ReraGenieLog inGet a buyer report

Home / Browse projects / Mumbai Suburban, Maharashtra / 25 West -A (East)Wing

Registered Litigation declared Residential / Group Housing project

25 West -A (East)Wing

By 25 West Realty Private Limited

RG-MH-29233 · RERA P51800028736 · Last updated on MahaRERA portal: 5 May 2026

Source: official MahaRERA filing

Red flags

  • Litigation declared, 6 cases
  • 5 complaints at MahaRERA

Clear

  • Completion date never moved
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Jun 2032Possession promisedno revision filed
5 of 11Construction stages donefurthest along: Slabs of Super Structure, 52%
30 of 65Units unsoldnot recorded sold or booked
5Complaints at MahaRERAon this registration
Jump to the 131 documents Report an error

25 West -A (East)Wing is a Residential / Group Housing project by 25 West Realty Private Limited in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800028736 on 30 Mar 2021. Possession is promised by 30 Jun 2032. 35 of the 65 units on this registration are recorded sold or booked, and 5 of 11 construction stages are filed complete. 5 complaints are on record with the regulator.

At a glance

Project

  • Name25 West -A (East)Wing
  • TypeResidential / Group Housing
  • Location
    • Mount Mary Hill
    • Bandra (West)
    • Andheri
    • Mumbai Suburban
    • 400050
  • Pincode400050
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51800028736
  • ReraGenie IDRG-MH-29233

Builder

  • Name25 West Realty Private Limited
  • Entity typeCompany
  • DirectorsRajesh Laxmikant Babladi, Pandharinath Maloji Thakur

Key dates

this monthRegisteredMar 2021PromisedJun 2032

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on30 Mar 2021
  • Promised completion30 Jun 2032
  • Revised completionNone
  • Buildings1 building record
  • Documents filed131 files

Current status

54%35 of 65 units booked
28.6%Work done, per cost certificate

Figures as on 5 May 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
SKairos East WingNA252365065

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 5 May 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

5 of 11 construction stages are filed complete. The stage furthest along is Slabs of Super Structure, at 52%.

SKairos East Wing: 50% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure52%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 5 May 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed221

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots221
Closed/Covered221

Land and ownership1

MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area1,100 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on30 Aug 2025
LandownerVillageDistrict
NHP Realty LLPAndheriMumbai Suburban

Approvals and building plan

Sanctioning authorityMCGM
Permissible FSI18553.81
Proposed, not sanctioned16,124 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchVile Parle East
Estimated costRs 277.77 cr
Cost incurredRs 79.43 cr
Work done28.6%
BuildingWingEstimatedIncurred
SKairos East WingNARs 257.89 crRs 79.29 cr
-NARs 19.88 crRs 14.03 lakh

Certifying professionals and partners6

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectMaya Vaidya
EngineerRAJEEVAN PARAMBAN
EngineerArvind Prayag Gupta
Chartered AccountantAmit Sheth
Chartered AccountantSANKET SHAH
Chartered AccountantDhiraj K Rathod
PartnerRole in project
25 West Realty Private Limited-

Litigation declared6

CaseCourtStatus
304/2019HIGH COURTDisposed
12078/2019HIGH COURTPending for withdrawal
443/2018CITY CIVIL COURTDisposed
444/2018CITY CIVIL COURTDisposed
11351/2019HIGH COURTPending for withdrawal
11357/2019HIGH COURTDisposed

Complaints filed with MahaRERA5

Case no.ComplainantRespondentFiled
CC006000000251351AVDHARNA INFRASTRUCTURE PRIVATE LIMITEDMEENA H AJWANI08/06/2022
CC006000000302895AVDHARNA INFRASTRUCTURE PRIVATE LIMITEDVishal Haribhawan Ajwani01/10/2022
CC1260276525 West Realty Private LimitedAparna Padgaonkar12/05/2026
CC1260313725 West Realty Private LimitedMr Nitin Vaidya26/05/2026
CC1260313825 West Realty Private LimitedMr Ninad Vaidya26/05/2026

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 26 Oct 2023
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 10 Aug 2023
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 16 Mar 2024
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 9 Mar 2024Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 30 Jun 2032

Documents filed131

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 131 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: FORM I Form _ I 25 west.pdf5 May 2026
Withdrawal Update Form 1File: FORM - I P51800028736 - 25 West ( Wing - A).pdf5 May 2026
Withdrawal Update Form 2File: FORM - II Engineers Certificate - 25 West.pdf5 May 2026
Withdrawal Update Form 2File: FORM - II Engineers Certificate -25 West- Dec 25.pdf5 May 2026
Withdrawal Update Form 3File: FORM - III Certification Of Form III 25 West Dec25.pdf5 May 2026
Withdrawal Update Form 3File: FORM - III Certification Of Form III 25 West Dec25.pdf5 May 2026
Withdrawal Update Form 1File: FORM I Form _ I 25 west.pdf4 May 2026
Withdrawal Update Form 2File: FORM - II Engineers Certificate - 25 West.pdf4 May 2026
Withdrawal Update Form 3File: Form III (Mar 26) SIGNED - 25 West -A (East) Wing.pdf4 May 2026
Withdrawal Update Form 1File: 25 West_ Architects certificate (1).pdf15 Nov 2025
Withdrawal Update Form 2File: Engineers Certificate - Sep 25 - 25 West East wing (1).pdf15 Nov 2025
Withdrawal Update Form 3File: Form III_25West.pdf15 Nov 2025
Form 5 (FY 2024-2025)File: 25 WEST.pdf4 Oct 2025
Form 5 (FY 2023-2024)File: 25 WEST.pdf4 Oct 2025
Form 1File: Arch Certificate_25 West_June 25.pdf20 Aug 2025
Form 2File: Engg Certificate - 25 West_June 25.pdf20 Aug 2025
Form 3File: CA Certificate_25 West_June 25.pdf20 Aug 2025
Disclosure of Sold and Booked InventoryFile: Disclosure of sold - 25 West_June 25.pdf20 Aug 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: P51800028736 - 25 West ( Wing - A).pdf19 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineers Certificate - Mount mary - Dec 24.pdf4 Feb 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM III - Sep 24_25 WEST REALTY.pdf31 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Arch Certificate_25 West_Dec 24 (1).pdf15 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 25 WEST_FORM III_JUNE 24 (2).pdf10 Dec 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form III_Sep 24_25 WEST_A(East) wing.pdf10 Dec 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGINEERS CERTIFICATE JUN 24 (2).pdf10 Dec 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineers Certificate -25 west Sep 24 (1).pdf10 Dec 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: P51800028736 - 25 West ( Wing - A).pdf16 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: P51800028736 - 25 West ( Wing - A) (3).pdf23 Jul 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGINEERS CERTIFICATE Mount mary March 24.pdf11 Jun 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 25 WEST A_Form III_March 24.pdf6 Jun 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Mount mary (1).pdf9 May 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: P51800028736 - 25 WEST.pdf22 Apr 2024
Building plan approvalFile: 15-MT MARY AMENDED APPROVAL PLAN-23-MAY-2022_11zon.pdf16 Mar 2024
Building plan approvalFile: MT MARY_SALE_AMENDED LETTER (Arch)-6TH-MAR-2024 (1).pdf16 Mar 2024
Building Plan Approval / NA Order for plotted developmentFile: 15-MT MARY AMENDED APPROVAL PLAN-23-MAY-2022_11zon.pdf16 Mar 2024
Building Plan Approval / NA Order for plotted developmentFile: MT MARY_SALE_AMENDED LETTER (Arch)-6TH-MAR-2024 (1).pdf16 Mar 2024
Commencement Certificates / NA Order for plotted developmentFile: MT MARY SALE CC UPTO 1st to 13th flr for RCC 14th to 16th of Wing-A-06TH-MAR-2024.pdf9 Mar 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: P51800028736 - 25 WEST.pdf7 Feb 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: CERTIFICATE 25 WEST.pdf7 Feb 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM III_SKAIROS_DEC 23 (1).pdf7 Feb 2024
Commencement Certificates / NA Order for plotted developmentFile: CC revalidation_mount mary.pdf22 Dec 2023
Details of encumbrances concerned to FinanceFile: Legal Encumbrance.pdf27 Oct 2023
Details of encumbrances concerned to LegalFile: Legal Encumbrance.pdf27 Oct 2023
Commencement Certificates / NA Order for plotted developmentFile: Revalidation of CC.pdf27 Oct 2023
Declaration about Commencement CertificateFile: DECLARATION (1).pdf27 Oct 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 25 West.pdf27 Oct 2023
CERSAI detailsFile: CERSAI_Search_Report_200284714137_For_Asset_Based_Search_26_10_2023_13_53_07_406.pdf27 Oct 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosure of interest_Rajesh Babladi (1).pdf27 Oct 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosure of interest _ P M Thakur.pdf27 Oct 2023
Proforma of Agreement for saleFile: AFS for RERA upload 27102023_compressed.pdf27 Oct 2023
Proforma of Allotment letterFile: Allotment Letter draft.pdf27 Oct 2023
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Seperate Bank letter.pdf27 Oct 2023
OtherFile: Consent _ 25 West A wing.pdf27 Oct 2023
PAN CardFile: PAN Card_25 West.pdf26 Oct 2023
Copy of the legal title reportFile: New title report_compressed.pdf26 Oct 2023
Commencement Certificates / NA Order for plotted developmentFile: ilovepdf_merged (6).pdf26 Oct 2023
Declaration in FORM BFile: Affidavit cum declaration 25 west.pdf26 Oct 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Quality Certificate form 2A.pdf26 Oct 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: New Form I_25 West.pdf23 Oct 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engg Certificate_Sept 23_25 West A wing_page-0001 (1).pdf23 Oct 2023
Disclosure of sold/ booked inventoryFile: Disclousre of sold unsold_25 West A wing.pdf23 Oct 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Skarios Form III_Sept 23_compressed.pdf23 Oct 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineers certificate - Shairose - Jun 23 (2).pdf21 Oct 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2A_QA Certificate_Skairos_Mar 22.pdf21 Oct 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM III (SKAIROS)_June 23 (1).pdf21 Oct 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: FORM 5 (25 WEST) (3).pdf21 Oct 2023
Building plan approvalFile: 03-MT MARY AMENDED APPROVAL PLAN-23-MAY-2022_compressed.pdf30 Aug 2023
Building Plan Approval / NA Order for plotted developmentFile: 03-MT MARY AMENDED APPROVAL PLAN-23-MAY-2022_compressed.pdf30 Aug 2023
Layout approvalFile: LAYOUT APPROVAL_Plan_compressed.pdf10 Aug 2023
Copy of Layout Approval (in case of layout)File: LAYOUT APPROVAL_Plan_compressed.pdf10 Aug 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGINEERS CERTIFICATE - SKAIROSE.pdf24 Jul 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: P51800028736 - MOUNT MARY.pdf20 Jul 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: SKAIROS FORM 3 MAR-23.pdf20 Jul 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Mount Mary Form 2A.pdf10 Jul 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: P51800028736 - MOUNT MARY.pdf10 Apr 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form III Dec 22_Skairos.pdf10 Apr 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineers Certificate Jun 22 - Skairos.pdf9 Feb 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGINEER CERTIFICATE SEP 22 - MOUNT MARY (1).pdf9 Feb 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2A_QA Certificate_Skairos_Mar 22.pdf23 Jan 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Skairos_FORM-5_March 22.pdf16 Jan 2023

How this compares with Mumbai Suburban

54%of this project is bookeddistrict median 30%
33%of Mumbai Suburban projects moved their completion datethis one has not
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is on the register

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep 25 West -A (East)Wing on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Bandra (West)6,700+ in Mumbai Suburban

2 km25 West -A (East)WingCompleted 31Lapsed / revoked 17Other 36Dot size: filed unitsN

Filed coordinates, straight-line distance. 84 registered projects within 2 km.

Builder: 25 West Realty Private Limited

25 West Realty Private Limited has 1 registration on MahaRERA, including 25 West -A (East)Wing. Its filings disclose no earlier MahaRERA projects. Litigation is declared on 1 of its registrations. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What are my rights if 25 West -A (East)Wing is delayed beyond 30 Jun 2032?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of 25 West -A (East)Wing?

The registered promoter entity is 25 West Realty Private Limited, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in 25 West -A (East)Wing?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against 25 West -A (East)Wing?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for 25 West -A (East)Wing?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at 25 West -A (East)Wing?

The professionals named in the filing: Architect: Maya Vaidya; Engineer: RAJEEVAN PARAMBAN; Engineer: Arvind Prayag Gupta; Chartered Accountant: Amit Sheth; Chartered Accountant: SANKET SHAH; Chartered Accountant: Dhiraj K Rathod. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in 25 West -A (East)Wing?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; how the declared litigation on this registration affects your risk; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About 25 West -A (East)Wing. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save 25 West -A (East)Wing to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.