Home / Browse projects / Mysore, Karnataka / aadiramenclave
aadiramenclave
By SRI.LAXMIDEVI TRADERS AND WORKS CONTRACTOR
RG-KA-72929 · RERA PRM/KA/RERA/1268/383/PR/030623/005964 · Last updated on RERA Karnataka portal: 25 May 2023
Source: official RERA Karnataka filing
Red flags
- No red flags in this filing
Clear
- No litigation declared
- No complaints on record
- Completion date never moved
- Separate project account declared
Saved.
aadiramenclave is a Plotted Development project by SRI.LAXMIDEVI TRADERS AND WORKS CONTRACTOR in Mysore, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1268/383/PR/030623/005964 on 3 Jun 2023. Possession is promised by 23 Jul 2023.
At a glance
Project
- Nameaadiramenclave
- TypePlotted Development
- Location
- Heggadadevana Kote
- Mysore
- PincodeNot stated
- RERA no.PRM/KA/RERA/1268/383/PR/030623/005964
- ReraGenie IDRG-KA-72929
Builder
- NameSRI.LAXMIDEVI TRADERS AND WORKS CONTRACTOR
- Entity typeProprietorship Firm
- GSTIN29AWYPS6377A1ZO
- Authorized SignatorySomashekara
Key dates
Key facts
Registration and timeline
- StatusRegistration approved
- Registered on3 Jun 2023
- Promised completion23 Jul 2023
- Revised completionNone
- BuildingsNot stated in filing
- Documents filed77 files
The full filing
Everything below is from the project's own RERA Karnataka filing, free to read.
Land and ownership4
This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
| Landowner | Village | District |
|---|---|---|
| S A Ramesh Babu | - | - |
| S A Ramesh Babu | - | - |
| S A Ramesh Babu | - | - |
| S A Ramesh Babu | - | - |
Project account and cost
70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Cost line | Estimated | Incurred |
|---|---|---|
| Estimated Cost of Construction as certified by Engineer | Rs 7.01 cr | - |
Certifying professionals and partners2
Certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Engineer | S Nagesha Rao |
| Chartered Accountant | Manju k |
Complaints filed with RERA Karnataka
No complaints on record against this registration.
Documents filed77
As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PRM/KA/RERA/1268/383/PR/030623/005964 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Electricity NOCFile: Electricity Noc.pdf | 25 May 2023 |
| KSPCB NOCFile: KSPCB Consent.pdf | 25 May 2023 |
| Electricity NOCFile: Electricity Noc.pdf | 19 May 2023 |
| Site listFile: Somshekara Rera Site Details.xlsx | 19 May 2023 |
| Upload title deed full extent of syno 116 and title deed for syno 115/1,117File: Sargur layout katha.pdf | 21 Mar 2023 |
| Advocate search reportFile: Legal Openion.pdf | 21 Mar 2023 |
| Individual plot Size, Dimension and Area not matching with the layout planFile: Somshekara Rera Site Details.xlsx | 21 Mar 2023 |
| KSPCB CFEFile: KPCB_organized.pdf | 21 Mar 2023 |
| Cost of construction for civil works (Summary of civil works) certified by the EngineerFile: Engineer certificate.pdf | 21 Mar 2023 |
| Proforma of Agreement for saleFile: AOS.pdf | 21 Mar 2023 |
| Proforma of Allotment letterFile: Allottment letter.pdf | 21 Mar 2023 |
| Section 3(1) notarized affidavitFile: sec 3 affidavit.pdf | 21 Mar 2023 |
| NOC issued by CESCOMFile: Electricity.pdf | 21 Mar 2023 |
| Water sourceFile: Water Board.pdf | 21 Mar 2023 |
| Title deed Sy No.117File: sale deed 117.pdf | 21 Mar 2023 |
| Reply letterFile: reply letter.pdf | 21 Mar 2023 |
| FY 2019-20File: FY 2019-20.pdf | 19 Jan 2023 |
| FY 2020-21File: FY 2020-21.pdf | 19 Jan 2023 |
| FY 2021-22File: FY 2021-22.pdf | 19 Jan 2023 |
| CA certificateFile: CA certificate.pdf | 19 Jan 2023 |
| Engineer certificateFile: Engineer certificate.pdf | 19 Jan 2023 |
| Sale deed SY No 116File: Sale Deed Survey No116.pdf | 19 Jan 2023 |
| Sale deed Sy No 48File: Sale Deed Survey No 48 Sargur.pdf | 19 Jan 2023 |
| Partition deedFile: Partition Deed Sargur_compressed.pdf | 19 Jan 2023 |
| Relesae deedFile: Release Deed Sargur_compressed.pdf | 19 Jan 2023 |
| Project specificationFile: project specifications.pdf | 19 Jan 2023 |
| Reply letterFile: reply letter.pdf | 19 Jan 2023 |
| profit and loss account and balance sheet, 2019-20 ,2020-21 & 2021-22File: income tax 20-21.pdf | 13 Dec 2022 |
| profit and loss account and balance sheet, 2019-20 ,2020-21 & 2021-22File: income tax 19-20.pdf | 13 Dec 2022 |
| profit and loss account and balance sheet, 2019-20 ,2020-21 & 2021-22File: Income tax 21-22.pdf | 13 Dec 2022 |
| Partition deedFile: Partition Deed Sargur_compressed.pdf | 13 Dec 2022 |
| Relesae deedFile: Release Deed Sargur_compressed.pdf | 13 Dec 2022 |
| sale deed SyNo.48File: Sale Deed Survey No 48 Sargur.pdf | 13 Dec 2022 |
| Sale deed Sy no.116File: Sale Deed Survey No116.pdf | 13 Dec 2022 |
| JDA from land owner to promoter firm nameFile: JDA.pdf | 13 Dec 2022 |
| notarized form b in rera prescribed formatFile: form b somashekara.pdf | 13 Dec 2022 |
| Non litigation affidavit & Joint affidavitFile: Joint affidavit and Non litigation.pdf | 13 Dec 2022 |
| Guidance value by sub registrarFile: Guidance Value.pdf | 13 Dec 2022 |
| Relinquishment deedFile: Deed of relinquishment.pdf | 13 Dec 2022 |
| NOC issued by CESCOM.File: Electricity Receipts.pdf | 13 Dec 2022 |
| Water Supply NOCFile: Water Board Approval.pdf | 13 Dec 2022 |
| Reply letterFile: reply letter.pdf | 13 Dec 2022 |
| RTC, survey 48 | - |
| Mutation, survey 48 | - |
| Encumbrance Certificate, survey 48 | - |
| Conversion/Alienation Order, survey 48 | - |
| Khatha, survey 48 | - |
| RTC, survey 115/1 | - |
| Mutation, survey 115/1 | - |
| Encumbrance Certificate, survey 115/1 | - |
| Conversion/Alienation Order, survey 115/1 | - |
| Khatha, survey 115/1 | - |
| RTC, survey 116 | - |
| Mutation, survey 116 | - |
| Encumbrance Certificate, survey 116 | - |
| Conversion/Alienation Order, survey 116 | - |
| Khatha, survey 116 | - |
| RTC, survey 117 | - |
| Mutation, survey 117 | - |
| Encumbrance Certificate, survey 117 | - |
| Conversion/Alienation Order, survey 117 | - |
| Khatha, survey 117 | - |
| Registration CertificateFile: GST CERTIFICATE.pdf | - |
| Project Chartered Accountant | - |
| Project Engineer | - |
| Balance Sheet 2020 - 2021File: BS 2020-21.pdf | - |
| Audited Profit and Loss Statement 2020 - 2021File: PL 2020-21.pdf | - |
| Income Tax Return Acknowledgement 2020 - 2021File: ITR 2020-21.pdf | - |
| Work Order | - |
| Electricity Receipts | - |
| Water Board Approval | - |
| Layout Plan | - |
| Layout Plan | - |
| Layout Plan | - |
| Layout Plan | - |
| JDA | - |
| Plot Excel SheetFile: Somshekara Rera Site Details.xlsx | - |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Mysore
Computed across the 700+ Mysore projects on ReraGenie, from their own filings.
Keep aadiramenclave on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Mysore700+ in Mysore
Construction of 2446 Dus at Mandakalli Mysore
MCC
Construction of 1440 houses at lalithadripura
City Corporation Myuru
Construction of 843 G+2 Houses
Chief Officer
JAL VAYU TOWERS
AIR FORCE NAVAL HOUSING BOARD
Sanaklp Temple Tree
Sankalp Constructions private limited
SANKALP CROWN PHASE 1
SANKALP CONSTRUCTIONS PRIVATE LIMITED
See every Mysore project, with the district possession charts
Builder: SRI.LAXMIDEVI TRADERS AND WORKS CONTRACTOR
SRI.LAXMIDEVI TRADERS AND WORKS CONTRACTOR has 1 registration on RERA Karnataka, including aadiramenclave. Its filings disclose no earlier RERA Karnataka projects. Read the full track record. See more projects on the Mysore district page.
Frequently asked questions
What are my rights if aadiramenclave is delayed beyond 23 Jul 2023?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.
How do I verify and contact the developer of aadiramenclave?
The registered promoter entity is SRI.LAXMIDEVI TRADERS AND WORKS CONTRACTOR, a proprietorship firm as per the filing. Its GSTIN 29AWYPS6377A1ZO can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.
Is my payment protected in aadiramenclave?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
Who certifies construction progress at aadiramenclave?
The professionals named in the filing: Engineer: S Nagesha Rao; Chartered Accountant: Manju k. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in aadiramenclave?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.
Report an error Share feedback