Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
Jan 2030Possession promisedno revision filed
3 of 16Construction stages donefurthest along: Sub-structure flooring (Parking Floor, 50%
2 of 24Units unsoldnot recorded sold or booked
0Complaints at RERA Karnatakaon this registration
Jump to the 121 documents Report an error

Sharadindu Stage V is a Residential/Group Housing project by Sree Senior Homes in Mandya, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1267/375/PR/280324/006739 on 28 Mar 2024. Possession is promised by 31 Jan 2030. 22 of the 24 units on this registration are recorded sold or booked, and 3 of 16 construction stages are filed complete.

At a glance

Project

  • NameSharadindu Stage V
  • TypeResidential/Group Housing
  • Location
    • Pandavapura
    • Mandya
    • 571434
  • Pincode571434
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PRM/KA/RERA/1267/375/PR/280324/006739
  • ReraGenie IDRG-KA-75514

Builder

  • NameSree Senior Homes
  • Entity typePartnership Firm
  • GSTIN29ABUFS6817L1Z4
  • Authorized SignatoryH S Sreenath
  • Other registrations3 more →
  • Declared earlier projects4 →

Key dates

this monthRegisteredMar 2024PromisedJan 2030

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on28 Mar 2024
  • Promised completion31 Jan 2030
  • Revised completionNone
  • Buildings2 building records
  • Documents filed121 files

Current status

92%22 of 24 units booked
16.0%Of the estimated cost spent so far

Figures as on 14 Oct 2026, this project's latest RERA Karnataka filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Block E---12012
Block F---12012

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 14 Oct 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

3 of 16 construction stages are filed complete. The stage furthest along is Sub-structure flooring (Parking Floor, at 50%.

Building: 31% average across the applicable activities

ActivityProgress
Earth work and other leveling preparation work100%
Foundation footing work100%
Upto Plinth Level100%
Sub-structure flooring (Parking Floor, more than one floor below general ground level)50%
Retaining wall (All types)Not applicable
RCC or MS Framed structure50%
Masonry Construction50%
Plastering inside , outside & Ceiling40%
Joinery: Doors, Windows, Ventilators etc10%
Basic work of Water supply, Sanitary and Electrification0%
Dadoing, Skirting, Flooring, Tiles work (All types)0%
Railing and Grill fixing0%
Electrification, Water supply and Sanitary Finishing0%
Painting0%
Fire prevention and fire fighting fitting and fixture with network0%
Weather Proof work(tile,concrete)0%
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Elevation work0%
Internal and External work including landscapes as per sanctioned drawingsNot applicable

Progress on shared amenities40

As on 14 Oct 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes100%
Sewage and Drainage SystemYes100%
Water conservation/rain water harvesting/recharge of ground waterYes100%
Energy managementNoNot applicable
Fire protection and fire safety requirementsYes60%
Solid waste management and disposalYes100%
Emergency Evacuation servicesYes50%
Internal Roads & FootpathsYes75%
Electricity supply transformer and substationYes70%
Storm water drainsNoNot applicable
Use of renewable energyNoNot applicable
Sewage Treatment Plant (STP)Yes100%
Parks & Tree plantingYes100%
Street LightingYes100%
ElectricityYes100%
Smart Home AutomationNoNot applicable
CCTV SurveillanceNoNot applicable
Club HouseYes95%
Community HallYes100%
Outdoor Sports facilityYes100%
Indoor Sports facilityYes100%
Swimming PoolYes0%
GymYes100%
ParksYes100%
Power BackupYes100%
Piped GasNoNot applicable
Water and SanitationYes100%
Air ConditioningNoNot applicable
StaircasesYes50%
LiftsYes0%
Corridor/LobbiesYes50%
Fire escapesNoNot applicable
Common entrance and exit for the building/common portico/foyer/verandahNoNot applicable
BasementNoNot applicable
TerraceYes50%
Outer WallNoNot applicable
Open parking areasNoNot applicable
Provision for lodging of management staff and security staffNoNot applicable
Water conservation and renewable energyNoNot applicable
Common storage spacesNoNot applicable

Land and ownership3

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area854 sq m
Named landowners3
LandownerVillageDistrict
Sree Senior Homes--
Sree Senior Homes--
Sree Senior Homes--

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 7.06 cr
Cost incurredRs 1.13 cr
Spent of the estimate16.03%
Cost lineEstimatedIncurred
Estimated Cost of Construction as certified by EngineerRs 3.66 crRs 82.31 lakh
On-site expenditure-Site OverheadRs 3.00 crRs 26.09 lakh
Payment of chargesRs 40.39 lakh-
On-site expenditure-Salaries of workers-Rs 4.73 lakh
On-site expenditure-Cost Of Services(Water, Electricity, Sewage)-Rs 4,546

Certifying professionals and partners3

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectTrupti N Shah
EngineerPraveen J
Chartered AccountantMN Sunil Kumar

Complaints filed with RERA Karnataka

No complaints on record against this registration.

Documents filed121

As listed on the registration, under the names the promoter filed them with; the newest 80 of 121 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1267/375/PR/280324/006739 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Q2 2026-27 Form-4 Certificate issued by Chartered AccountantFile: FORM_4_CA_CERTIFICATE_JULY_TO_SEPT_2026.pdf14 Oct 2026
Q2 2026-27 Form-5 Certificate issued by ArchitectFile: FORM 5_ARCHITECT CERTIFICATE - JULY -SEPT 2026.pdf14 Oct 2026
Q2 2026-27 Form-6 Certificate issued by Structural EngineerFile: Q2_Form_6_Engineer_Certificate_Stage_V_JULY_TO_SEPT_2026 (1).pdf14 Oct 2026
Q2 2026-27 Water supply and sewage board14 Oct 2026
Q2 2026-27 KSPCB- PCB (10 Acres to 125 Acres)14 Oct 2026
Q2 2026-27 KPTCL- BESCOM14 Oct 2026
Q1 2026-27 Form-4 Certificate issued by Chartered AccountantFile: Q1 26-27 Form 4 CA SD V.pdf14 Jul 2026
Q1 2026-27 Form-5 Certificate issued by ArchitectFile: Q1 26-27 Form 5 Ar SD V.pdf14 Jul 2026
Q1 2026-27 Form-6 Certificate issued by Structural EngineerFile: Q1 26-27 Form 6 Er SD V.pdf14 Jul 2026
Q1 2026-27 Water supply and sewage board14 Jul 2026
Q1 2026-27 KSPCB- PCB (10 Acres to 125 Acres)14 Jul 2026
Q1 2026-27 KPTCL- BESCOM14 Jul 2026
Q4 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Q4_CA_CERTIFICATE_JAN_MAR_2026 SB V.pdf15 Apr 2026
Q4 2025-26 Form-5 Certificate issued by ArchitectFile: Q4 ARCHITECT JAN TO MAR 2026 SB V.pdf15 Apr 2026
Q4 2025-26 Form-6 Certificate issued by Structural EngineerFile: Q4 Engineer JAN TO MAR_2026 SB V.pdf15 Apr 2026
Q4 2025-26 Water supply and sewage board15 Apr 2026
Q4 2025-26 KSPCB- PCB (10 Acres to 125 Acres)15 Apr 2026
Q4 2025-26 KPTCL- BESCOM15 Apr 2026
Q3 2025-26 Form-4 Certificate issued by Chartered AccountantFile: FORM 4 CA OCT DEC 2025.pdf14 Jan 2026
Q3 2025-26 Form-5 Certificate issued by ArchitectFile: FORM 5 ARCHITECT OCT DEC 2025.pdf14 Jan 2026
Q3 2025-26 Form-6 Certificate issued by Structural EngineerFile: Form 6 Engineer OCT TO DEC 2025.pdf14 Jan 2026
Q3 2025-26 Water supply and sewage board14 Jan 2026
Q3 2025-26 KSPCB- PCB (10 Acres to 125 Acres)14 Jan 2026
Q3 2025-26 KPTCL- BESCOM14 Jan 2026
fORM 1 CA CERTIFICATE NEW FORMATFile: 1 FORM_1_CA_CERTIFICATE NEW FORMAT.pdf7 Mar 2024
CLARIFICATION ON JDA WITH ALL THE SUPPORTING DOCUMENTSFile: 3 Clarification on JDA with all the necessary documents_compressed.pdf7 Mar 2024
COMMENCEMENT CERTIFICATEFile: 2 Commencement_Certificate_Stage_V.pdf7 Mar 2024
BS 2020-21 with UDIN, Schedules and Attested by PartnerFile: 1 Balance_Sheet_2020-21 (3).pdf25 Feb 2024
BS 2021-22 with UDIN, Schedules and Attested by PartnerFile: 2 Balance_sheet_2021-22.pdf25 Feb 2024
BS 2022-23 with UDIN, Schedules and Attested by PartnersFile: 3 Balance_Sheet_2022-23.pdf25 Feb 2024
P&L 2020-21 with UDIN, Schedules and Attested by PartnerFile: P___L_2020_-21.pdf25 Feb 2024
P&L 2021-22 with UDIN, Schedules and Attested by PartnerFile: P___L_2021_-22.pdf25 Feb 2024
P&L 2022-23 with UDIN, Schedules and Attested by PartnerFile: P___L_2022-23.pdf25 Feb 2024
Form 1 in the New FormatFile: 4 New Format FORM_1_CA_CERTIFICATE.pdf25 Feb 2024
Bank Affidavit with all three accounts notorisedFile: 6 AFFIDAVIT_BANK.pdf25 Feb 2024
Sources of Funds with all the supporting documentsFile: Sources of funds with backup documents.pdf25 Feb 2024
RTC with Clear ClarificationFile: 1 Note_-_RTC.pdf25 Feb 2024
MR before Hissa PodhiFile: 2 MR_before_Hissa_Podhi (2).pdf25 Feb 2024
MRsFile: 3 MR_hissa_podhi.pdf25 Feb 2024
Clarification on FARFile: 1 Clarification on FAR (1).pdf25 Feb 2024
Clarification over the height of the buildingFile: 2 Clarification over the height of the building.pdf25 Feb 2024
DTCP Approval Single PlotFile: 3 DTCP_Approval-_single_plot.pdf25 Feb 2024
Single Plot LayoutFile: 4 Single_plot_layout.pdf25 Feb 2024
Carpet Area Block E as certifiedFile: 5 Carpet_Area_Block_E.pdf25 Feb 2024
Carpet Area Block F as certifiedFile: 6 Carpet_Area_Block_F.pdf25 Feb 2024
Clarification on CDPFile: 7 CLARIFICATION_CDP.pdf25 Feb 2024
Commencement Certificate Block EFile: 8 Commencement_Certificate_Block_E.pdf25 Feb 2024
Commencement Certificate Block FFile: 9 Commencement_Certificate_Block_F.pdf25 Feb 2024
KSPCB CFO with the clear clarification till end of the projectFile: 10 KSPCB NOC_merged.pdf25 Feb 2024
Note on KSPCB CFEFile: Note_-_CFE.pdf25 Feb 2024
Clarification over the submission of Form 6 as its a launchFile: 1 Clarification on submission of Form 6 (2).pdf25 Feb 2024
Certified Common Areas and AmenitiesFile: 2 COMMON_AREA_AMENITIES.pdf25 Feb 2024
Engineer's License self attestedFile: 4 Engineer's License self attested.pdf25 Feb 2024
Abstract of Cost of Construction with clear estimations for E & F attachedFile: 5 Abstract with the estimation of cost E & F Blocks.pdf25 Feb 2024
STP drawings with demarcationFile: 6 STP Drawings.pdf25 Feb 2024
Land Cost as per guidance value certifiedFile: 7 Land_Cost_as_per_guidance_value.pdf25 Feb 2024
Kaveri water sanctionFile: 8 Kaveri_Water_Sanctioned.pdf25 Feb 2024
RTC, survey 45/1-
Mutation, survey 45/1-
Encumbrance Certificate, survey 45/1-
Conversion/Alienation Order, survey 45/1-
Sale/Title/Gift Deed, survey 45/1-
Khatha, survey 45/1-
RTC, survey 45/3-
Mutation, survey 45/3-
Encumbrance Certificate, survey 45/3-
Conversion/Alienation Order, survey 45/3-
Sale/Title/Gift Deed, survey 45/3-
Khatha, survey 45/3-
RTC, survey 49/3-
Mutation, survey 49/3-
Encumbrance Certificate, survey 49/3-
Conversion/Alienation Order, survey 49/3-
Sale/Title/Gift Deed, survey 49/3-
Khatha, survey 49/3-
Registration CertificateFile: Reg_of_Firm_New.pdf-
Partnership DeedFile: Partnership deed.pdf-
Partner Details-
Partner Details-
Certificate issued by CA Form 1File: FORM_1_CA_CERTIFICATE.pdf-

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 not delivered by the promised date
ProjectLocationStatusPromisedDelivered
Sharadindu Stage IVKhatha 254, Ranganakoppalu Village, Kasaba Hobli, Pandavapura Taluk, Mandya DistrictOngoingMar 2026Not delivered

How this compares with Mandya

92%of this project is bookeddistrict median 92%
18%of Mandya projects moved their completion datethis one has not
0%of Mandya registrations are shown as withdrawn or revokedthis one is not

Computed across the 81 Mandya projects on ReraGenie, from their own filings.

Keep Sharadindu Stage V on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Mandya81 in Mandya

Builder: Sree Senior Homes

Sree Senior Homes has 4 registrations on RERA Karnataka, including Sharadindu Stage VI and Sharadindu - State III. Its filings declare 4 earlier projects, 3 of them declared completed. Read the full track record. See more projects on the Mandya district page.

Frequently asked questions

What are my rights if Sharadindu Stage V is delayed beyond 31 Jan 2030?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of Sharadindu Stage V?

The registered promoter entity is Sree Senior Homes, a partnership firm as per the filing. Its GSTIN 29ABUFS6817L1Z4 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in Sharadindu Stage V?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at Sharadindu Stage V?

The professionals named in the filing: Architect: Trupti N Shah; Engineer: Praveen J; Chartered Accountant: MN Sunil Kumar. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Sharadindu Stage V?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Sharadindu Stage V. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Sharadindu Stage V to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.