ReraGenieLog inGet a buyer report

Home / Browse projects / Nashik, Maharashtra / AASHIYANA

Registered No litigation declared Others project

AASHIYANA

By SKYLINE AASHIYANA LLP

RG-MH-23409 · RERA P51600078721 · Last updated on MahaRERA portal: 6 Oct 2025

Source: official MahaRERA filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

Nothing adverse is on this record. The buyer report still reads the filed documents themselves, and places this filing against every project registered within 2 km.

See what the report covers Free either way: or have every new Nashik registration emailed to you, free during the pilot beta.
Jun 2028Possession promisedno revision filed
0 of 11Construction stages donefurthest along: Excavation, 0%
64 of 68Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 53 documents Report an error

AASHIYANA is a Others project by SKYLINE AASHIYANA LLP in Nashik, Maharashtra, registered with MahaRERA as P51600078721 on 7 Jan 2025. Possession is promised by 30 Jun 2028. 4 of the 68 units on this registration are recorded sold or booked, and 0 of 11 construction stages are filed complete.

At a glance

Project

  • NameAASHIYANA
  • TypeOthers
  • Location
    • NASHIK SHIWAR
    • NASHIK
    • Nashik (M Corp.)
    • 422001
  • Pincode422001
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51600078721
  • ReraGenie IDRG-MH-23409

Builder

  • NameSKYLINE AASHIYANA LLP
  • Entity typeOthers

Key dates

this monthRegisteredJan 2025PromisedJun 2028

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on7 Jan 2025
  • Promised completion30 Jun 2028
  • Revised completionNone
  • Buildings1 building record
  • Documents filed53 files

Current status

6%4 of 68 units booked
68.5%Work done, per cost certificate

Figures as on 6 Oct 2025, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
AASHIYANANA99531568

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 6 Oct 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

0 of 11 construction stages are filed complete. The stage furthest along is Excavation, at 0%.

AASHIYANA: 0% average across the applicable activities

ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 6 Oct 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingYes0%

Parking filed106

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots106
Closed/Covered1
Open Space105

Land and ownership

Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area1,188 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on16 Jan 2026

Approvals and building plan

Sanctioning authorityNASHIK MUNICIPAL CORPORATION
Permissible FSI4587.52
Proposed, not sanctioned4,588 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchHDFC BANK LTD GRD FLR MAHENDRA MEMORIAL CENTER S NO874 4B 8 PLOT NO7 VADALA PATHRDI RD BAPU BUNGLOW NASHIK MAHARASHTRA 422009
Estimated costRs 8.03 cr
Cost incurredRs 5.50 cr
Work done68.51%
BuildingWingEstimatedIncurred
AASHIYANANARs 7.50 crRs 5.50 cr
-NARs 52.82 lakh-

Certifying professionals and partners4

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectTHINKING SPACES
EngineerROHAN KIRAN GHUMARE
Chartered AccountantMIRZA KOTKAR AND CO
Chartered AccountantBHUSHAN BHARAT GOSAR
PartnerRole in project
SKYLINE AASHIYANA LLP-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 16 Oct 2024
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 16 Oct 2024
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 16 Oct 2024
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 16 Oct 2024Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 30 Jun 2028

Documents filed53

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 5 (FY 2024-2025)File: FORM_5_AASHIYANA_FY 2024-25.pdf6 Oct 2025
Other - LegalFile: 30 and 32 - 1.pdf20 Nov 2024
Other - LegalFile: 30 and 32 - 2.pdf20 Nov 2024
Other - LegalFile: 31 and 33 - 1.pdf20 Nov 2024
Other - LegalFile: 31 and 33 - 2.pdf20 Nov 2024
Other - LegalFile: 34 - 1.pdf20 Nov 2024
Other - LegalFile: 34 - 2.pdf20 Nov 2024
Other - TechnicalFile: Annexure A.pdf20 Nov 2024
Other - TechnicalFile: NMC Mail.pdf20 Nov 2024
Proforma of Agreement for saleFile: RERA - Draft -SHOP.pdf20 Nov 2024
Other - LegalFile: Final 7_12.pdf24 Oct 2024
Details of encumbrances concerned to FinanceFile: No encumbrance.pdf18 Oct 2024
Proforma of Allotment letterFile: Allotment Letter.pdf18 Oct 2024
CERSAI detailsFile: Cersai.pdf18 Oct 2024
Deviation Report with respect to Allotment letterFile: No deviation allotment.pdf18 Oct 2024
Details of encumbrances concerned to LegalFile: No encumbrance.pdf18 Oct 2024
Deviation Report with respect to model copy of AgreementFile: No deviation agreement.pdf18 Oct 2024
Proforma of Agreement for saleFile: RERA - Draft -FLAT.pdf18 Oct 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: Amjad.pdf18 Oct 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: Wasim.pdf18 Oct 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: Touseen.pdf18 Oct 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: Sumaiyya.pdf18 Oct 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: Samir.pdf18 Oct 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: Sameena.pdf18 Oct 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: Nilofer.pdf18 Oct 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: Lalmohammad.pdf18 Oct 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: Jamir.pdf18 Oct 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: Bashir.pdf18 Oct 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: Asif.pdf18 Oct 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: Ambadas.pdf18 Oct 2024
Disclosure for secured/unsecured finance availed for the projectFile: Secured unsecured.pdf18 Oct 2024
Building plan approvalFile: Bldg Plan Part 3.pdf16 Oct 2024
Building plan approvalFile: Bldg Plan Part 2.pdf16 Oct 2024
Building plan approvalFile: Bldg Plan Part 1 (1).pdf16 Oct 2024
Layout approvalFile: Bldg Plan Part 3.pdf16 Oct 2024
Layout approvalFile: Bldg Plan Part 2.pdf16 Oct 2024
Layout approvalFile: Bldg Plan Part 1 (1).pdf16 Oct 2024
PAN CardFile: SKYLINE PAN.pdf16 Oct 2024
Copy of the legal title reportFile: rera title search report.pdf16 Oct 2024
Copy of Layout Approval (in case of layout)File: Bldg Plan Part 1 (1).pdf16 Oct 2024
Copy of Layout Approval (in case of layout)File: Bldg Plan Part 2.pdf16 Oct 2024
Copy of Layout Approval (in case of layout)File: Bldg Plan Part 3.pdf16 Oct 2024
Declaration in FORM BFile: Form B.pdf16 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Skyline.pdf16 Oct 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Skyline Aashiyana Form 3.pdf16 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Skyline.pdf16 Oct 2024
Commencement Certificates / NA Order for plotted developmentFile: Aashiyana Commencement (1).pdf16 Oct 2024
Building Plan Approval / NA Order for plotted developmentFile: Bldg Plan Part 1 (1).pdf16 Oct 2024
Building Plan Approval / NA Order for plotted developmentFile: Bldg Plan Part 2.pdf16 Oct 2024
Building Plan Approval / NA Order for plotted developmentFile: Bldg Plan Part 3.pdf16 Oct 2024
Declaration about Commencement CertificateFile: Declaration_Format D.pdf16 Oct 2024
Declaration about all RERA Designated Bank Accounts (Format A)File: DECLARATIO SEPARATE BANK ACCOUNT.pdf16 Oct 2024
Letter from the bank regarding the opening of RERA Designated Bank Accounts (Format B)File: Format B.pdf16 Oct 2024

How this compares with Nashik

6%of this project is bookeddistrict median 17%
10%of Nashik projects moved their completion datethis one has not
19%of Nashik registrations have lapsed or been cancelledthis one is on the register

Computed across the 4,100+ Nashik projects on ReraGenie, from their own filings.

Free monthly report: Nashik on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep AASHIYANA on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near NASHIK4,100+ in Nashik

2 kmAASHIYANACompleted 76Lapsed / revoked 20Other 66Dot size: filed unitsN

Filed coordinates, straight-line distance. 162 registered projects within 2 km.

Builder: SKYLINE AASHIYANA LLP

SKYLINE AASHIYANA LLP has 1 registration on MahaRERA, including AASHIYANA. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Nashik district page.

Frequently asked questions

What are my rights if AASHIYANA is delayed beyond 30 Jun 2028?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of AASHIYANA?

The registered promoter entity is SKYLINE AASHIYANA LLP, an others as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in AASHIYANA?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for AASHIYANA?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at AASHIYANA?

The professionals named in the filing: Architect: THINKING SPACES; Engineer: ROHAN KIRAN GHUMARE; Chartered Accountant: MIRZA KOTKAR AND CO; Chartered Accountant: BHUSHAN BHARAT GOSAR. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in AASHIYANA?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About AASHIYANA. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save AASHIYANA to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.