Home / Browse projects / Mumbai Suburban, Maharashtra / 4810 Heights

Registered No litigation declared Residential / Group Housing project

4810 Heights

By Urvi Realtors

RG-MH-99333 · RERA P51800008732 · Last updated on MahaRERA portal: 21 Aug 2026

Source: official MahaRERA filing

Red flags

  • 7 complaints at MahaRERA
  • Completion date moved by 96 months
  • 5 extensions taken

Clear

  • No litigation declared
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Dec 2027Possession promisedmoved 96 months from the original
4 of 11Construction stages donefurthest along: Slabs of Super Structure, 89%
38 of 164Units unsoldnot recorded sold or booked
7Complaints at MahaRERAon this registration
Jump to the 99 documents Report an error

4810 Heights is a Residential / Group Housing project by Urvi Realtors in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800008732 on 19 Aug 2017. Possession is promised by 31 Dec 2027. The completion date has moved by 96 months from the original filing. 126 of the 164 units on this registration are recorded sold or booked, and 4 of 11 construction stages are filed complete. 7 complaints are on record with the regulator.

At a glance

Project

  • Name4810 Heights
  • TypeResidential / Group Housing
  • Location
    • ASHOKVAN
    • Borivali East
    • Borivali
    • Mumbai Suburban
    • 400066
  • Pincode400066
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51800008732
  • ReraGenie IDRG-MH-99333

Builder

  • NameUrvi Realtors
  • Entity typePartnership
  • PartnerShantilal V Gala

Key dates

this monthRegisteredAug 2017First promiseDec 2019Revised toDec 2027

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on19 Aug 2017
  • Promised completion31 Dec 2027
  • Revised completionRevised to 31 Dec 2027 (originally 31 Dec 2019)
  • Buildings1 building record
  • Documents filed99 files

Current status

77%126 of 164 units booked
70.0%Work done, per cost certificate

Figures as on 21 Aug 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
4810 HeightsNA1911640164

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 21 Aug 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

4 of 11 construction stages are filed complete. The stage furthest along is Slabs of Super Structure, at 89%.

4810 Heights: 82% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure89%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises89%
Sanitary Fittings within the flats / premises80%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks89%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.89%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.67%

Progress on shared amenities15

As on 21 Aug 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes67%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes67%
Storm Water DrainsYes80%
Landscaping & Tree PlantingNoNot applicable
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes67%
Electrical meter room, sub-station, receiving stationYes90%
Aggregate area of recreational Open SpaceYes0%
Open ParkingYes100%

Parking filed47

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots47
Closed/Covered41
Open Space6

Land and ownership1

MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area5,225 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on11 Oct 2025
LandownerVillageDistrict
Right Channel Constructions Pvt LtdBorivaliMumbai Suburban

Approvals and building plan

Sanctioning authoritySlum Rehabilation Authority
Permissible FSI7891.27
Proposed, not sanctioned6,625 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchCTS No 341, SANGEETA, SHOP NO 1 and 2, S V ROAD, KANDIVALI WEST MUMBAI 400067
Estimated costRs 31.75 cr
Cost incurredRs 22.23 cr
Work done70.0%
BuildingWingEstimatedIncurred
4810 HeightsNARs 31.75 crRs 22.23 cr

Certifying professionals and partners5

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSanjay Neve
EngineerH M Raje
Chartered AccountantParag Ashwin Gudhkha
Chartered AccountantR K AM & Associate
Chartered AccountantAshish Sinha
PartnerRole in project
Urvi Realtors-

Extensions applied for5

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51800005400Dec 2019 → Dec 2020

Reason as filed by the promoterDear Sir, We hereby apply for the extension of project and renewal of the registration of the following project: 4810 Heights CTS No.2330 A/1/2 at, Borivali, Mumbai Suburban District. Though, we have tried our best to complete the project within the defined deadline, however, due to unavoidable circumstances in relation with the availability of the sufficient funds to complete the project, we seek an extension for the project for the period of 1 year from the date of completion as registered with the authority. To the best of our knowledge and efforts, we strongly believe that within this exte

EXT51800011210Dec 2019 → Dec 2022

Reason as filed by the promotercovid 19

EXT51800013159Dec 2019 → Dec 2023

Reason as filed by the promoterDear Sir, Due to multiple factors like delay in receiving further CC from the concern authorities in the past before implication of RERA, the project got delayed. However, post RERA implication, factors like pending approval of further CC from authority, financial crisis due to demonetization & GST implication etc. affected the project development. However, we have received the mandatory consent from our buyers on mutual ground to allow us to complete the project within the required extension of 1 year. Kindly consider the same and grant us the extension. Thanking you

EXT51800019388Dec 2019 → Dec 2024

Reason as filed by the promoterThis is a project initiated by a joint venture company before enforcementnt of Rera. Due to certain finafinancially inappropriate circumstances, the project got delayed. Currently, the construction is near to completion, however, we are still struggling to manage the required funds to get the completion certificate. Our existing buyers are aware of the circumstances and are supportive in the process. We are trying our best to hand over the project to its buyers at the earliest. We have taken the consent from our buyers for the extension as attached. Please grant us the extension.

EA20122518875Dec 2019 → Dec 2027

Reason as filed by the promoterThe delay in completion of the project is due to delays in obtaining necessary approvals and clearances from MCGM, unforeseen technical challenges during execution, and shortage of labour arising from external market conditions. These factors were beyond our control. However, continuous efforts have been made to expedite construction by streamlining approvals, resolving technical issues, and augmenting manpower, and all possible steps are being taken to complete the project at the earliest.

Complaints filed with MahaRERA7

Case no.ComplainantRespondentFiled
CC006000000056135Mrs Jayshree Arvind DholakiaRight Channel Constructions Private Ltd29/12/2018
CC006000000023456Devang KakkadRight Channel Constructions Pvt Ltd, Urvi Realtors, Shri Sanjay Hanumanprasad Pandey26/02/2018
CC006000000023517Bharati KakkadRight Channel Construction Pvt Ltd, Urvi Realtors, Shri Sanjay Hanumanprasad Pandey,26/02/2018
CC006000000192460Devang KakkadUrvi Realtors22/02/2020
CC006000000192718Bharti KakkadUrvi Realtors22/02/2020
CC006000000023858Nishant S. ShirkeRight Channel Constructions Private Limited23/03/2018
CC006000000161243Sharad Fakir DayalM/s. Right Channel Constructions Pvt Ltd13/10/2019

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 31 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 31 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 31 Jul 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 2 Jan 2024Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2027

Documents filed99

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 99 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Form 1 July to September UR.pdf21 Aug 2026
Withdrawal Update Form 1File: Form 1 Jan to March UR.pdf21 Aug 2026
Withdrawal Update Form 2File: FORM 2 URVI REALTORS January to March (1).pdf21 Aug 2026
Withdrawal Update Form 2File: FORM 2 URVI REALTORS January to March (1).pdf21 Aug 2026
Withdrawal Update Form 3File: Form 3 July to September.pdf21 Aug 2026
Withdrawal Update Form 3File: Form 3 Jan 26 to March 26.pdf21 Aug 2026
Withdrawal Update Form 1File: Form 1 April to June 2026 UR.pdf19 Aug 2026
Withdrawal Update Form 1File: Form 1 Jan to March UR.pdf19 Aug 2026
Withdrawal Update Form 1File: Form 1 October to December UR.pdf19 Aug 2026
Withdrawal Update Form 1File: Form 1 April to June 2026 UR.pdf19 Aug 2026
Withdrawal Update Form 1File: Form 1 April to June UR.pdf19 Aug 2026
Withdrawal Update Form 1File: Form 1 July to September UR.pdf19 Aug 2026
Withdrawal Update Form 2File: FORM 2 URVI REALTORS APRIL TO JUNE.pdf19 Aug 2026
Withdrawal Update Form 2File: FORM 2 URVI REALTORS APRIL TO JUNE.pdf19 Aug 2026
Withdrawal Update Form 2File: FORM-2 October to December.pdf19 Aug 2026
Withdrawal Update Form 2File: FORM 2 URVI REALTORS APRIL TO JUNE 2026.pdf19 Aug 2026
Withdrawal Update Form 2File: FORM 2 URVI REALTORS APRIL TO JUNE.pdf19 Aug 2026
Withdrawal Update Form 2File: FORM 2 URVI REALTORS July TO September (1).pdf19 Aug 2026
Withdrawal Update Form 3File: Form 3 April 26 to June 26.pdf19 Aug 2026
Withdrawal Update Form 3File: Form 3 Jan 26 to March 26.pdf19 Aug 2026
Withdrawal Update Form 3File: Form 3 Oct 25 to Dec 25.pdf19 Aug 2026
Withdrawal Update Form 3File: Form 3 April 26 to June 26.pdf19 Aug 2026
Withdrawal Update Form 3File: Form 3 April to June.pdf19 Aug 2026
Withdrawal Update Form 3File: Form 3 July to September.pdf19 Aug 2026
Withdrawal Update Form 1File: Form 1 April to June.pdf4 Aug 2026
Withdrawal Update Form 1File: Jul 25 - Sep 25.pdf4 Aug 2026
Withdrawal Update Form 1File: Form 1 October to December.pdf4 Aug 2026
Withdrawal Update Form 1File: Form 1 Jan to March.pdf4 Aug 2026
Withdrawal Update Form 1File: Form 1 April to June.pdf4 Aug 2026
Withdrawal Update Form 2File: FORM 2 URVI REALTORS APRIL TO JUNE.pdf4 Aug 2026
Withdrawal Update Form 2File: FORM 2 URVI REALTORS July TO September.pdf4 Aug 2026
Withdrawal Update Form 2File: FORM-2 October to December.pdf4 Aug 2026
Withdrawal Update Form 2File: FORM 2 URVI REALTORS January to March.pdf4 Aug 2026
Withdrawal Update Form 2File: FORM 2 URVI REALTORS APRIL TO JUNE.pdf4 Aug 2026
Withdrawal Update Form 3File: Apr 25 - Jun 25.pdf4 Aug 2026
Withdrawal Update Form 3File: Jul 25 - Sep 25.pdf4 Aug 2026
Withdrawal Update Form 3File: Form 3 October to December.pdf4 Aug 2026
Withdrawal Update Form 3File: Jan 26 - Mar 26.pdf4 Aug 2026
Withdrawal Update Form 3File: Apr 25 - Jun 25.pdf4 Aug 2026
Disclosure of sold/ booked inventoryFile: Sold Booked Inventory.pdf13 Mar 2024
Certificates of CA (Form 3)File: FORM 3 FY 2022-23.pdf8 Jan 2024
Other - LegalFile: No Legal Litigation and No Financial Encumbrances.pdf4 Jan 2024
Other - FinanceFile: No Legal Litigation and No Financial Encumbrances.pdf4 Jan 2024
Commencement Certificates / NA Order for plotted developmentFile: Further Commencement Certificate_ Dated 29 June 2022.pdf2 Jan 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A Engineers Quality Certificate_FY 2022-2023.pdf2 Jan 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: FORM 5 FY 2022-23 URVI REALTORS.pdf2 Jan 2024
Declaration about Commencement CertificateFile: Format D.pdf14 May 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form-1 16 01 23.pdf14 May 2023
Disclosure of sold/ booked inventoryFile: 05 Disclosure of Sold Booked Inventory 26-04-2023.pdf14 May 2023
Certificates of CA (Form 3)File: 03_FORM 3_CA_Urvi.pdf14 May 2023
Certificates of CA (Form 3)File: RC_Form-3_Mar 2023.pdf14 May 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 DIMPLE BHAVSAR RERA URVI.pdf29 Mar 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: FORM 2A DIMPLE BHAVSAR RERA URVI.pdf29 Mar 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: From 5 Till 31-03-2022.pdf29 Mar 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form - 2_27-02-2023.pdf27 Feb 2023
Deviation Report with respect to Allotment letterFile: DEVIATION REPORT ALLOTMENT LETTER.pdf26 Feb 2023
Deviation Report with respect to model copy of AgreementFile: DEVIATION REPORT AFS.pdf26 Feb 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: ANNEXURE A Interest in other projects.pdf22 Feb 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Architect Certificate 16_01_2023.pdf17 Feb 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: FORM 2A_2023.pdf17 Feb 2023
Disclosure of sold/ booked inventoryFile: 4810_sold_Booked_inventory_31_01_2022_Right channel.pdf17 Feb 2023
Disclosure of sold/ booked inventoryFile: 4810_SOLD_BOOKED_INVENTORY_22_12_2022_Urvi.pdf17 Feb 2023
Certificates of CA (Form 3)File: FORM 3 CA CERTIFICATE_2022_Right Channel_compressed (1).pdf17 Feb 2023
Certificates of CA (Form 3)File: FORM 3 FY 2021-22 URVI REALTORS MAHARERA PARGBHAI_compressed.pdf17 Feb 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: FORM 5 URVI REALTORS RERA FY 2021-22.pdf17 Feb 2023
Declaration about Commencement CertificateFile: Declaration_About_CC_Forma-D_20-12-2022.pdf5 Jan 2023
Details of encumbrances concerned to FinanceFile: DECLARATION OF ENCUMBRANCE TO LEGAL.pdf23 Dec 2022
Details of encumbrances concerned to LegalFile: DECLARATION OF ENCUMBRANCE TO LEGAL.pdf23 Dec 2022
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: SEPARATE BANK ACC DETAILS FORMAT - A.pdf23 Dec 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2A_2021-22.pdf19 Dec 2022
CERSAI detailsFile: CERSAI_Search_Report_200255199160_For_Asset_Based_Search_19_12_2022_15_18_19_045 (1).pdf19 Dec 2022
Proforma of Agreement for saleFile: 4_updated_AFS.pdf19 Dec 2022
Declaration about Commencement CertificateFile: 32 Declaration about commencement Certificate.pdf18 Jun 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Form 2A Quality Assurance Certificate.pdf18 Jun 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2A Quality Assurance Certificate.pdf18 Jun 2022
Disclosure of sold/ booked inventoryFile: 29 Sold Booked Inventory.pdf18 Jun 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: FORM 5 ANNUAL REPORT CA FY 2018-2019.pdf18 Jun 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: FORM 5 Annual Report CA FY 2019-2020 RCC.pdf18 Jun 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: FORM 5 ANNUAL REPORT CA FY 2019-2020.pdf18 Jun 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: FORM 5 Annual Report CA FY 2020-2021 RCC.pdf18 Jun 2022

How this compares with Mumbai Suburban

77%of this project is bookeddistrict median 30%
33%of Mumbai Suburban projects moved their completion datethis one moved by 96 months
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is on the register

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep 4810 Heights on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Borivali East6,700+ in Mumbai Suburban

2 km4810 HeightsCompleted 65Lapsed / revoked 45Other 106Dot size: filed unitsN

Filed coordinates, straight-line distance. 216 registered projects within 2 km.

Builder: Urvi Realtors

Urvi Realtors has 1 registration on MahaRERA, including 4810 Heights. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What are my rights if 4810 Heights is delayed beyond 31 Dec 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of 4810 Heights?

The registered promoter entity is Urvi Realtors, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in 4810 Heights?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against 4810 Heights?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for 4810 Heights?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at 4810 Heights?

The professionals named in the filing: Architect: Sanjay Neve; Engineer: H M Raje; Chartered Accountant: Parag Ashwin Gudhkha; Chartered Accountant: R K AM & Associate; Chartered Accountant: Ashish Sinha. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in 4810 Heights?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About 4810 Heights. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save 4810 Heights to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.