Home / Browse projects / Bengaluru Urban, Karnataka / YGR GRANDEUR
YGR GRANDEUR
By YGR CORP
RG-KA-34221 · RERA PRM/KA/RERA/1251/310/PR/041023/006306 · Last updated on RERA Karnataka portal: 4 Oct 2023
Source: official RERA Karnataka filing
Red flags
- No red flags in this filing
Clear
- No litigation declared
- No complaints on record
- Completion date never moved
- Separate project account declared
Saved.
YGR GRANDEUR is a Residential/Group Housing project by YGR CORP in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/310/PR/041023/006306 on 4 Oct 2023. Possession is promised by 31 Dec 2023.
At a glance
Project
- NameYGR GRANDEUR
- TypeResidential/Group Housing
- Location
- Bengaluru South
- Bengaluru Urban
- PincodeNot stated
- RERA no.PRM/KA/RERA/1251/310/PR/041023/006306
- ReraGenie IDRG-KA-34221
Builder
- NameYGR CORP
- Entity typePartnership Firm
- GSTIN29AAPFH1693N1ZJ
- Authorized SignatoryM Y GOWTHAM
Key dates
Key facts
Registration and timeline
- StatusRegistration approved
- Registered on4 Oct 2023
- Promised completion31 Dec 2023
- Revised completionNone
- Buildings1 building record
- Documents filed114 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| YGR GRANDEUR | - | - | - | 16 | 0 | 16 |
The full filing
Everything below is from the project's own RERA Karnataka filing, free to read.
Construction progress by building1
As on 4 Oct 2023, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
Building:
| Activity | Progress |
|---|---|
| Earth work and other leveling preparation work | - |
| Foundation footing work | - |
| Upto Plinth Level | - |
| Sub-structure flooring (Parking Floor, more than one floor below general ground level) | - |
| Retaining wall (All types) | - |
| RCC or MS Framed structure | - |
| Masonry Construction | - |
| Plastering inside , outside & Ceiling | - |
| Joinery: Doors, Windows, Ventilators etc | - |
| Basic work of Water supply, Sanitary and Electrification | - |
| Dadoing, Skirting, Flooring, Tiles work (All types) | - |
| Railing and Grill fixing | - |
| Electrification, Water supply and Sanitary Finishing | - |
| Painting | - |
| Fire prevention and fire fighting fitting and fixture with network | Not applicable |
| Weather Proof work(tile,concrete) | Not applicable |
| Wardrobe, Showcase, Kitchen cabinet, Puja work | Not applicable |
| Elevation work | - |
| Internal and External work including landscapes as per sanctioned drawings | - |
Progress on shared amenities40
As on 4 Oct 2023, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Water Supply | Yes | - |
| Sewage and Drainage System | Yes | - |
| Water conservation/rain water harvesting/recharge of ground water | Yes | - |
| Energy management | Yes | - |
| Fire protection and fire safety requirements | Yes | - |
| Solid waste management and disposal | No | Not applicable |
| Emergency Evacuation services | No | Not applicable |
| Internal Roads & Footpaths | No | Not applicable |
| Electricity supply transformer and substation | Yes | - |
| Storm water drains | No | Not applicable |
| Use of renewable energy | No | Not applicable |
| Sewage Treatment Plant (STP) | Yes | - |
| Parks & Tree planting | Yes | - |
| Street Lighting | Yes | - |
| Electricity | Yes | - |
| Smart Home Automation | No | Not applicable |
| CCTV Surveillance | Yes | - |
| Club House | No | Not applicable |
| Community Hall | No | Not applicable |
| Outdoor Sports facility | No | Not applicable |
| Indoor Sports facility | No | Not applicable |
| Swimming Pool | No | Not applicable |
| Gym | No | Not applicable |
| Parks | No | Not applicable |
| Power Backup | Yes | - |
| Piped Gas | No | Not applicable |
| Water and Sanitation | Yes | - |
| Air Conditioning | No | Not applicable |
| Staircases | Yes | - |
| Lifts | Yes | - |
| Corridor/Lobbies | Yes | - |
| Fire escapes | Yes | - |
| Common entrance and exit for the building/common portico/foyer/verandah | Yes | - |
| Basement | No | Not applicable |
| Terrace | Yes | - |
| Outer Wall | Yes | - |
| Open parking areas | No | Not applicable |
| Provision for lodging of management staff and security staff | No | Not applicable |
| Water conservation and renewable energy | No | Not applicable |
| Common storage spaces | No | Not applicable |
Land and ownership1
This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
| Landowner | Village | District |
|---|---|---|
| YGR CORP Managing Partner M Y Gowtham | - | - |
Project account and cost
70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Cost line | Estimated | Incurred |
|---|---|---|
| Estimated Cost of Construction as certified by Engineer | Rs 7.49 cr | - |
| On-site expenditure-Cost Of Services(Water, Electricity, Sewage) | Rs 15.00 lakh | - |
| On-site expenditure-Salaries of workers | Rs 12.00 lakh | - |
| On-site expenditure-Site Overhead | Rs 12.00 lakh | - |
| On-site expenditure-Consultants Fees | Rs 10.00 lakh | - |
| Payment of fees | Rs 5.00 lakh | - |
| Payment of taxes | Rs 2.50 lakh | - |
| Payment of Premiums | Rs 50,000 | - |
Certifying professionals and partners3
Certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | G Bhanumathy |
| Engineer | Srinivasa Rao Bollimunta |
| Chartered Accountant | Sai Ganesh M |
Complaints filed with RERA Karnataka
No complaints on record against this registration.
Documents filed114
As listed on the registration, under the names the promoter filed them with; the newest 80 of 114 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/310/PR/041023/006306 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| RERA COLLECTION ACCOUNT STATEMENTFile: Collection Account (1).pdf | 4 Oct 2023 |
| CA CERTIFICATEFile: CA Certificate YGR Grandeur.pdf | 4 Oct 2023 |
| Unsecured Loan of 5 CroresFile: UL (1).png | 4 Oct 2023 |
| Deed of Land PurchaseFile: Land Purchase Deed (1).pdf | 4 Oct 2023 |
| Gowtham M Y FY 2020-21File: Gowtham 20-21.pdf | 4 Oct 2023 |
| Gowtham M Y FY 2021-22File: Gowtham 21-22.pdf | 4 Oct 2023 |
| Yogamurthy FY 2020-21File: Yogamurthy 20-21.pdf | 4 Oct 2023 |
| Yogamurthy FY 2021-22File: Yogamurthy 21-22.pdf | 4 Oct 2023 |
| RERA COLLECTION ACCOUNT STATEMENTFile: Collection Account.pdf | 23 Sep 2023 |
| CA CERTIFICATEFile: CA Certificate - YGR Grandeur.pdf | 23 Sep 2023 |
| Unsecured Loan of 5 CroresFile: UL.png | 23 Sep 2023 |
| Deed of Land PurchaseFile: Land Purchase Deed.pdf | 23 Sep 2023 |
| CA certificateFile: CA certificate Form1.pdf | 11 Sep 2023 |
| Source of FundsFile: Source of Funds.pdf | 11 Sep 2023 |
| CA FORM -01File: CA Form 1 Rectified.pdf | 1 Sep 2023 |
| YGR CORP financialFile: YGR CORP Financial.pdf | 1 Sep 2023 |
| YGR Corp financialsFile: YGR Corp financials.pdf | 1 Sep 2023 |
| Source of FundsFile: Source of Fund (5).pdf | 1 Sep 2023 |
| Single plot clarificationFile: Single plot Clarification.pdf | 1 Sep 2023 |
| DCFile: DC Copies.pdf | 1 Sep 2023 |
| Village mapFile: Village MAP with Proposed Site.pdf | 1 Sep 2023 |
| CDP proposed siteFile: CDP Proposed Site (1).pdf | 1 Sep 2023 |
| Engineer certificate Form-6File: FORM 6 (1).pdf | 1 Sep 2023 |
| STP Engg certifiedFile: STP Eng Certified.pdf | 1 Sep 2023 |
| Conversion Order of the DCFile: CCI_000080.pdf | 11 Aug 2023 |
| Survey Sketch of the Proposed SiteFile: Survey Sketch.pdf | 11 Aug 2023 |
| COA CertificateFile: COA Certificate.pdf | 11 Aug 2023 |
| CDP map showing the proposed site Page No. 2File: CDP Proposed Site.pdf | 11 Aug 2023 |
| STP design drawingFile: 10 KLD YGR.pdf | 11 Aug 2023 |
| Proof of COA Certificate NumberFile: ScreenShot of Verify Your Architect.png | 11 Aug 2023 |
| CA certificate in prescribed format form -01File: CA Form 1.pdf | 11 Aug 2023 |
| Mother Deed 1997File: Sale Deed 1997.pdf | 21 Jul 2023 |
| Gift Deed To Sultan AliFile: Gift Deed To Sultan Ali.pdf | 21 Jul 2023 |
| BESCOM NOC and Fee ReceiptFile: BESCOM NOC_Fee Receipt.pdf | 21 Jul 2023 |
| BWSSB NOC Fee ReceiptFile: BWSSB Receipt.pdf | 21 Jul 2023 |
| Village MAP_Proposed SiteFile: Village MAP with Proposed Site.pdf | 21 Jul 2023 |
| CDP MAP_Proposed SiteFile: CDP_ Proposed Site.pdf | 21 Jul 2023 |
| Stablity CertificateFile: Stability Certificate.pdf | 21 Jul 2023 |
| Project Specification with SignatureFile: Project Specifications (1).pdf | 21 Jul 2023 |
| Current Project StatusFile: YGR Grandeur.jpg | 21 Jul 2023 |
| BESCOM NOCFile: BESCOM NOC.pdf | 15 Jun 2023 |
| BUILDING LICENSEFile: Building License.pdf | 15 Jun 2023 |
| CONVERSION COPYFile: Conversion Copy.pdf | 15 Jun 2023 |
| ECFile: EC.pdf | 15 Jun 2023 |
| ESTIMATION COPYFile: Estimation Copy.pdf | 15 Jun 2023 |
| GIFT DEEDFile: Gift Deed.pdf | 15 Jun 2023 |
| KHATA AND EXTRACTFile: Khata and Extract.pdf | 15 Jun 2023 |
| YGR CORP ITR FY 2020.21File: YGR CORP 20-21.pdf | 15 Jun 2023 |
| YGR CORP ITR FY 2021.22File: YGR CORP 21-22.pdf | 15 Jun 2023 |
| PROJECT SPECIFICATIONFile: Project Specifications.pdf | 15 Jun 2023 |
| Village MAP with SiteFile: Pattanagere Village MAP (1).pdf | 15 Jun 2023 |
| RTC, survey 2078/2017/1769/34/8 | - |
| Mutation, survey 2078/2017/1769/34/8 | - |
| Encumbrance Certificate, survey 2078/2017/1769/34/8 | - |
| Sale/Title/Gift Deed, survey 2078/2017/1769/34/8 | - |
| Khatha, survey 2078/2017/1769/34/8 | - |
| Registration CertificateFile: Partnership - YGR CORP.pdf | - |
| Partnership DeedFile: Partnership - YGR CORP.pdf | - |
| Partner Details | - |
| Partner Details | - |
| Certificate issued by CA Form 1File: CA Form 1.pdf | - |
| Certificate issued by Architect Form 2File: Form -2, Architect (PR).pdf | - |
| Certificate issued by Engineer Form 3File: Form - 3, Engineer (PR).pdf | - |
| Project Chartered Accountant | - |
| Project Engineer | - |
| Project Architect | - |
| AffidavitFile: Affidavit Non Litigation.pdf | - |
| Certificate from Chartered AccountFile: CA AC.pdf | - |
| Balance Sheet 2021 - 2022File: Yet To.pdf | - |
| Balance Sheet 2020 - 2021File: BS FY 2122.pdf | - |
| Balance Sheet 2019 - 2020File: BS FY 2021.pdf | - |
| Audited Profit and Loss Statement 2021 - 2022File: Yet To.pdf | - |
| Audited Profit and Loss Statement 2020 - 2021File: PL FY 2021.pdf | - |
| Audited Profit and Loss Statement 2019 - 2020File: PL FY 2021.pdf | - |
| Income Tax Return Acknowledgement 2021 - 2022File: Yet To.pdf | - |
| Income Tax Return Acknowledgement 2020 - 2021File: ITR Ack.pdf | - |
| Income Tax Return Acknowledgement 2019 - 2020File: ITR Ack.pdf | - |
| CC | - |
| BWSSB Noc | - |
| BBMP Plan | - |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Bengaluru Urban
Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.
Keep YGR GRANDEUR on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Bengaluru Urban4,100+ in Bengaluru Urban
Prestige Park Grove
PRESTIGE PROJECTS PRIVATE LIMITED
Prestige Lakeside Habitat
Prestige Habitat Ventures
LivingTree by Kalyani Developers
Kalyani Tech Park Private Limited
PRESTIGE FALCON CITY
PRESTIGE NOTTINGHILL INVESTMENTS
SATTVA CITY
SATTVA CITY PRIVATE LIMITED
GM AMBITIOUS ENCLAVE
M/s. Allam Infinite India Private Limited
See every Bengaluru Urban project, with the district possession charts
Builder: YGR CORP
YGR CORP has 1 registration on RERA Karnataka, including YGR GRANDEUR. Its filings disclose no earlier RERA Karnataka projects. Read the full track record. See more projects on the Bengaluru Urban district page.
Frequently asked questions
What are my rights if YGR GRANDEUR is delayed beyond 31 Dec 2023?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.
How do I verify and contact the developer of YGR GRANDEUR?
The registered promoter entity is YGR CORP, a partnership firm as per the filing. Its GSTIN 29AAPFH1693N1ZJ can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.
Is my payment protected in YGR GRANDEUR?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
Who certifies construction progress at YGR GRANDEUR?
The professionals named in the filing: Architect: G Bhanumathy; Engineer: Srinivasa Rao Bollimunta; Chartered Accountant: Sai Ganesh M. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in YGR GRANDEUR?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.
Report an error Share feedback