RG-KA-66605 · RERA PRM/KA/RERA/1267/374/PR/171019/000810

Source: official RERA Karnataka filing

Red flags

  • 7 complaints at RERA Karnataka
  • Completion date moved by 12 months
  • 2 extensions taken

Clear

  • Separate project account declared
Mar 2021Possession promisedmoved 12 months from the original
7Complaints at RERA Karnatakaon this registration
Jump to the 61 documents Report an error

Zuari Garden city - Kaveri Apartments is a Residential/Group Housing project by ZUARI INFRAWORLD INDIA LIMITED in Mandya, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1267/374/PR/171019/000810 on 19 Oct 2017. Possession is promised by 31 Mar 2021. The completion date has moved by 12 months from the original filing. 7 complaints are on record with the regulator.

At a glance

Project

  • NameZuari Garden city - Kaveri Apartments
  • TypeResidential/Group Housing
  • Location
    • Shrirangapattna
    • Mandya
  • PincodeNot stated
  • RERA no.PRM/KA/RERA/1267/374/PR/171019/000810
  • ReraGenie IDRG-KA-66605

Builder

  • NameZUARI INFRAWORLD INDIA LIMITED
  • Entity typeCompany
  • CINU45309KA2007PLC043161
  • Authorized SignatoryK. Harsha Raja Urs
  • OthersVivekanand Maroor
  • Other registrations2 more →
  • Declared earlier projects2 →

Key dates

this monthRegisteredOct 2017First promiseMar 2020Revised toMar 2021

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on19 Oct 2017
  • Promised completion31 Mar 2021
  • Revised completionRevised to 31 Mar 2021 (originally 31 Mar 2020)
  • Buildings3 building records
  • Documents filed61 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Tower - E---76076
Tower - F---66066
Tower - G---78078

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

Building:

ActivityProgress
Earth work and other leveling preparation work-
Foundation footing work-
Retaining wall (All types)-
Plinth level BeamNot applicable
Sub-structure flooring (Parking Floor, more than one floor below general ground level)-
RCC or MS Framed structure-
Masonry construction: Bricks, Concrete blocks etc-
Plastering inside , outside & Ceiling-
Joinery: Doors, Windows, Ventilators etc-
Basic work of Water supply, Sanitary and Electrification-
Dadoing, Skirting, Flooring, Tiles work (All types)-
Railing and Grill fixing-
Electrification, Water supply and Sanitary Finishing-
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Fire prevention and fire fighting fitting and fixture with network-
Weather Proof work(tile,concrete)-
Painting-
Elevation work-
Internal and External work including landscapes as per santioned drawings-

Progress on shared amenities41

Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes-
Internal Roads & FootpathsYes-
Sewage and Drainage SystemYes-
Parks & Tree plantingYes-
Street LightingYes-
Provision for community buildings and for treatment and disposal of sewage and sullage waterYes-
Solid waste management and disposalYes-
Water conservationYes-
Energy managementYes-
Fire protection and fire safety requirementsYes-
Education/Health/Other public amenitiesNoNot applicable
Electricity supply transformer and substationYes-
Emergency Evacuation servicesYes-
Storm water drainsYes-
Use of renewable energyNoNot applicable
Water conservation/rain water harvesting/recharge of ground waterYes-
ElectricityYes-
Smart Home AutomationNoNot applicable
CCTV SurveillanceNoNot applicable
Club HouseYes-
Community HallNoNot applicable
Outdoor Sports facilityYes-
Indoor Sports facilityYes-
Swimming PoolYes-
GymYes-
ParksYes-
Power BackupYes-
GasNoNot applicable
Water and SanitationYes-
Air Conditioning And incerntionNoNot applicable
StaircasesYes-
LiftsYes-
Staircases and Lift lobbies, corridor,lobbies, corridorYes-
Fire escapesYes-
Common entrance and exit for the building / common portico/foyer/verandahYes-
BasementYes-
TerraceYes-
Outer WallYes-
Open parking areas and common storage spacesNoNot applicable
Provision for lodging of management staff and security staffNoNot applicable
Water conservation and renewable energyYes-

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area283,884 sq m
Named landownersNone

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 86.16 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectThomas Associates
EngineerAnagha Engineering Consultants

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

ExtensionMar 2020 → Sep 2021

No reason recorded in the filing

EX/PRM/KA/RERA/1267/374/PR/220620/000810Sep 2021 → Mar 2021

Reason as filed by the promoterActivities undertaken by BMRDA, BBPM, BESCOM etc. leading to delay in construction; Force Majeure

Complaints filed with RERA Karnataka7

Case no.ComplainantRespondentFiled
CMP/190508/0002954-ZUARI INFRAWORLD INDIA LIMITED08/05/2019
CMP/190510/0002971-ZUARI INFRAWORLD INDIA LIMITED10/05/2019
CMP/200427/0005850-ZUARI INFRAWORLD INDIA LIMITED27/04/2020
CMP/210106/0007345-ZUARI INFRAWORLD INDIA LIMITED06/01/2021
01241/2023-ZUARI INFRAWORLD INDIA LIMITED10/08/2023
01798/2023-ZUARI INFRAWORLD INDIA LIMITED07/12/2023
00300/2024-ZUARI INFRAWORLD INDIA LIMITED21/03/2024

Documents filed61

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PRM/KA/RERA/1267/374/PR/171019/000810 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
CertificateFile: CIN.pdf-
Architect Certificate for Work Completion Schedule till DateFile: Kaveri Architect-Certificate (QU) Dec 19.pdf-
Engineer Certificate for Work Completion Schedule till DateFile: Kaveri Architect-Certificate (QU) Dec 19.pdf-
CA Certificate for Funds UtilizationFile: CA Certificate-Kaveri Apts-01-01-2020.pdf-
Architect Certificate for Pending Work Completion Schedule.File: Kaveri Architect-Certificate (QU) Dec 19.pdf-
Engineer Certificate for Pending Work Completion Schedule.File: Kaveri Architect-Certificate (QU) Dec 19.pdf-
CA Certificate for Funds required for Project CompletionFile: CA Certificate-Kaveri Apts-01-01-2020.pdf-
AffidavitFile: Notorized Affidavit.pdf-
Latest Encumbrance CertificateFile: ZGC Project EC till date - 15-01-2020.pdf-
Details Of Sold/ Un-sold UnitsFile: SoldUnsoldDetails-15-01-2020.pdf-
Commencement certificate_ Kaveri-
Site Plan_ Apartment 2-Modified-
Site Plan_ Apartment 1-
Proforma Sale Deed_ Kaveri-
Proforma agreement to Sell_ Kaveri-
Site Plan_ Apartment 2-Modified-
clarification_Letter_ Apartments-
Sale deed & RTC_ BS-
Site Plan_ Apartment 2-Modified-
DEVELOPMENT PLAN_ Apartment-
Proforma Allottment letter_ Kaveri-
3491_001-ilovepdf-compressed-min-
NOC Sub-ilovepdf-compressed-
Project Spec Sheet Phase II-
Encumbrance Certificate-
Khatha Grampanchayat-
Mutation-
Conversion order-
13_ Statement of collection_ Kaveri-
Relinquishment Deed-
NOC - FIRE-
NOC - Airport Authority-
NOC_CESCOM-
NOC - KUWS&DB-
NOC - KSPCB-
Balance Sheet 2015 - 2016File: Balance sheet_2016.pdf-
Balance Sheet 2014 - 2015File: Balance sheet_2015.pdf-
Balance Sheet 2013 - 2014File: Balance sheet_2014.pdf-
Audited Profit and Loss Statement 2015 - 2016File: P&L Account_2016.pdf-
Audited Profit and Loss Statement 2014 - 2015File: P&L Account_2015.pdf-
Audited Profit and Loss Statement 2013 - 2014File: P& L Account_2014.pdf-
Director's Report 2015 - 2016File: Directors_2016.pdf-
Director's Report 2014 - 2015File: Directors Report_2015.pdf-
Director's Report 2013 - 2014File: Directors Report_2014.pdf-
Cash Flow Statement 2015 - 2016File: CFS_2016.pdf-
Cash Flow Statement 2014 - 2015File: CFS_2015.pdf-
Auditor's Report 2015 - 2016File: Auditors Report_2016.pdf-
Auditor's Report 2014 - 2015File: Auditros Report_2015.pdf-
Auditor's Report 2013 - 2014File: Auditors Report_2014.pdf-
Income Tax Return Acknowledgement 2015 - 2016File: ITR_2016.pdf-
Income Tax Return Acknowledgement 2014 - 2015File: ITR_2015.pdf-
Income Tax Return Acknowledgement 2013 - 2014File: ITR_2014.pdf-
17_Form_B_ Affidavit_Kaveri-
Prospectus/BrochureFile: ZGCApartment_Brochure.pdf-
Advertisement Copy 1File: Advertisement_ ZGC_Apartment_Ad.pdf-
Tower Excel SheetFile: PRM_KA_RERA_1267_374_PR_171019_000810 (2).xlsx-
Loan raised documentFile: Compressed Kaveri_Form 4CC.pdf-
Occupancy CertificateFile: ZGC - Kaveri.pdf-
Architect certificate for having completed the work(in format no 5)File: Form 5 Architect Certificate on Completion Kaveri 23A.pdf-
Chartered Accountant certificate for having completed the work(in format no 4)File: Compressed Kaveri_Form 4CC.pdf-
Affidavit cum declaration from promoter for having completed the project as per specification and as per adverFile: Affidavit cum Declaration.pdf-

How this compares with Mandya

18%of Mandya projects moved their completion datethis one moved by 12 months
0%of Mandya registrations are shown as withdrawn or revokedthis one is not

Computed across the 81 Mandya projects on ReraGenie, from their own filings.

Keep Zuari Garden city - Kaveri Apartments on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Mandya81 in Mandya

Builder: ZUARI INFRAWORLD INDIA LIMITED

Zuari Infraworld India Limited has 3 registrations on RERA Karnataka, including Zuari Garden City - Plots and Zuari Garden City - Brindavan Serenity. Its filings declare 2 earlier projects, 2 of them declared completed. Read the full track record. See more projects on the Mandya district page.

Frequently asked questions

What are my rights if Zuari Garden city - Kaveri Apartments is delayed beyond 31 Mar 2021?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of Zuari Garden city - Kaveri Apartments?

The registered promoter entity is ZUARI INFRAWORLD INDIA LIMITED, a company as per the filing. Its CIN U45309KA2007PLC043161 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in Zuari Garden city - Kaveri Apartments?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against Zuari Garden city - Kaveri Apartments?

Each case number above is a complaint filed with RERA Karnataka. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

Who certifies construction progress at Zuari Garden city - Kaveri Apartments?

The professionals named in the filing: Architect: Thomas Associates; Engineer: Anagha Engineering Consultants. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Zuari Garden city - Kaveri Apartments?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Zuari Garden city - Kaveri Apartments. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Zuari Garden city - Kaveri Apartments to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.