NITIN DWARKADAS NYATI has 12 registrations on MahaRERA, including NYATI ELYSIA I and NYATI ETERNITY COMMERCIAL I. Its filings disclose 11 earlier MahaRERA projects: declares 10 of 11 past projects completed on time. Litigation is declared on 1 of its registrations.
Projects by this developer
Showing all 12 projects.
Largest first, by the unit count in the filing.
| Project | Location | Units | Booked | Registered | Status |
|---|---|---|---|---|---|
| NYATI EKAANT IP52100027858 | PUNE, Pune, 411041 | - | - | 10 Jan 2021 | Registration lapsed |
| NYATI ELITEP52100045651 | UNDRI VILLAGE, Pune, 411060 | - | - | 26 May 2022 | Completed |
| NYATI ELYSIA IP52100000860 | KHARADI, 411014 | - | - | 23 Jul 2017 | Completed |
| NYATI ELYSIA IIP52100018643 | KHARADI, 411014 | - | - | 22 Nov 2018 | Completed |
| NYATI ELYSIA IIIP52100021737 | KHARADI, 411014 | - | - | 22 Jul 2019 | Registration lapsed |
| NYATI ELYSIA IVP52100021738 | KHARADI, 411014 | - | - | 22 Jul 2019 | Completed |
| NYATI ELYSIA VP52100027025 | KHARADI, 411014 | - | - | 10 Nov 2020 | Completed |
| NYATI EMBRACE IP52100002290 | UNDRI, Pune, 411060 | - | - | 31 Jul 2017 | Completed |
| NYATI ETERNITY COMMERCIAL IP52100000954 | UNDRI, Pune, 411060 | - | - | 25 Jul 2017 | Completed |
| NYATI ETERNITY COMMERCIAL IIP52100021443 | AXIS BANK UNDRI, Pune, 411060 | - | - | 28 Jun 2019 | Completed |
| NYATI KALEIDOSCOPE IP52100017920 | KHARADI, 411014 | - | - | 25 Sep 2018 | Completed |
| NYATI KALEIDOSCOPE IIP52100018178 | KHARADI, 411014 | - | - | 12 Oct 2018 | Completed |
What this promoter declares as its own experience
NITIN DWARKADAS NYATI declares experience on 11 earlier projects. 8 of them carry a registration number we could match on MahaRERA, all under this promoter's own name.
8 of these declarations can be compared with the dates those projects' own registrations hold. Every one of them gives the same original completion date its registration holds. A completion date is also recorded against 1 registration MahaRERA does not show as completed. A registration lapses when a promoter files neither a completion nor an extension, so that can mean the completion was never filed rather than that the project was not finished.
From the promoter experience table each promoter files with MahaRERA, matched to the register by registration number. A declaration naming another promoter's project is a claim of involvement, and involvement takes several shapes: a parent and its project company, one firm re-registering under a second name, or a joint venture between two separate developers. We publish the claim as filed and do not treat it as proof that the entities are one builder.
Past projects, as disclosed in RERA filings
| Project | Promised completion | Actual completion | Delivery |
|---|---|---|---|
| Nyati Eternity I | 30 Jun 2016 | 23 Oct 2015 | On time |
| Nyati Eternity II | 30 Dec 2016 | 23 Jan 2017 | +1 months |
| Nyati Eternity IV | 31 Jan 2018 | 23 Jan 2017 | On time |
| NYATI KALEIDOSCOPE I P52100017920 | 31 Mar 2019 | 31 Mar 2019 | On time |
| NYATI KALEIDOSCOPE II P52100018178 | 31 Mar 2019 | 31 Mar 2019 | On time |
| NYATI ELYSIA I P52100000860 | 30 Mar 2022 | 30 Mar 2022 | On time |
| NYATI ELYSIA II P52100018643 | 30 Mar 2023 | 30 Mar 2023 | On time |
| NYATI ELYSIA III P52100021737 | 30 Mar 2023 | 30 Mar 2023 | On time |
| NYATI ELYSIA IV P52100021738 | 30 Sep 2023 | 30 Sep 2023 | On time |
| NYATI ELYSIA V P52100027025 | 30 Sep 2023 | 30 Sep 2023 | On time |
| NYATI ELITE P52100045651 | 30 Jun 2024 | 30 Jun 2024 | On time |
Frequently asked questions
How do I verify NITIN DWARKADAS NYATI as a legal entity before signing?
Your agreement for sale must name the exact entity registered for the project, not a group brand. The registration certificate on each project's MahaRERA page names the exact legal entity; ask for it if the sales office only uses a brand name. Large builders commonly register one company or LLP per project, which is normal; the entity on the registration certificate is the one legally accountable to you.
How should I use this delivery record when booking with NITIN DWARKADAS NYATI?
Their completed projects have landed on time so far, but apply the same test to the specific project: promised date, current progress, and sales pace. If possession then slips past your agreement date, section 18 entitles you to interest at SBI's highest MCLR plus 2 percent (currently 10.90% per annum) for every month of delay, or an exit with a full refund with interest.
Does the declared litigation make NITIN DWARKADAS NYATI unsafe to buy from?
Not by itself. Litigation on a registration ranges from a boundary dispute to an allottee case about delay; what matters is the case type, which court or forum, and whether it touches the land title of the project you are buying. The case list is in each project's filed documents. Treat litigation as a question to resolve in writing before booking, not as a verdict either way.