White Rose
RG-MH-39609 · RERA P51700019187 · Last updated on MahaRERA portal: 17 Jul 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- 6 complaints at MahaRERA
- Completion date moved by 33 months
- 3 extensions taken
Clear
- No litigation declared
- No encumbrance on the project land
- Separate project account declared
- Allotment letter follows the model form
3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Thane registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
White Rose is a Others project by M/s Eeshan Enterprises in Thane, Maharashtra, registered with MahaRERA as P51700019187 on 9 Jan 2019. Possession is promised by 31 Dec 2026. The completion date has moved by 33 months from the original filing. 142 of the 164 units on this registration are recorded sold or booked, and 13 of 22 construction stages are filed complete. 6 complaints are on record with the regulator.
At a glance
Project
- NameWhite Rose
- TypeOthers
- Location
- Service Road
- Louis Wadi
- Thane (M Corp.)
- Thane
- 400604
- Pincode400604
- MapView location on Google Maps (as filed on RERA)
- RERA no.P51700019187
- ReraGenie IDRG-MH-39609
Builder
- NameM/s Eeshan Enterprises
- Entity typePartnership
- PartnersMUSTAK SAIFAN SHAIKH, RITU TARUN GUPTA, MONIKA DEVENDER GUPTA, NAJMA MUSTAK SHAIKH
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on9 Jan 2019
- Promised completion31 Dec 2026
- Revised completionRevised to 31 Dec 2026 (originally 30 Mar 2024)
- Buildings2 building records
- Documents filed182 files
Current status
Figures as on 17 Jul 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| White Rose Building No B2 | NA | 31 | 30 | 137 | 22 | 159 |
| Krantinagar Rahivashi Sangh Sahakari Grihanirman Sanstha | NA | 26 | 25 | 4 | 1 | 5 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building2
As on 17 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
13 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Internal walls, at 90%.
White Rose Building No B275%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 90% |
| Sanitary Fittings within the flats / premises | 80% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 90% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 90% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 80% |
Krantinagar Rahivashi Sangh Sahakari Grihanirman Sanstha82%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Progress on shared amenities15
As on 17 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 0% |
| Storm Water Drains | Yes | 0% |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | No | Not applicable |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 0% |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | Yes | 70% |
| Fire protection and fire safety requirements | Yes | 75% |
| Electrical meter room, sub-station, receiving station | Yes | 30% |
| Aggregate area of recreational Open Space | Yes | 0% |
| Open Parking | Yes | 0% |
Parking filed411
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Closed/Covered | Open Space | Total |
|---|---|---|---|
| White Rose Building No B2 | 245 | 0 | 245 |
| Krantinagar Rahivashi Sangh Sahakari Grihanirman Sanstha | 158 | 8 | 166 |
Land and ownership
Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| White Rose Building No B2 | NA | Rs 43.81 cr | Rs 43.73 cr |
| Krantinagar Rahivashi Sangh Sahakari Grihanirman Sanstha | NA | Rs 18.41 cr | Rs 17.95 cr |
| - | NA | Rs 6.87 cr | Rs 5.41 cr |
Certifying professionals and partners5
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | NEXSTEP CONSULTANT |
| Engineer | SSCONS CONSULTING STRUCTURAL ENGINEERS |
| Engineer | Rajkumar Bhonde |
| Chartered Accountant | Nilesh G Palande & Associates |
| Chartered Accountant | Rahul Bombale of R V B & Associates |
| Partner | Role in project |
|---|---|
| M/s Eeshan Enterprises | - |
Extensions applied for3
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterDue to covid outbreak for the period March 2020 to February 2022 the project got impacted due to unavailability of labour and material hence project got delayed therefore we seek extension till 31.12.24 to complete the project. Request you to please grant the extension.
Reason as filed by the promoter• The real estate industry went through multiple challenges over the pandemic years with supply chain disruption, labour crisis, and budget crunch slowing down growth. • We have been grappled with shortage of labour and a demand slump challenges triggered by market volatility. Construction rates have shot up and the market has also witnessed the pressure of inflation. • Due to unavailability of skilled labour and labour migration issues, project is affected a lot. Even contractors are asking us to allow them more time due to labour issues. • The geopolitical tension around the globe has led to
Reason as filed by the promoter•The extension is essential to maintain the validity of the project registration. Without the extension, the registration will lapse, which will: halt ongoing construction work, stall disbursement of home loans by banks / financial institutions Institutions, prevent registration of new agreements for sale, and result in severe cash flow disruption, adversely affecting allottees. •The project has been delayed due to circumstances beyond the control of the Promoter, such as shortage of labour and demand slump triggered by market volatility. Unavailability of skilled labour and labour migration i
Complaints filed with MahaRERA6
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CC006000000591132 | INDERJIT KAUR PANESAR | EESHAN ENTERPRISES | 11/07/2024 |
| CC12501653 | Prashant jadhav | M/s Eeshan Enterprises | 21/05/2025 |
| CC12502426 | Daniel Anthony Noronha | M/s Eeshan Enterprises | 16/07/2025 |
| CC12601394 | Madhura Nandan Khambete | M/s Eeshan Enterprises | 13/03/2026 |
| CC12601673 | Anand Rabhaji Navale | M/s Eeshan Enterprises | 24/03/2026 |
| CC12602472 | Amit Ashok Pangam | M/s Eeshan Enterprises | 27/04/2026 |
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 28 Dec 2018 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 19 Jul 2024 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 19 Jul 2024 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 19 Jul 2024Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateOn the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
uploaded 27 Jul 2024
Documents filed182
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 182 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Withdrawal Update Form 1File: Eeshan Form 1 (1).pdf | 17 Jul 2026 |
| Withdrawal Update Form 2File: Eeshan Form 2 (1).pdf | 17 Jul 2026 |
| Withdrawal Update Form 3File: Eeshan Form 3 (1).pdf | 17 Jul 2026 |
| Form 2A (FY 2025-2026)File: Form 2A FY 25-26 .pdf | 16 May 2026 |
| Withdrawal Update Form 1File: Eeshan Form 1 (1).pdf | 5 May 2026 |
| Withdrawal Update Form 2File: Eeshan Form 2 (1).pdf | 5 May 2026 |
| Withdrawal Update Form 3File: Eeshan Form 3 (1)_11zon.pdf | 5 May 2026 |
| Form 5 (FY 2024-2025)File: Signed_Form 5_FY 2024-25.pdf | 6 Feb 2026 |
| Withdrawal Update Form 1File: SIGN_FORM 1.pdf | 5 Feb 2026 |
| Withdrawal Update Form 2File: SIGN_FORM 2.pdf | 5 Feb 2026 |
| Withdrawal Update Form 3File: SIGN_FORM 3_compressed.pdf | 5 Feb 2026 |
| Withdrawal Update Form 1File: Eeshan Form 1 sign.pdf | 6 Dec 2025 |
| Withdrawal Update Form 2File: Form 2_Q2.pdf | 6 Dec 2025 |
| Withdrawal Update Form 3File: Form 3_Q2.pdf | 6 Dec 2025 |
| Withdrawal Update Form 1File: Eeshan Form 1 June 25.pdf | 4 Oct 2025 |
| Withdrawal Update Form 2File: Eeshan Form 2 june 25.pdf | 4 Oct 2025 |
| Withdrawal Update Form 3File: Eeshan Form 3 June 25.pdf | 4 Oct 2025 |
| Form 2A (FY 2024-2025)File: eeshan form 2A (1).pdf | 29 Jul 2025 |
| Form 1File: EESHAN_FORM 1_Q3_FY24-25.pdf | 13 Jun 2025 |
| Form 2File: EESHAN_FORM 2_31st Dec 2024.pdf | 13 Jun 2025 |
| Form 3File: Form 3_Q3_FY 2024-25.pdf | 13 Jun 2025 |
| Disclosure of Sold and Booked InventoryFile: Disclosure Of Sold Inventory 31 dec 24.pdf | 13 Jun 2025 |
| OthersFile: Declarations.pdf | 13 Jun 2025 |
| Form 1File: EESHAN_FORM 1_Q4_FY24-25.pdf | 13 Jun 2025 |
| Form 2File: EESHAN_FORM 2_31st Mar 2025.pdf | 13 Jun 2025 |
| Form 3File: Form 3_White Rose_Q4_FY 2024-25_compressed.pdf | 13 Jun 2025 |
| OthersFile: Declarations Merged.pdf | 13 Jun 2025 |
| Disclosure of Sold and Booked InventoryFile: Disclosure Of Sold Inventory 31 Mar 25.pdf | 13 Jun 2025 |
| Details of encumbrances concerned to FinanceFile: Annexure K-Non-Encumbrance Concerned to Finance and Legal.pdf | 19 May 2025 |
| CERSAI detailsFile: Annexure G-Asset Based Declaration.pdf | 19 May 2025 |
| CERSAI detailsFile: Annexure L- Debtor Based Declaration.pdf | 19 May 2025 |
| Details of encumbrances concerned to LegalFile: Annexure K-Non-Encumbrance Concerned to Finance and Legal.pdf | 19 May 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: EESHAN_FORM 1_Q3_FY24-25.pdf | 3 Mar 2025 |
| Certificates of CA (Form 3)File: Form 3_Q3_FY 2024-25_compressed.pdf | 3 Mar 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: EESHAN_FORM 2_31st Dec 2024.pdf | 3 Mar 2025 |
| Disclosure of sold/ booked inventoryFile: Disclosure Of Sold Inventory 31 dec 24.pdf | 3 Mar 2025 |
| Details of encumbrances concerned to FinanceFile: Eeshan_ Financial And Legal Encumbrance position-1.pdf | 24 Feb 2025 |
| CERSAI detailsFile: Asset Based Declaration.pdf | 24 Feb 2025 |
| CERSAI detailsFile: Debtor Based Declaration.pdf | 24 Feb 2025 |
| Details of encumbrances concerned to LegalFile: Eeshan_ Financial And Legal Encumbrance position-1.pdf | 24 Feb 2025 |
| Declaration about Commencement CertificateFile: EESHAN DECLARATION_FORMAT D.pdf | 24 Dec 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: EESHAN_FORM -5_FY 23-24.pdf | 24 Dec 2024 |
| Details of encumbrances concerned to FinanceFile: Non-Encumbrance concerned to Legal and Finance.pdf | 21 Dec 2024 |
| Declaration in FORM BFile: FORM-'B'-Affidavit_Compressed.pdf | 21 Dec 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: EESHAN_ FORM 1_30th NOV 2024 final.pdf | 21 Dec 2024 |
| Certificates of CA (Form 3)File: Final Form 3_Q4_V2 compressed.pdf | 21 Dec 2024 |
| Certificates of CA (Form 3)File: Form 3_Q1_Fy 2024-25_V2_compressed.pdf | 21 Dec 2024 |
| Certificates of CA (Form 3)File: Final Form 3_Q2_FY_2024-25_V2_compressed.pdf | 21 Dec 2024 |
| Certificates of CA (Form 3)File: EESHAN_FORM-3 upto 30-11-24.pdf | 21 Dec 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: EESHAN_FORM 2_30th Nov 2024.pdf | 21 Dec 2024 |
| Disclosure of sold/ booked inventoryFile: Disclosure of sold-unsold as on 30 nov 24 revised final_compressed.pdf | 21 Dec 2024 |
| CERSAI detailsFile: Asset Based declaration.pdf | 21 Dec 2024 |
| CERSAI detailsFile: Debtor Based Declaration.pdf | 21 Dec 2024 |
| Details of encumbrances concerned to LegalFile: Non-Encumbrance concerned to Legal and Finance.pdf | 21 Dec 2024 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosure of Interest in Other Real Estate Organizations_MONIKA GUPTA.pdf | 21 Dec 2024 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosure of Interest in Other Real Estate Organizations_MUSTAK SHAIKH.pdf | 21 Dec 2024 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosure of Interest in Other Real Estate Organizations_Najma Shaikh.pdf | 21 Dec 2024 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosure of Interest in Other Real Estate Organizations_RITU GUPTA.pdf | 21 Dec 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: EESHAN_ FORM 2A.pdf | 21 Dec 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: EESHAN_FORM -1_MARCH 24.pdf | 17 Dec 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: EESHAN_FORM -1_JUNE 24.pdf | 17 Dec 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: EESHAN_FORM -1_SEPTEMBER 24.pdf | 17 Dec 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: EESHAN_ FORM 2_SEPTEMBER 2024.pdf | 17 Dec 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: EESHAN_ FORM 2_JUNE 2024.pdf | 17 Dec 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: EESHAN_ FORM 2_MARCH 2024.pdf | 17 Dec 2024 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: OC PART GR FLOOR TO 1ST FLOOR REHAB BLDG.pdf | 27 Jul 2024 |
| Layout approvalFile: Layout Oct 222.pdf | 19 Jul 2024 |
| Building plan approvalFile: Building plan.pdf | 19 Jul 2024 |
| Copy of Layout Approval (in case of layout)File: Layout Oct 222.pdf | 19 Jul 2024 |
| Building Plan Approval (IOD)File: Building plan.pdf | 19 Jul 2024 |
| Commencement Certificates / NA Order for plotted developmentFile: CC-1.pdf | 19 Jul 2024 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: scan .pdf | 19 Jul 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 30th sep 23.pdf | 6 Feb 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 31st dec 23.pdf | 6 Feb 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 31st dec 23.pdf | 6 Feb 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 30th sep 23.pdf | 6 Feb 2024 |
| Disclosure of sold/ booked inventoryFile: SOLD UNSOLD 30th sep 23.pdf | 6 Feb 2024 |
| Disclosure of sold/ booked inventoryFile: SOLD UNSOLD 31st dec 23.pdf | 6 Feb 2024 |
| Certificates of CA (Form 3)File: Form 3 30th sept 23.pdf | 6 Feb 2024 |
| Certificates of CA (Form 3)File: Form 3 31st dec 23_compressed.pdf | 6 Feb 2024 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Thane
Computed across the 7,600+ Thane projects on ReraGenie, from their own filings.
Free monthly report: Thane on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 3 conditions on this project's record read and explained, with the clear checks alongside
- Joined against every project registered within 2 km, which the RERA portal never shows together
- All 182 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep White Rose on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Louis Wadi7,600+ in Thane
Filed coordinates, straight-line distance. 343 registered projects within 2 km.
Dosti 604
Dosti Corporation Business Park
ONE ARTHASYA
TOP FLOOR REALTY LLP
ASHAR MERAC PHASE I
AJAY PRATAP ASHAR
EMPERIA I PARK
MANOMETER (INDIA) LLP
Ace Signature IT Park
Yojit Builder
O22 Business Park
MIDAS TOUCH
See every Thane project, with the district possession charts
Builder: M/s Eeshan Enterprises
M/s Eeshan Enterprises has 1 registration on MahaRERA, including White Rose. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Thane district page.
Frequently asked questions
What are my rights if White Rose is delayed beyond 31 Dec 2026?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of White Rose?
The registered promoter entity is M/s Eeshan Enterprises, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in White Rose?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against White Rose?
Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
How current is the construction progress shown for White Rose?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at White Rose?
The professionals named in the filing: Architect: NEXSTEP CONSULTANT; Engineer: SSCONS CONSULTING STRUCTURAL ENGINEERS; Engineer: Rajkumar Bhonde; Chartered Accountant: Nilesh G Palande & Associates; Chartered Accountant: Rahul Bombale of R V B & Associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in White Rose?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback