaRERA portal: 2 Jul 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Possession 1 months past the filed date
- Completion date moved by 48 months
- 1 extension taken
Clear
- No litigation declared
- No complaints on record
- No encumbrance on the project land
- Separate project account declared
- Allotment letter follows the model form
3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Nagpur registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
Aashray Township is a Mixed project by Veeplus Arcades Private Limited in Nagpur, Maharashtra, registered with MahaRERA as P50500027062 on 13 Nov 2020. Possession was promised by 30 Sep 2026 and is now 1 months past that date. The completion date has moved by 48 months from the original filing. 32 of the 59 units on this registration are recorded sold or booked, and 24 of 297 construction stages are filed complete.
At a glance
Project
- NameAashray Township
- TypeMixed
- Location
- Kh no .202
- Mauza Persodi
- Umred (Rural)
- Umred
- Nagpur
- 441203
- Pincode441203
- MapView location on Google Maps (as filed on RERA)
- RERA no.P50500027062
- ReraGenie IDRG-MH-02695
Builder
- NameVeeplus Arcades Private Limited
- Entity typeCompany
- DirectorsBhupal Damodhar Ramteke, Madhuri Sanjay Bhiogade
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on13 Nov 2020
- Promised completion30 Sep 2026
- Revised completionRevised to 30 Sep 2026 (originally 30 Sep 2022)
- Buildings27 building records
- Documents filed70 files
Current status
Figures as on 2 Jul 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| Building No 9 | NA | 3 | 1 | 1 | 0 | 1 |
| Building No 10 | NA | 3 | 1 | 1 | 0 | 1 |
| Building No 11 | NA | 3 | 1 | 1 | 0 | 1 |
| Building No 12 | NA | 3 | 1 | 1 | 0 | 1 |
| Building No 13 | NA | 3 | 1 | 1 | 0 | 1 |
| Building No 14 | NA | 3 | 1 | 1 | 0 | 1 |
| Building No 17 | NA | 3 | 1 | 1 | 0 | 1 |
| Building No 18 | NA | 4 | 1 | 1 | 0 | 1 |
| Building No 19 | NA | 4 | 1 | 1 | 0 | 1 |
| Building No 20 | NA | 3 | 1 | 1 | 0 | 1 |
| Building No 21 | NA | 3 | 1 | 1 | 0 | 1 |
| Building No 26 | NA | 3 | 1 | 1 | 0 | 1 |
| Building No 27 | NA | 3 | 1 | 1 | 0 | 1 |
| Building No 28 | NA | 3 | 1 | 1 | 0 | 1 |
| Building No 29 | NA | 3 | 1 | 1 | 0 | 1 |
| Building No 35 | NA | 3 | 1 | 1 | 0 | 1 |
| Building No 36 | NA | 3 | 1 | 1 | 0 | 1 |
| Building No 49 | NA | 3 | 1 | 1 | 0 | 1 |
| Building No 50 | NA | 3 | 1 | 1 | 0 | 1 |
| Building No 51 | NA | 3 | 1 | 1 | 0 | 1 |
| Building No 52 | NA | 3 | 1 | 1 | 0 | 1 |
| Building No 41 | NA | 3 | 1 | 2 | 0 | 2 |
| Building No 42 | NA | 3 | 1 | 2 | 0 | 2 |
| Building No 43 | NA | 3 | 1 | 2 | 0 | 2 |
| Building No 44 | NA | 3 | 1 | 2 | 0 | 2 |
| Building No 45 | NA | 3 | 1 | 2 | 0 | 2 |
| Building No 46 | NA | 3 | 1 | 2 | 0 | 2 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building20
As on 2 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection. The count above covers all 28 buildings; the table lists the first 20.
24 of 297 construction stages are filed complete across 28 buildings. The stage furthest along is Internal walls, at 80%.
Building No 90%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Building No 100%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Building No 110%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Building No 120%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Building No 130%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Building No 140%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Building No 170%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Building No 180%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Building No 190%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Building No 200%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Building No 210%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Building No 260%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Building No 270%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Building No 280%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Building No 290%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Building No 350%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Building No 360%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Building No 4949%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 80% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 80% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 80% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Building No 5049%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 80% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 80% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 80% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Building No 5149%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 80% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 80% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 80% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Progress on shared amenities15
As on 2 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 90% |
| Water Supply | Yes | 30% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | No | Not applicable |
| Storm Water Drains | No | Not applicable |
| Landscaping & Tree Planting | No | Not applicable |
| Street Lighting | No | Not applicable |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | No | Not applicable |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | No | Not applicable |
| Electrical meter room, sub-station, receiving station | No | Not applicable |
| Aggregate area of recreational Open Space | Yes | 0% |
| Open Parking | Yes | 0% |
Parking filed38
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Closed/Covered | Open Space | Total |
|---|---|---|---|
| Building No 18 | 1 | 0 | 1 |
| Building No 19 | 1 | 0 | 1 |
| Building No 41 | 0 | 6 | 6 |
| Building No 42 | 0 | 6 | 6 |
| Building No 43 | 0 | 6 | 6 |
| Building No 44 | 0 | 6 | 6 |
| Building No 45 | 0 | 6 | 6 |
| Building No 46 | 0 | 6 | 6 |
Land and ownership1
MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.
| Landowner | Village | District |
|---|---|---|
| Veeplus Arcades Private Limited | Umred (Rural) | Nagpur |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| - | NA | Rs 4.07 cr | Rs 96.00 lakh |
Certifying professionals and partners7
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Pankaj Kriplani |
| Architect | SARANG AGRAWAL |
| Engineer | Sajid Ansari |
| Engineer | AYUSH LONARE |
| Chartered Accountant | Ruchi Mendiretta |
| Chartered Accountant | HETAL SAMPAT |
| Chartered Accountant | ASHISH AGARWAL |
| Partner | Role in project |
|---|---|
| Veeplus Arcades Private Limited | - |
Extensions applied for1
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterThe project was approved in November 2020. Immediately thereafter second wave of Covid-19 pandemic hampered the operations. Neither construction activity nor marketing activity could be carried out during this period. This has led to delay of the project.
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 8 Sep 2020 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 8 Sep 2020 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 8 Sep 2020 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 8 Sep 2020Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot on the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
Documents filed70
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Withdrawal Update Form 1File: Form 1 Architect Certificate March 26.pdf | 2 Jul 2026 |
| Withdrawal Update Form 2File: Form 2 Engineer Certificate March 26.pdf | 2 Jul 2026 |
| Withdrawal Update Form 3File: Form 3 CA Certificate March 26.pdf | 2 Jul 2026 |
| Form 2A (FY 2024-2025)File: Form- 2A FY 2024-25.pdf | 24 Jun 2026 |
| Form 2A (FY 2023-2024)File: Form 2A FY 23-24.pdf | 24 Jun 2026 |
| Form 2A (FY 2022-2023)File: Form 2A FY 22-23.pdf | 24 Jun 2026 |
| Form 5 (FY 2023-2024)File: FORM 5 VEEPLUS FY 23-24.pdf | 2 Apr 2026 |
| Form 5 (FY 2024-2025)File: FORM 5 VEEPLUS FY 24-25.pdf | 2 Apr 2026 |
| Form 5 (FY 2022-2023)File: FORM 5 VEEPLUS FY 22-23.pdf | 1 Apr 2026 |
| Withdrawal Update Form 1File: Form 1 Architect Certificate June 2025.pdf | 31 Mar 2026 |
| Withdrawal Update Form 1File: Form 1 Architect Certificate Sept 2025.pdf | 31 Mar 2026 |
| Withdrawal Update Form 1File: Form 1 Architect Certificate Dec 2025.pdf | 31 Mar 2026 |
| Withdrawal Update Form 2File: Form 2 Engineer certificate June 2025.pdf | 31 Mar 2026 |
| Withdrawal Update Form 2File: Form 2 Engineer Certificate Sept 2025.pdf | 31 Mar 2026 |
| Withdrawal Update Form 2File: Engineer certificate Dec 2025 Veeplus (2).pdf | 31 Mar 2026 |
| Withdrawal Update Form 3File: Form 3 CA Certificate June 2025.pdf | 31 Mar 2026 |
| Withdrawal Update Form 3File: Form 3 CA Certificate Sept 2025.pdf | 31 Mar 2026 |
| Withdrawal Update Form 3File: Form 3 CA Certificate Dec 2025.pdf | 31 Mar 2026 |
| Form 1File: Form 1 Architect Certificate Sept 2023.pdf | 30 Mar 2026 |
| Form 2File: Engineer certificate Sept 2023 Veeplus.pdf | 30 Mar 2026 |
| Form 3File: Form 3 CA Certificate Sept 2023.pdf | 30 Mar 2026 |
| Disclosure of Sold and Booked InventoryFile: Sold and Booked Inventory Sept 2023.pdf | 30 Mar 2026 |
| Form 1File: Form 1 Architect Certificate Dec 2023.pdf | 30 Mar 2026 |
| Form 2File: Form 2 Engineer certificate Dec 2023.pdf | 30 Mar 2026 |
| Form 3File: Form 3 CA Certificate Dec 2023.pdf | 30 Mar 2026 |
| Disclosure of Sold and Booked InventoryFile: Sold and Booked Inventory Dec 2023.pdf | 30 Mar 2026 |
| Form 1File: Form 1 Architect Certificate March 2024.pdf | 30 Mar 2026 |
| Form 2File: Form 2 Engineer certificate March 2024.pdf | 30 Mar 2026 |
| Form 3File: Form 3 CA Certificate March 2024.pdf | 30 Mar 2026 |
| Disclosure of Sold and Booked InventoryFile: Sold and Booked Inventory March 2024.pdf | 30 Mar 2026 |
| Form 1File: Form 1 Architect Certificate June 2024.pdf | 30 Mar 2026 |
| Form 2File: Form 2 Engineer certificate June 2024.pdf | 30 Mar 2026 |
| Form 3File: Form 3 CA Certificate June 2024.pdf | 30 Mar 2026 |
| Disclosure of Sold and Booked InventoryFile: Sold and Booked Inventory June 2024.pdf | 30 Mar 2026 |
| Form 1File: Form 1 Architect Certificate Sept 2024.pdf | 30 Mar 2026 |
| Form 2File: Form 2 Engineer certificate Sept 2024.pdf | 30 Mar 2026 |
| Form 3File: Form 3 CA Certificate Sept 2024.pdf | 30 Mar 2026 |
| Disclosure of Sold and Booked InventoryFile: Sold and Booked Inventory Sept 2024.pdf | 30 Mar 2026 |
| Form 1File: Form 1 Architect Certificate Dec 2024.pdf | 30 Mar 2026 |
| Form 2File: Form 2 Engineer certificate Dec 2024.pdf | 30 Mar 2026 |
| Form 3File: Form 3 CA Certificate Dec 2024.pdf | 30 Mar 2026 |
| Disclosure of Sold and Booked InventoryFile: Sold and Booked Inventory Dec 2024.pdf | 30 Mar 2026 |
| Form 1File: Form 1 Architect Certificate March 2025.pdf | 30 Mar 2026 |
| Form 2File: Form 2 Engineer certificate March 2025.pdf | 30 Mar 2026 |
| Form 3File: Form 3 CA Certificate Mar 2025.pdf | 30 Mar 2026 |
| Disclosure of Sold and Booked InventoryFile: Sold and Booked Inventory Mar 2025.pdf | 30 Mar 2026 |
| Form 1File: Form 1 Architect Certificate March 2023.pdf | 29 Mar 2026 |
| Form 2File: Form 2 Engineer certificate March 2023.pdf | 29 Mar 2026 |
| Form 3File: Form 3 CA Certificate March 2023.pdf | 29 Mar 2026 |
| Disclosure of Sold and Booked InventoryFile: Sold and Booked Inventory March 2023.pdf | 29 Mar 2026 |
| Form 1File: Form 1 Architect Certificate June 2023.pdf | 29 Mar 2026 |
| Form 2File: Form 2 Engineer certificate June 2023.pdf | 29 Mar 2026 |
| Form 3File: Form 3 CA Certificate June 2023.pdf | 29 Mar 2026 |
| Disclosure of Sold and Booked InventoryFile: Sold and Booked Inventory June 2023.pdf | 29 Mar 2026 |
| Declaration about Commencement CertificateFile: DECLARATION.pdf | 28 Sep 2022 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: FORM - 2A.pdf | 28 Sep 2022 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: FORM 5 - 2021.pdf | 28 Sep 2022 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: FORM 5 - 2022.pdf | 28 Sep 2022 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: ca cerificate.pdf | 7 Nov 2020 |
| Layout approvalFile: LAYOUT PLAN-converted_compressed.pdf | 8 Sep 2020 |
| Building plan approval or NA orderFile: COMMENCEMENT CERTIFICATE.pdf | 8 Sep 2020 |
| Copy of the legal title reportFile: LEGAL OPINION_NEW_compressed.pdf | 8 Sep 2020 |
| Details of encumbrancesFile: NON-ENCUMBRANCE CERTIFICATE.pdf | 8 Sep 2020 |
| Copy of Layout Approval (in case of layout)File: LAYOUT PLAN-converted_compressed.pdf | 8 Sep 2020 |
| Building Plan Approval / NA Order for plotted developmentFile: COMMENCEMENT CERTIFICATE.pdf | 8 Sep 2020 |
| Commencement Certificates / NA Order for plotted developmentFile: COMMENCEMENT CERTIFICATE.pdf | 8 Sep 2020 |
| Declaration in FORM BFile: AFFIDAVIT CUM DECLARATION.pdf | 8 Sep 2020 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCHITECTS CERTIFICATE.pdf | 8 Sep 2020 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGINEERS CERTIFICATE.pdf | 8 Sep 2020 |
| Proforma of Allotment letterFile: Agreement for sale-converted.pdf | 8 Sep 2020 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Nagpur
Computed across the 2,800+ Nagpur projects on ReraGenie, from their own filings.
Free monthly report: Nagpur on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 3 conditions on this project's record read and explained, with the clear checks alongside
- Joined against every project registered within 2 km, which the RERA portal never shows together
- All 70 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep Aashray Township on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Mauza Persodi2,800+ in Nagpur
Filed coordinates, straight-line distance. 7 registered projects within 2 km.
ANAND SAGAR
SHRIRAM DEVELOPERS
Reyansh Residency
METRO REALITIES & INFRAVENTURES PVT LTD
METRO HOMES 2.0 Sector-1
LISHA YOGESH GANGWANI
REYANSH RESIDENCY-3
METRO REALITIES & INFRAVENTURES PVT LTD
SIDDHESH NAGAR - 2
METRO REALITIES & INFRAVENTURES PVT LTD
CHATRAPATI SHIVAJI NAGAR 2
VASANTA SHIVRAMJI DANGARE
See every Nagpur project, with the district possession charts
Builder: Veeplus Arcades Private Limited
Veeplus Arcades Private Limited has 1 registration on MahaRERA, including Aashray Township. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Nagpur district page.
Frequently asked questions
What are my rights if Aashray Township is delayed beyond 30 Sep 2026?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of Aashray Township?
The registered promoter entity is Veeplus Arcades Private Limited, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in Aashray Township?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for Aashray Township?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at Aashray Township?
The professionals named in the filing: Architect: Pankaj Kriplani; Architect: SARANG AGRAWAL; Engineer: Sajid Ansari; Engineer: AYUSH LONARE; Chartered Accountant: Ruchi Mendiretta; Chartered Accountant: HETAL SAMPAT. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Aashray Township?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback