Home / Browse projects / Raigarh, Maharashtra / 21 ENCLAVE

Registered No litigation declared Residential / Group Housing project

21 ENCLAVE

By Pushpam Infra LLP

RG-MH-85000 · RERA P52000045327 · Last updated on MahaRERA portal: 19 Sep 2026

Source: official MahaRERA filing

Red flags

  • Completion date moved by 22 months
  • 3 extensions taken

Clear

  • No litigation declared
  • No complaints on record
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Raigarh registration emailed to you, free during the pilot beta.
Oct 2027Possession promisedmoved 22 months from the original
1 of 11Construction stages doneacross 4 buildings; furthest along: Basement (if any), 0%
16 of 21Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 113 documents Report an error

21 ENCLAVE is a Residential / Group Housing project by Pushpam Infra LLP in Raigarh, Maharashtra, registered with MahaRERA as P52000045327 on 12 May 2022. Possession is promised by 30 Oct 2027. The completion date has moved by 22 months from the original filing. 5 of the 21 units on this registration are recorded sold or booked, and 1 of 11 construction stages are filed complete.

At a glance

Project

  • Name21 ENCLAVE
  • TypeResidential / Group Housing
  • Location
    • Murbad Road
    • Kashele
    • Karjat
    • Raigarh
    • 410201
  • Pincode410201
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52000045327
  • ReraGenie IDRG-MH-85000

Builder

  • NamePushpam Infra LLP
  • Entity typePartnership
  • GSTIN27AAQFP3028F1Z5
  • GSTIN is from this promoter's other MahaRERA registrations. This project's own filing does not repeat it.
  • PartnersShrikant Ashok Chopda, Ashok Dagduram Chopda, Sachin Ashok Chopda
  • Other registrations9 more →
  • Completed4 of 10
  • No longer live3 lapsed, de-registered or revoked

Key dates

this monthRegisteredMay 2022First promiseDec 2025Revised toOct 2027

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on12 May 2022
  • Promised completion30 Oct 2027
  • Revised completionRevised to 30 Oct 2027 (originally 31 Dec 2025)
  • Buildings4 building records
  • Documents filed113 files

Current status

24%5 of 21 units booked
26.5%Work done, per cost certificate

Figures as on 19 Sep 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
ENA22303
BNA22808
CNA22303
DNA22707

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building4

As on 19 Sep 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

1 of 11 construction stages are filed complete across 4 buildings. The stage furthest along is Basement (if any), at 0%.

E9%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
BNot stated
ActivityProgress
ExcavationNot applicable
Basement (if any)Not applicable
Podiums (if any)Not applicable
PlinthNot applicable
Stilt FloorNot applicable
Slabs of Super StructureNot applicable
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/PremisesNot applicable
Sanitary Fittings within the flats / premisesNot applicable
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water TanksNot applicable
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.Not applicable
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.Not applicable
CNot stated
ActivityProgress
ExcavationNot applicable
Basement (if any)Not applicable
Podiums (if any)Not applicable
PlinthNot applicable
Stilt FloorNot applicable
Slabs of Super StructureNot applicable
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/PremisesNot applicable
Sanitary Fittings within the flats / premisesNot applicable
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water TanksNot applicable
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.Not applicable
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.Not applicable
DNot stated
ActivityProgress
ExcavationNot applicable
Basement (if any)Not applicable
Podiums (if any)Not applicable
PlinthNot applicable
Stilt FloorNot applicable
Slabs of Super StructureNot applicable
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/PremisesNot applicable
Sanitary Fittings within the flats / premisesNot applicable
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water TanksNot applicable
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.Not applicable
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.Not applicable

Progress on shared amenities15

As on 19 Sep 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes90%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes90%
Street LightingYes0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingNoNot applicable
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceYes90%
Open ParkingYes0%

Parking filed22

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots22
Closed/Covered22
BuildingClosed/CoveredTotal
E33
B99
C33
D77

Land and ownership1

MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area4,804 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on18 Nov 2025
LandownerVillageDistrict
Prishanova RealityMumbai CityMumbai City

Approvals and building plan

Sanctioning authorityAlibaug Municipal Corporation, Raigad
Permissible FSI2871.2
Proposed, not sanctioned2,871 sq m
Buildings approved4
Buildings sanctioned4

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchGround floor 635/1B New Gajara Society Bibwewadi Pune 411037
Estimated costRs 20.00 cr
Cost incurredRs 5.30 cr
Work done26.5%
BuildingWingEstimatedIncurred
ENARs 4.50 crRs 80.00 lakh
BNARs 4.50 crRs 2.30 cr
CNARs 4.50 crRs 80.00 lakh
DNARs 4.50 crRs 80.00 lakh
-NARs 2.00 crRs 60.00 lakh

Certifying professionals and partners10

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectDivya Gore
ArchitectASHLESHA MULEY
EngineerSamjay Balai
EngineerNeel Shreekant Chopda
Chartered AccountantDeepika Bhattad
Chartered AccountantSachin K Mishra
Chartered AccountantSantvani and Associates
Chartered AccountantVIPIN KHOBRAGADE
Chartered AccountantNIKHIL BHUTADA
Chartered AccountantANURAG MEHERWAL
PartnerRole in project
Pushpam Infra LLP-

Extensions applied for3

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52000028405Dec 2025 → Jun 2026

Reason as filed by the promoterPlan revised

EA10062621300Dec 2025 → Jun 2027

Reason as filed by the promoterShortage of labour

P52000045327/WarDec 2025 → Oct 2027

Reason as filed by the promoterNA

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 25 Apr 2022
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 13 Aug 2024
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 13 Aug 2024
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 13 Aug 2024Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 30 Oct 2027

Documents filed113

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 113 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Form1 21enclave.pdf19 Sep 2026
Withdrawal Update Form 2File: Form-2 21Enclave.pdf19 Sep 2026
Withdrawal Update Form 3File: Form3- 21Enclave.pdf19 Sep 2026
Withdrawal Update Form 1File: FORM 1.pdf10 Jun 2026
Withdrawal Update Form 2File: FORM 2.pdf10 Jun 2026
Withdrawal Update Form 3File: FORM 3.pdf10 Jun 2026
Form 2A (FY 2025-2026)File: Form 2A.pdf10 Jun 2026
Form 5 (FY 2025-2026)File: FORM 5.pdf10 Jun 2026
Withdrawal Update Form 1File: Form1 21enclave.pdf27 Feb 2026
Withdrawal Update Form 2File: 21enclave engineer.pdf27 Feb 2026
Withdrawal Update Form 3File: 21enclave ca.pdf27 Feb 2026
Withdrawal Update Form 1File: 21enclave architect.pdf24 Nov 2025
Withdrawal Update Form 2File: 21enclave Engineer.pdf24 Nov 2025
Withdrawal Update Form 3File: 21enclave CA.pdf24 Nov 2025
Form 1File: FORM-1-21-ENCLAVE-30-06-2025.pdf21 Aug 2025
Form 2File: FORM -2 21-ENCLAVE-30-06-2025.pdf21 Aug 2025
Form 3File: FORM-3-21-ENCLAVE-30-06-2025.pdf21 Aug 2025
Disclosure of Sold and Booked InventoryFile: DISCLOSURE OF SOLD-UNSOLD INVENTARY-21-ENCLAVE -30-06-2025.pdf21 Aug 2025
Declaration in FORM BFile: Form B.pdf7 Jun 2025
Disclosure of sold/ booked inventoryFile: Disclosur of sold booked Inventory.pdf7 Jun 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 31122024.pdf4 Jun 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 31032025.pdf4 Jun 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 21 ENCALVE 31122024.pdf4 Jun 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 21 ENCLAVE 31032025.pdf4 Jun 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 31122024.pdf4 Jun 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 31032025.pdf4 Jun 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A 2024-25.pdf4 Jun 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2024-25)File: FORM 5 21 ENCLAVE 2024-25.pdf4 Jun 2025
Form 1File: FORM 1 31032025.pdf4 Jun 2025
Form 2File: Form 2 31032025.pdf4 Jun 2025
Form 3File: FORM 3 21 ENCLAVE 31032025.pdf4 Jun 2025
Declaration in FORM BFile: Affidavit Cum Declaration.pdf8 May 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 30062024.pdf3 Dec 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 30092024.pdf3 Dec 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 31032024.pdf3 Dec 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 31122023.pdf3 Dec 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 30092023.pdf3 Dec 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 30062023.pdf3 Dec 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 31032023.pdf3 Dec 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate_March-23.pdf26 Nov 2024
Disclosure of sold/ booked inventoryFile: Disclosure of Sold Booked Inventory_March 23.pdf9 Nov 2024
Disclosure of sold/ booked inventoryFile: Disclosure of Sold Booked Inventory_March 24.pdf9 Nov 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: RA 22-23.pdf9 Nov 2024
Disclosure of sold/ booked inventoryFile: 1 Sold Unsold Inventory June 23.pdf6 Nov 2024
Disclosure of sold/ booked inventoryFile: 2SoldUnsold InventorySept 23.pdf6 Nov 2024
Disclosure of sold/ booked inventoryFile: 3 Sold Unsold Inventory Dec 23.pdf6 Nov 2024
Disclosure of sold/ booked inventoryFile: 4 Sold Unsold Inventory March 24.pdf6 Nov 2024
Disclosure of sold/ booked inventoryFile: 5 Sold Unsold Inventory June 24.pdf6 Nov 2024
Disclosure of sold/ booked inventoryFile: 6 Sold Unsold Inventory Sept 24.pdf6 Nov 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: AR Certificate- Sep 23.pdf11 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: AR Certificate- Dec 23.pdf11 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: AR Certificate- Marh 24.pdf11 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: AR Certificate- June 24.pdf11 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: AR Certificate- Sep 24.pdf11 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: AR Certificate- June 23.pdf11 Oct 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate_Sept 2024.pdf11 Oct 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate_June 2024.pdf11 Oct 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate_Mar 2024.pdf11 Oct 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate_Dec 2023.pdf11 Oct 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate_Sept 2023.pdf11 Oct 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate_June 2023.pdf11 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ER Certificate- June 24.pdf11 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ER Certificate- Sep 24.pdf11 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ER Certificate- March 24.pdf11 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ER Certificate- Dec 23.pdf11 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ER Certificate- Sep 23.pdf11 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ER Certificate- June 23.pdf11 Oct 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: RERA Audit Report_23-24.pdf11 Oct 2024
Layout approvalFile: Sheet No-1 - converted.pdf13 Aug 2024
Building plan approvalFile: Sheet No-1 - converted.pdf13 Aug 2024
Building plan approvalFile: Sheet No-2 Building-B - converted.pdf13 Aug 2024
Building plan approvalFile: Sheet No-3 Building-D - converted.pdf13 Aug 2024
Building plan approvalFile: Sheet No-4 Building_C D - converted.pdf13 Aug 2024
Building plan approvalFile: Sheet No-1 - converted.pdf13 Aug 2024
Copy of Layout Approval (in case of layout)File: Sheet No-1 - converted.pdf13 Aug 2024
Building Plan Approval / NA Order for plotted developmentFile: Sheet No-1 - converted.pdf13 Aug 2024
Building Plan Approval / NA Order for plotted developmentFile: Sheet No-2 Building-B - converted.pdf13 Aug 2024
Building Plan Approval / NA Order for plotted developmentFile: Sheet No-3 Building-D - converted.pdf13 Aug 2024
Building Plan Approval / NA Order for plotted developmentFile: Sheet No-4 Building_C D - converted.pdf13 Aug 2024
Building Plan Approval / NA Order for plotted developmentFile: Sheet No-1 - converted.pdf13 Aug 2024

How this compares with Raigarh

24%of this project is bookeddistrict median 29%
20%of Raigarh projects moved their completion datethis one moved by 22 months
26%of Raigarh registrations have lapsed or been cancelledthis one is on the register

Computed across the 5,900+ Raigarh projects on ReraGenie, from their own filings.

Free monthly report: Navi Mumbai and Raigad on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep 21 ENCLAVE on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Kashele5,900+ in Raigarh

2 km21 ENCLAVECompleted 3Other 1Dot size: filed unitsN

Filed coordinates, straight-line distance. 4 registered projects within 2 km.

Builder: Pushpam Infra LLP

Pushpam Infra LLP has 10 registrations on MahaRERA, including Swapna Pushpa and Swapna Pushpa Phase II. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Raigarh district page.

Frequently asked questions

What are my rights if 21 ENCLAVE is delayed beyond 30 Oct 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of 21 ENCLAVE?

The registered promoter entity is Pushpam Infra LLP, a partnership as per the filing. Its GSTIN 27AAQFP3028F1Z5 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in 21 ENCLAVE?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for 21 ENCLAVE?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at 21 ENCLAVE?

The professionals named in the filing: Architect: Divya Gore; Architect: ASHLESHA MULEY; Engineer: Samjay Balai; Engineer: Neel Shreekant Chopda; Chartered Accountant: Deepika Bhattad; Chartered Accountant: Sachin K Mishra. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in 21 ENCLAVE?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About 21 ENCLAVE. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save 21 ENCLAVE to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.