New projects and RERA data in Vadodara district, Gujarat
2908 projects are registered in Vadodara district: 297,375 units across them, 189 registered in the last 12 months. Sales and inventory trends accumulate from each future quarterly update; this page shows the first one.
Of the 2908 covered registrations, 679 have revised their promised completion date. Of the 2731 that file a booking figure, the median is 70% booked as of the current data. Every figure comes from the projects' own GujRERA filings.
How far Vadodara possession dates have moved
Builders may revise the possession date they filed at registration. Each bar is the year a project first promised, split by how far that date has since moved. 679 of 2,908 projects (23%) have moved at least once; the median move is 12 months and the longest is 87 months.
Kept the original dateMoved by under 2 yearsMoved by 2 years or more
Read down a bar to see how much of that year's cohort held its promise. Facts as per filings on RERA website.
Hatched years are ones where most builders never filed a flat count, so the bar understates the real total. Read down a bar to see how much of that year's cohort held its promise. Facts as per filings on RERA website.
Where in Vadodara: projects by taluka
2,908 of the 2,908 registrations on this page name their taluka.
| Taluka | Projects | Share |
|---|---|---|
| Vadodara | 2,742 | 94% |
| 7 other talukas | 166 | 6% |
Projects in Vadodara
Showing 1 to 60 of 2,908 projects.
Largest first, by the unit count in the filing.
| Project | Developer | Units | Booked | Registered | Status |
|---|---|---|---|---|---|
| PMAY, EWS, TP 28, FP 152/1+152/2, R.S.no.585/1 ATLADRA | VADODARA MUNICIPAL CORPORATION | 1980 | 0% | 26 May 2022 | Valid until 30 Apr 2028 |
| AGORA CITY CENTERSama, 390008 | MANAV INFRASTRUCTURE PRIVATE LIMITED | 1785 | 47% | 15 Nov 2017 | Valid until 30 Apr 2027 |
| 49 shops + 1560 EWS - II at Gorwa, Phase 5Gorva, 390016 | GUJARAT HOUSING BOARD | 1609 | 97% | 10 May 2019 | Valid until 31 Oct 2023 |
| PMAY-KHATAMBAKhatamba, 390025 | VADODARA URBAN DEVELOPMENT AUTHORITY | 1386 | 93% | 10 Apr 2018 | Valid until 14 Jun 2021 |
| Akshar PavilionGotri, 391101 | AKSHAR PHC REALCON | 1274 | 61% | 1 Feb 2018 | Valid until 25 Jul 2023 |
| NAZARBAUG PALACE PHASE-1Vadodara Kasba, 390006 | ONS BUILDTECH LLP | 1206 | 83% | 8 Jun 2018 | Valid until 30 Jun 2025 |
| AKSHAR CITYKelanpur, 390004 | AKSHAR BUILDERS | 1070 | 91% | 4 Apr 2018 | Valid until 31 Jul 2022 |
| SHYAMALCOUNTYAmodar, 390019 | SHREE GANESH INFRA | 1014 | 95% | 7 Apr 2018 | Valid until 25 Jun 2022 |
| SHYAMAL PARKVadodara, 390012 | SHREE GANESH INFRA HOMES | 990 | 58% | 14 Sep 2018 | Valid until 30 Jan 2027 |
| 440 LIG-II + 208 MIG-I + 208 MIG-II + 20 SHOPS AT PHASE-3, PACKAGE NO. 21, SAMTA , VADODARAGorwa, 390023 | GUJARAT HOUSING BOARD | 856 | - | 5 Sep 2018 | Valid until 31 Mar 2019 |
| VUDA PMAY BILL TP1FP67Bill | VADODARA URBAN DEVELOPMENT AUTHORITY | 756 | 100% | 21 Dec 2020 | Valid until 31 May 2024 |
| LIG SCHEME AT TP 60 FP 127 MMGYGotri, 391101 | VADODARA MUNICIPAL CORPORATION | 752 | 96% | 10 Oct 2018 | Valid until 30 Dec 2021 |
| 54 MIG-I + 334 LIG-II + 336 LIG-I +12 SHOPS at Plot-A, Phase-2, Package No.13Gorwa, 390023 | GUJARAT HOUSING BOARD | 736 | 97% | 24 Aug 2018 | Valid until 31 Oct 2019 |
| VANDE MATARAMVadsar, 390011 | Geeta Enterprise | 719 | 0% | 16 Jan 2025 | Valid until 31 Jul 2032 |
| Joyos Hubtown VadodaraTarsali, 390010 | HUBTOWN BUS TERMINAL (VADODARA) PRIVATE LIMITED | 713 | 52% | 6 Oct 2018 | Valid until 30 Dec 2022 |
| Survi Pristine | SURVI INFRASPACE LLP | 704 | 56% | 30 Sep 2022 | Valid until 30 Apr 2028 |
| SHREE SIDDHESHWAR HELENIUM | NYALKARAN SOURCE | 653 | 26% | 1 Sep 2023 | Valid until 1 Nov 2028 |
| AKSHAR AASHRAYWaghodia, 390019 | SHREE AKSHAR ENTERPRISE | 631 | 94% | 14 Sep 2018 | Valid until 30 Jun 2024 |
| SAMANVAY WESTFIELDS | SAMANVAY SPARSH | 625 | 72% | 20 Feb 2019 | Valid until 30 Jun 2023 |
| THE GOKULESH CITYJobantekri, 390004 | Gokulesh Infra | 622 | 87% | 11 Jul 2018 | Valid until 30 Jun 2021 |
| SAMANVAY STATUS 2Atladara, 391410 | Status Realty | 621 | 91% | 6 Oct 2017 | Valid until 31 Dec 2020 |
| SHYAMAL HEIGHTSAnkhol | RKP INVESTMENTS | 567 | 76% | 25 Oct 2019 | Valid until 18 Jan 2027 |
| PMAY BILL 532 EWS-II FP 38Bill, 391410 | VADODARA URBAN DEVELOPMENT AUTHORITY | 542 | 97% | 6 Dec 2019 | Valid until 7 Mar 2022 |
| SAMANVAY WESTBREEZEGotri, 390021 | SAMANVAY SPARSH | 542 | 73% | 2 Mar 2019 | Valid until 30 Jun 2023 |
| AATMIYA LANDMARKVadodara, 390014 | AATMIYA REALTY | 510 | 5% | 22 Nov 2018 | Valid until 30 Oct 2027 |
| THE KRISHNA CITYKelanpur, 390004 | KRISHNA DEVELOPERS | 510 | 71% | 20 Sep 2018 | Valid until 30 Jun 2025 |
| JV TRANSLIFENizampura, 390024 | KATIRA CONSTRUCTION LIMITED | 494 | 35% | 13 May 2019 | Valid until 30 Sep 2026 |
| LIG SCHEME TP 1 FP 145Harni, 390022 | VADODARA MUNICIPAL CORPORATION | 493 | 94% | 7 Sep 2018 | Valid until 30 Dec 2019 |
| PMAY-SEWASI-F.P.75Sevasi, 391101 | VADODARA URBAN DEVELOPMENT AUTHORITY | 491 | 91% | 10 Apr 2018 | Valid until 18 Nov 2020 |
| SIDDESHWAR THE BUSINESS HARBOURKapurai, 390025 | NYALKARAN INFRA | 488 | 43% | 16 Jan 2018 | Valid until 30 Dec 2021 |
| WINGS (TOWER A)Makarpura, 390014 | ONS BUILDTECH LLP | 486 | 34% | 5 Mar 2018 | Valid until 30 Jun 2019 |
| SHREE SIDDHESHWAR PARTHESHWAR | S P INFRASTRUCTURE | 483 | 84% | 28 Jan 2022 | Valid until 30 Apr 2027 |
| Samanvay SaptarshiVadodara Kasba, 390011 | Samanvay saptarshi | 482 | 97% | 11 Apr 2018 | Valid until 31 Dec 2019 |
| THE MARKBill, 391410 | SHREE GANESH DEVLOPERS | 482 | 89% | 4 Apr 2018 | Valid until 18 Feb 2022 |
| THE RISE PLAZATarsali, 390014 | THE DWARKESH INFRA | 474 | 28% | 26 Sep 2018 | Valid until 30 Oct 2027 |
| RUDRA HEIGHTSSAMA | CHARBHUJA DEVELOPERS | 472 | 31% | 3 Mar 2021 | Valid until 30 Apr 2027 |
| 19 Shops and 448 2 and 3 BHK Flats at Gorwa Phase 6 | GUJARAT HOUSING BOARD | 467 | 0% | 24 Mar 2023 | Valid until 30 Apr 2027 |
| AARYA EMPIREKalali, 390012 | SHIVAM INFRA | 466 | 81% | 11 Apr 2018 | Valid until 30 Jun 2022 |
| Star City ITandalja, 390012 | SAMANVAY SPARSH | 464 | 87% | 16 Sep 2019 | Valid until 30 Sep 2023 |
| PMAY BHAYLI TP1 FP122Bhayli | VADODARA URBAN DEVELOPMENT AUTHORITY | 461 | 97% | 2 Dec 2020 | Valid until 15 Nov 2023 |
| Broadway PrideSevasi, 391101 | ARIHANT INFRASTRUCTURE | 449 | 61% | 6 Jun 2018 | Valid until 30 Jun 2020 |
| SAMANVAY CAMPUSVADODARA KASBA | SAMANVAY HOMES | 447 | 45% | 27 Sep 2022 | Valid until 30 Apr 2027 |
| SHREE SIDDHESHWAR HABITATTarsali | NYALKARAN BUILDERS LLP | 444 | 98% | 13 Jan 2020 | Valid until 30 Jun 2025 |
| VAIKUNTHDHAM CO-OPERATIVE HOUSING SOCIETY LTD | VAIKUNTHDHAM CO OPERATIVE HOUSING SOCIETY LIMITED & Others | 443 | 70% | 7 Oct 2022 | Valid until 30 Oct 2027 |
| AAMRAPALI RESI-COMAtladara, 390012 | GAYATRI DEVELOPERS | 441 | 84% | 18 Sep 2018 | Valid until 30 Jun 2026 |
| DARSHANAM SELTOSASEVASI | DARSHANAM BUILDCON | 437 | 68% | 14 Dec 2020 | Valid until 31 Dec 2025 |
| Fortune prestige | Varniraj Infra | 436 | 49% | 11 Oct 2023 | Valid until 30 Jan 2029 |
| V R VIVANTA | DAXON REALTY LIMITED | 436 | 67% | 26 Oct 2023 | Valid until 30 Oct 2030 |
| DREAM AATMANVadasar, 390010 | NEELA DEVELOPERS | 431 | 99% | 30 Dec 2017 | Valid until 30 Jun 2023 |
| Emerlad OneVadodara Kasba, 390020 | EMERALD ONE | 430 | 96% | 12 Oct 2018 | Valid until 30 Jun 2021 |
| SHREE BALAJI SKYRISEAtladara, 390012 | MANAV INFRASTRUCTURE PRIVATE LIMITED | 430 | 51% | 20 Nov 2017 | Valid until 30 May 2022 |
| NYSA SKYDALEChhani, 391740 | CHALLENGE INFRASTRUCTURE | 424 | 43% | 27 Sep 2017 | Valid until 7 Oct 2021 |
| ANANTA SAVERA SWAGATAMBil, 391410 | S S INFRA | 420 | 94% | 26 Jul 2018 | Valid until 30 Sep 2021 |
| PMAY BHAYLI 392 EWS-II FP 114Bhayli, 391410 | VADODARA URBAN DEVELOPMENT AUTHORITY | 418 | 91% | 23 Jul 2019 | Valid until 7 Mar 2022 |
| ROYAL LIFESJesangpura, 390019 | MAKHIJA INFRASTRUCTURE PRIVATE LIMITED | 418 | 62% | 19 Nov 2018 | Valid until 30 Jun 2020 |
| EVEREST UNITY/TRINITY/DIGNITY-IIBhayli | EVEREST CONSTRUCTION COMPANY | 417 | 87% | 29 Feb 2020 | Valid until 30 Jun 2024 |
| DREAM AATMAN IIVadasar | PARTHIV REALTY | 416 | 84% | 22 Jan 2020 | Valid until 30 Jun 2025 |
| SAFAL IRISAtladara, 390012 | SAHAJANAND INFRA | 416 | 73% | 22 Feb 2019 | Valid until 29 Jun 2025 |
| SHREE SIDDHESHWAR HILLCRESTBAPOD, 390019 | N K CAMPUS | 415 | 15% | 25 May 2026 | Valid until 28 Dec 2030 |
| SHREE SIDDHESHWAR HIGHNESS390019 | NYALKARAN PROCON | 406 | 59% | 19 Mar 2022 | Valid until 30 May 2027 |
Developers active in Vadodara
VADODARA URBAN DEVELOPMENT AUTHORITY (29), VADODARA MUNICIPAL CORPORATION (23), SHREEJI DEVELOPERS (20), SHIVAM DEVELOPERS (14), SAMANVAY SPARSH (11), DARSHANAM LIFE SPACE PRIVATE LIMITED (11). Each link opens the promoter's track record built from their own filings.
Frequently asked questions
How do I shortlist among the Vadodara projects listed above?
Compare each project against its neighbours, not against the brochure. Of the 2731 projects on this page that file a booking figure, the median is 70% booked, which is the benchmark to hold any single project against. A project selling much slower than the district may have a pricing or credibility problem; one selling much faster deserves a look at whether construction is keeping pace with collections. Then open the developer link to check their delivery record on other projects, and compare filed carpet areas rather than super built-up marketing areas.
What does a revised completion date on a Vadodara project actually mean?
The promoter has moved their deadline with the regulator, usually under section 6, which allows an extension of up to one year for reasons beyond their control. It does not move the date in your agreement for sale: your section 18 claim for delay interest or refund runs from the possession date you signed for. Before booking a project with a revision on record, ask which approvals or works the new date depends on.
What if a Vadodara project shows strong sales but slow construction?
That shape means the promoter is collecting money faster than they are building, which is fine under a disciplined promoter and dangerous under a stretched one. The law helps: withdrawals from the project account need architect, engineer and CA certificates in proportion to progress. Check the promoter's delivery record, and watch the next quarterly filing (due within 20 days of each quarter end) to see whether the construction line moves.
Does something here look wrong, or is there a number you expected to find and did not? Every figure on this page is summed from the projects' own GujRERA filings, and we read every report.
Report an errorShare feedbackData from official GujRERA filings.