ReraGenieLog inGet a buyer report

Home / Browse projects / Vadodara, Gujarat / SHYAMAL HEIGHTS

Valid until 18 Jan 2027 Mixed Development project

SHYAMAL HEIGHTS

By RKP INVESTMENTS

RG-GJ-32694 · RERA PR/GJ/VADODARA/VADODARA/Others/MAA06265/EX1/EX2/310126/180127 · Last updated on GujRERA portal: 24 Oct 2026

Source: official GujRERA filing

Red flags

  • Completion date moved by 24 months
  • 2 extensions taken

Clear

  • Nothing verified clear yet
Jan 2027Possession promisedmoved 24 months from the original
33 of 36Construction stages doneacross 4 buildings; furthest along: External plumbing and external plaster, 30%
136 of 567Units unsoldnot recorded sold or booked
Jump to the 43 documents Report an error

SHYAMAL HEIGHTS is a Mixed Development project by RKP INVESTMENTS in Vadodara, Gujarat, registered with GujRERA as PR/GJ/VADODARA/VADODARA/Others/MAA06265/EX1/EX2/310126/180127 on 25 Oct 2019. Possession is promised by 18 Jan 2027. The completion date has moved by 24 months from the original filing. 431 of the 567 units on this registration are recorded sold or booked, and 33 of 36 construction stages are filed complete.

At a glance

Project

  • NameSHYAMAL HEIGHTS
  • TypeMixed Development
  • Location
    • SHYAMAL HEIGHTS
    • B/H L & T KNOWLEDGE CITY
    • WAGHODIA- ANKHOL ROAD
    • Ankhol
    • Vadodara
  • PincodeNot stated
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/VADODARA/VADODARA/Others/MAA06265/EX1/EX2/310126/180127
  • ReraGenie IDRG-GJ-32694

Builder

  • NameRKP INVESTMENTS
  • Entity typePARTNERSHIP FIRM
  • Other registrations1 more →

Key dates

this monthRegisteredOct 2019First promiseJan 2025Revised toJan 2027

Key facts

Registration and timeline

  • StatusValid until 18 Jan 2027
  • Registered on25 Oct 2019
  • Promised completion18 Jan 2027
  • Revised completionRevised to 18 Jan 2027 (originally 18 Jan 2025)
  • Buildings4 building records
  • Documents filed43 files

Current status

76%431 of 567 units booked
116.9%Of the estimated cost spent so far

Figures as on 24 Oct 2026, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
A+B+C---12025145
D+E+F+G---1605165
H+I+J---1200120
K+L+M---11423137

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building4

As on 24 Oct 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

33 of 36 construction stages are filed complete across 4 buildings. The stage furthest along is External plumbing and external plaster, at 30%.

A+B+C100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
D+E+F+G100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
H+I+J70%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats0%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing30%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing0%
K+L+M100%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%

Progress on shared amenities19

As on 24 Oct 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsYes100%
Water supplyYes90%
Sewerage (chamber, lines, septic tank, STP)Yes90%
Storm water drainsYes85%
Landscaping and tree plantingYes100%
Street lightingYes90%
Community buildingsYes100%
Treatment and disposal of sewage and sullage waterYes85%
Solid waste management and disposalYes90%
Water conservation, rain water harvestingYes90%
Energy managementNoNot applicable
Fire protection and fire safety requirementsYes85%
Electrical meter room, sub-station, receiving stationNoNot applicable
Fire fightingNoNot applicable
Drinking water facilitiesYes90%
Emergency evacuationNoNot applicable
Use of renewable energyNoNot applicable
SecurityYes95%
Letter boxYes95%

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area11,146 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountNot declared
Estimated costRs 55.00 cr
Cost incurredRs 64.29 cr
Spent of the estimate116.89%
BuildingWingEstimatedIncurred
A+B+CNARs 15.43 crRs 18.52 cr
D+E+F+GNARs 14.30 crRs 17.16 cr
H+I+JNARs 13.95 crRs 15.03 cr
K+L+MNARs 11.32 crRs 13.58 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectRUCHIR SHETH(DESIGN STUDIO ASSOCIATES)
EngineerASHUTOSH DESAI

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

PR/GJ/VADODARA/VADODARA/Others/MAA06265/EX1/200325/180126Applied Dec 2024; approved Mar 2025
PR/GJ/VADODARA/VADODARA/Others/MAA06265/EX1/EX2/310126/180127Applied Jan 2026; approved Jan 2026

Documents filed43

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/VADODARA/VADODARA/Others/MAA06265/EX1/EX2/310126/180127 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Accountant's certificate (Form 3)24 Oct 2026
Engineer's certificate (Form 2)17 Oct 2026
Engineer's certificate annexure17 Oct 2026
Architect's certificate (Form 1)16 Oct 2026
Site photograph, A+B+C12 Oct 2026
Site photograph, D+E+F+G12 Oct 2026
Site photograph, H+I+J12 Oct 2026
Site photograph, K+L+M12 Oct 2026
RERA registration certificate25 Oct 2019
Extension certificate-
Auditor's report (1 of 3)-
Auditor's report (2 of 3)-
Auditor's report (3 of 3)-
Income tax return (1 of 3)-
Income tax return (2 of 3)-
Income tax return (3 of 3)-
Project specific document-
Directors' report (1 of 3)-
Directors' report (2 of 3)-
Directors' report (3 of 3)-
Commencement certificate-
Approved sanctioned plan-
Approved layout plan-
Agreement-
Land location-
Encumbrance certificate-
Area development document-
Brochure-
Project related document-
Declaration in Form B-
Title clearance certificate-
Title report-
Property card-
Project photograph-
Audited balance sheet (1 of 3)-
Audited balance sheet (2 of 3)-
Audited balance sheet (3 of 3)-
Audited profit and loss statement (1 of 3)-
Audited profit and loss statement (2 of 3)-
Audited profit and loss statement (3 of 3)-
Cash flow statement (1 of 3)-
Cash flow statement (2 of 3)-
Cash flow statement (3 of 3)-

How this compares with Vadodara

76%of this project is bookeddistrict median 70%
23%of Vadodara projects moved their completion datethis one moved by 24 months

Computed across the 2,900+ Vadodara projects on ReraGenie, from their own filings.

Keep SHYAMAL HEIGHTS on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Ankhol2,900+ in Vadodara

2 kmSHYAMAL HEIGHTSOther 156Dot size: filed unitsN

Filed coordinates, straight-line distance. 156 registered projects within 2 km.

Builder: RKP INVESTMENTS

RKP INVESTMENTS has 2 registrations on GujRERA, including SHYAMAL HEIGHTS and SHYAMAL ORCHID. Read the full track record. See more projects on the Vadodara district page.

Frequently asked questions

What are my rights if SHYAMAL HEIGHTS is delayed beyond 18 Jan 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of SHYAMAL HEIGHTS?

The registered promoter entity is RKP INVESTMENTS, a partnership firm as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in SHYAMAL HEIGHTS?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at SHYAMAL HEIGHTS?

The professionals named in the filing: Architect: RUCHIR SHETH(DESIGN STUDIO ASSOCIATES); Engineer: ASHUTOSH DESAI. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SHYAMAL HEIGHTS?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SHYAMAL HEIGHTS. Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SHYAMAL HEIGHTS to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.