Red flags

  • Completion date moved by 12 months
  • 1 extension taken

Clear

  • No complaints on record
  • Separate project account declared
Jul 2019Possession promisedmoved 12 months from the original
0Complaints at RERA Karnatakaon this registration
Jump to the 58 documents Report an error

WILLOW PARK is a Residential/Group Housing project by INDES PROJECTS (INDIA) PVT LTD in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/446/PR/171024/000590 on 24 Oct 2017. Possession is promised by 25 Jul 2019. The completion date has moved by 12 months from the original filing.

At a glance

Project

  • NameWILLOW PARK
  • TypeResidential/Group Housing
  • Location
    • Bengaluru East
    • Bengaluru Urban
  • PincodeNot stated
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PRM/KA/RERA/1251/446/PR/171024/000590
  • ReraGenie IDRG-KA-99518

Builder

  • NameINDES PROJECTS (INDIA) PVT LTD
  • Entity typeCompany
  • CINU70200KA2012PTC065450
  • Authorized SignatoryP L NARASIMHAM
  • DirectorPHANI K PRASAD
  • Other registrations1 more →

Key dates

this monthRegisteredOct 2017First promiseJul 2018Revised toJul 2019

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on24 Oct 2017
  • Promised completion25 Jul 2019
  • Revised completionRevised to 25 Jul 2019 (originally 25 Jul 2018)
  • Buildings2 building records
  • Documents filed58 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
A---47047
B---47047

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

Building:

ActivityProgress
Earth work and other leveling preparation work-
Foundation footing work-
Retaining wall (All types)-
Plinth level Beam-
Sub-structure flooring (Parking Floor, more than one floor below general ground level)-
RCC or MS Framed structure-
Masonry construction: Bricks, Concrete blocks etc-
Plastering inside , outside & Ceiling-
Joinery: Doors, Windows, Ventilators etc-
Basic work of Water supply, Sanitary and Electrification-
Dadoing, Skirting, Flooring, Tiles work (All types)-
Railing and Grill fixing-
Electrification, Water supply and Sanitary Finishing-
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Fire prevention and fire fighting fitting and fixture with network-
Weather Proof work(tile,concrete)-
Painting-
Elevation workNot applicable
Internal and External work including landscapes as per santioned drawings-

Progress on shared amenities41

Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes-
Internal Roads & FootpathsNoNot applicable
Sewage and Drainage SystemYes-
Parks & Tree plantingYes-
Street LightingNoNot applicable
Provision for community buildings and for treatment and disposal of sewage and sullage waterYes-
Solid waste management and disposalNoNot applicable
Water conservationYes-
Energy managementYes-
Fire protection and fire safety requirementsNoNot applicable
Education/Health/Other public amenitiesYes-
Electricity supply transformer and substationNoNot applicable
Emergency Evacuation servicesNoNot applicable
Storm water drainsNoNot applicable
Use of renewable energyNoNot applicable
Water conservation/rain water harvesting/recharge of ground waterYes-
ElectricityYes-
Smart Home AutomationNoNot applicable
CCTV SurveillanceNoNot applicable
Club HouseNoNot applicable
Community HallYes-
Outdoor Sports facilityYes-
Indoor Sports facilityNoNot applicable
Swimming PoolYes-
GymYes-
ParksYes-
Power BackupYes-
GasNoNot applicable
Water and SanitationNoNot applicable
Air Conditioning And incerntionNoNot applicable
StaircasesYes-
LiftsYes-
Staircases and Lift lobbies, corridor,lobbies, corridorYes-
Fire escapesYes-
Common entrance and exit for the building / common portico/foyer/verandahYes-
BasementYes-
TerraceYes-
Outer WallYes-
Open parking areas and common storage spacesYes-
Provision for lodging of management staff and security staffYes-
Water conservation and renewable energyYes-

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area4,596 sq m
Named landownersNone

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 20.00 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectVasanthmadhava R
EngineerYerranna Bhaskar

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EX/PRM/KA/RERA/1251/446/PR/200117/000590Jul 2018 → Jul 2019

Reason as filed by the promoterApplied for modification

Complaints filed with RERA Karnataka

No complaints on record against this registration.

Documents filed58

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/446/PR/171024/000590 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
CertificateFile: Incorporation certificate.jpg-
Architect Certificate for Work Completion Schedule till DateFile: Architecture Copy- Work Completed.pdf-
Engineer Certificate for Work Completion Schedule till DateFile: Engineers copy-work completed.pdf-
CA Certificate for Funds UtilizationFile: CA certificate - funds utilized_compressed.pdf-
Architect Certificate for Pending Work Completion Schedule.File: Architecture Copy-Work Pending.pdf-
Engineer Certificate for Pending Work Completion Schedule.File: Engineers Copy-Work Pending.pdf-
CA Certificate for Funds required for Project CompletionFile: CA certificate - funds required_compressed.pdf-
AffidavitFile: Affidavit.pdf-
Consent letter from 2/3rd of AllotteesFile: consent letter.pdf-
Details Of Sold/ Un-sold UnitsFile: SOLD-UNSOLD-DETAILS.xlsx-
Document 1File: Affidavit.pdf-
Document 2File: HDFC CA -6984.rar-
CC-
Site Plan-
Basement Floor Plan-
proforma sale deed-
proforma sale agreement-
Site Plan-
speck-
RTC-
Ground Floor Plan-
Master site Plan-
allotment letter-
E_brochure_Willow Park-
NOCS (1)-
speck-
6 EC-
khatha certificate-
GPA&JDA Merge-
td1-
CC-
AAI Height cleance-KALKERE-
bangalore electricity-
BWBS-
KSPCB-
BSNL-
Section-
Balance Sheet 2015 - 2016File: BL 2015-2016.pdf-
Balance Sheet 2014 - 2015File: BL 2014-2015.pdf-
Balance Sheet 2013 - 2014File: BL 2013-2014.pdf-
Audited Profit and Loss Statement 2015 - 2016File: P & L 2015-2016.pdf-
Audited Profit and Loss Statement 2014 - 2015File: P & L 2014-2015.pdf-
Audited Profit and Loss Statement 2013 - 2014File: P & L 2013-2014.pdf-
Director's Report 2015 - 2016File: Director Report 2015-2016.pdf-
Director's Report 2014 - 2015File: Director Report 2014-2015.pdf-
Director's Report 2013 - 2014File: Director Report 2013-2014.pdf-
Cash Flow Statement 2015 - 2016File: Cash Flow Statement 2015-2016.pdf-
Cash Flow Statement 2014 - 2015File: Cash Flow Statement 2014-2015.pdf-
Auditor's Report 2015 - 2016File: ITR - 6 - INDES PROJECTS (INDIA) PRIVATE LIMITED_AY1516.pdf-
Auditor's Report 2014 - 2015File: Auditor Report 2014-2015.pdf-
Auditor's Report 2013 - 2014File: ITR - 6 - INDES PROJECTS (INDIA) PRIVATE LIMITED_AY1516.pdf-
Income Tax Return Acknowledgement 2015 - 2016File: ITR ACK 2015-2016.pdf-
Income Tax Return Acknowledgement 2014 - 2015File: ITR ACK 2014-2015.pdf-
Income Tax Return Acknowledgement 2013 - 2014File: ITR ACK 2013-2014.pdf-
DFB-
Prospectus/BrochureFile: WP.LEAFLET.jpg-
Advertisement Copy 1File: WP.LEAFLET.jpg-
Tower Excel SheetFile: PRM_KA_RERA_1251_446_PR_171024_000590.xlsx-

How this compares with Bengaluru Urban

34%of Bengaluru Urban projects moved their completion datethis one moved by 12 months
1%of Bengaluru Urban registrations are shown as withdrawn or revokedthis one is not

Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.

Keep WILLOW PARK on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bengaluru Urban4,100+ in Bengaluru Urban

2 kmWILLOW PARKOther 19Dot size: filed unitsN

Filed coordinates, straight-line distance. 19 registered projects within 2 km.

Builder: INDES PROJECTS (INDIA) PVT LTD

INDES PROJECTS (INDIA) PVT LTD has 2 registrations on RERA Karnataka, including WILLOW PARK and DEWDROPS. Its filings disclose no earlier RERA Karnataka projects. Read the full track record. See more projects on the Bengaluru Urban district page.

Frequently asked questions

What are my rights if WILLOW PARK is delayed beyond 25 Jul 2019?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of WILLOW PARK?

The registered promoter entity is INDES PROJECTS (INDIA) PVT LTD, a company as per the filing. Its CIN U70200KA2012PTC065450 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in WILLOW PARK?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at WILLOW PARK?

The professionals named in the filing: Architect: Vasanthmadhava R; Engineer: Yerranna Bhaskar. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in WILLOW PARK?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About WILLOW PARK. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save WILLOW PARK to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.