ReraGenieLog inGet a buyer report

Home / Browse projects / Vadodara, Gujarat / THE RISE PLAZA

Valid until 30 Oct 2027 Commercial project

THE RISE PLAZA

By THE DWARKESH INFRA

RG-GJ-12773 · RERA PR/GJ/VADODARA/VADODARA/Others/RAA03505/A1C/030220 · Last updated on GujRERA portal: 10 Oct 2025

Source: official GujRERA filing

Red flags

  • Completion date moved by 16 months
  • 1 extension taken

Clear

  • Nothing verified clear yet
Oct 2027Possession promisedmoved 16 months from the original
10 of 18Construction stages doneacross 2 buildings; furthest along: Installation of lifts, 98%
339 of 474Units unsoldnot recorded sold or booked
Jump to the 39 documents Report an error

THE RISE PLAZA is a Commercial project by THE DWARKESH INFRA in Vadodara, Gujarat, registered with GujRERA as PR/GJ/VADODARA/VADODARA/Others/RAA03505/A1C/030220 on 26 Sep 2018. Possession is promised by 30 Oct 2027. The completion date has moved by 16 months from the original filing. 135 of the 474 units on this registration are recorded sold or booked, and 10 of 18 construction stages are filed complete.

At a glance

Project

  • NameTHE RISE PLAZA
  • TypeCommercial
  • Location
    • NR TARSALI BYPASS
    • NH N- 8
    • TARSALI
    • Tarsali
    • Vadodara
    • 390014
  • Pincode390014
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/VADODARA/VADODARA/Others/RAA03505/A1C/030220
  • ReraGenie IDRG-GJ-12773

Builder

  • NameTHE DWARKESH INFRA
  • Entity typePARTNERSHIP FIRM

Key dates

this monthRegisteredSep 2018First promiseJun 2026Revised toOct 2027

Key facts

Registration and timeline

  • StatusValid until 30 Oct 2027
  • Registered on26 Sep 2018
  • Promised completion30 Oct 2027
  • Revised completionRevised to 30 Oct 2027 (originally 30 Jun 2026)
  • Buildings2 building records
  • Documents filed39 files

Current status

28%135 of 474 units booked
75.2%Of the estimated cost spent so far

Figures as on 10 Oct 2025, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
TOWER1---0342342
TOWER2---0132132

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building2

As on 10 Oct 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

10 of 18 construction stages are filed complete across 2 buildings. The stage furthest along is Installation of lifts, at 98%.

TOWER198%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor94%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats95%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing92%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing98%
TOWER296%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor88%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats96%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing88%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing96%

Progress on shared amenities19

As on 10 Oct 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsYes40%
Water supplyYes75%
Sewerage (chamber, lines, septic tank, STP)Yes60%
Storm water drainsYes70%
Landscaping and tree plantingYes10%
Street lightingYes40%
Community buildingsNoNot applicable
Treatment and disposal of sewage and sullage waterNoNot applicable
Solid waste management and disposalNoNot applicable
Water conservation, rain water harvestingNoNot applicable
Energy managementNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes0%
Fire fightingNoNot applicable
Drinking water facilitiesNoNot applicable
Emergency evacuationNoNot applicable
Use of renewable energyNoNot applicable
SecurityNoNot applicable
Letter boxNoNot applicable

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area6,423 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountNot declared
Estimated costRs 11.22 cr
Cost incurredRs 8.44 cr
Spent of the estimate75.22%
BuildingWingEstimatedIncurred
TOWER1NARs 7.38 crRs 5.55 cr
TOWER2NARs 3.84 crRs 2.88 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectMITESH PATEL
Engineerzarna associates

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

ExtensionApplied Jun 2026; no approval date filed

Documents filed39

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/VADODARA/VADODARA/Others/RAA03505/A1C/030220 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Architect's certificate (Form 1)10 Oct 2025
Engineer's certificate (Form 2)10 Oct 2025
Engineer's certificate annexure10 Oct 2025
Accountant's certificate (Form 3)10 Oct 2025
Site photograph, TOWER19 Oct 2025
Site photograph, TOWER29 Oct 2025
RERA registration certificate26 Sep 2018
Proforma agreement for sale-
Auditor's report (1 of 3)-
Auditor's report (2 of 3)-
Auditor's report (3 of 3)-
Income tax return (1 of 3)-
Income tax return (2 of 3)-
Income tax return (3 of 3)-
Project specific document-
Directors' report (1 of 3)-
Directors' report (2 of 3)-
Directors' report (3 of 3)-
Commencement certificate-
Approved sanctioned plan-
Approved layout plan-
Agreement-
Land location-
Encumbrance certificate-
Area development document-
Proforma allotment letter-
Brochure-
Project related document-
Declaration in Form B-
Project photograph-
Audited balance sheet (1 of 3)-
Audited balance sheet (2 of 3)-
Audited balance sheet (3 of 3)-
Audited profit and loss statement (1 of 3)-
Audited profit and loss statement (2 of 3)-
Audited profit and loss statement (3 of 3)-
Cash flow statement (1 of 3)-
Cash flow statement (2 of 3)-
Cash flow statement (3 of 3)-

How this compares with Vadodara

28%of this project is bookeddistrict median 70%
23%of Vadodara projects moved their completion datethis one moved by 16 months

Computed across the 2,900+ Vadodara projects on ReraGenie, from their own filings.

Keep THE RISE PLAZA on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Tarsali2,900+ in Vadodara

2 kmTHE RISE PLAZAOther 139Dot size: filed unitsN

Filed coordinates, straight-line distance. 139 registered projects within 2 km.

Builder: THE DWARKESH INFRA

THE DWARKESH INFRA has 1 registration on GujRERA, including THE RISE PLAZA. Read the full track record. See more projects on the Vadodara district page.

Frequently asked questions

What are my rights if THE RISE PLAZA is delayed beyond 30 Oct 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of THE RISE PLAZA?

The registered promoter entity is THE DWARKESH INFRA, a partnership firm as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in THE RISE PLAZA?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at THE RISE PLAZA?

The professionals named in the filing: Architect: MITESH PATEL; Engineer: zarna associates. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in THE RISE PLAZA?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About THE RISE PLAZA. Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save THE RISE PLAZA to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.