WHITE LOTUS OHANA
By WHITE LOTUS LIFESCAPES PRIVATE LIMITED
RG-KA-54763 · RERA PRM/KA/RERA/1251/309/PR/190809/002762
Source: official RERA Karnataka filing
Red flags
- Completion date moved by 21 months
- 2 extensions taken
Clear
- No complaints on record
- Separate project account declared
Saved.
WHITE LOTUS OHANA is a Residential/Group Housing project by WHITE LOTUS LIFESCAPES PRIVATE LIMITED in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/309/PR/190809/002762 on 9 Aug 2019. Possession is promised by 30 Jan 2024. The completion date has moved by 21 months from the original filing.
At a glance
Project
- NameWHITE LOTUS OHANA
- TypeResidential/Group Housing
- Location
- Bengaluru North
- Bengaluru Urban
- PincodeNot stated
- MapView location on Google Maps (as filed on RERA)
- RERA no.PRM/KA/RERA/1251/309/PR/190809/002762
- ReraGenie IDRG-KA-54763
Builder
- NameWHITE LOTUS LIFESCAPES PRIVATE LIMITED
- Entity typeCompany
- CINU45201KA2010PTC056108
- Authorized SignatoryPAVAN KUMAR ADAPA
- DirectorsDEEPTI PREMCHANDRA, PAVAN KUMAR ADAPA
- Declared earlier projects1 →
Key dates
Key facts
Registration and timeline
- StatusRegistration approved
- Registered on9 Aug 2019
- Promised completion30 Jan 2024
- Revised completionRevised to 30 Jan 2024 (originally 30 Apr 2022)
- Buildings1 building record
- Documents filed56 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| White Lotus OHANA | - | - | - | 15 | 0 | 15 |
The full filing
Everything below is from the project's own RERA Karnataka filing, free to read.
Construction progress by building1
The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
Building:
| Activity | Progress |
|---|---|
| Earth work and other leveling preparation work | - |
| Foundation footing work | - |
| Retaining wall (All types) | - |
| Plinth level Beam | Not applicable |
| Sub-structure flooring (Parking Floor, more than one floor below general ground level) | - |
| RCC or MS Framed structure | - |
| Masonry construction: Bricks, Concrete blocks etc | - |
| Plastering inside , outside & Ceiling | - |
| Joinery: Doors, Windows, Ventilators etc | - |
| Basic work of Water supply, Sanitary and Electrification | - |
| Dadoing, Skirting, Flooring, Tiles work (All types) | - |
| Railing and Grill fixing | - |
| Electrification, Water supply and Sanitary Finishing | - |
| Wardrobe, Showcase, Kitchen cabinet, Puja work | Not applicable |
| Fire prevention and fire fighting fitting and fixture with network | Not applicable |
| Weather Proof work(tile,concrete) | - |
| Painting | - |
| Elevation work | - |
| Internal and External work including landscapes as per santioned drawings | - |
Progress on shared amenities41
Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Water Supply | Yes | - |
| Internal Roads & Footpaths | No | Not applicable |
| Sewage and Drainage System | Yes | - |
| Parks & Tree planting | No | Not applicable |
| Street Lighting | No | Not applicable |
| Provision for community buildings and for treatment and disposal of sewage and sullage water | Yes | - |
| Solid waste management and disposal | No | Not applicable |
| Water conservation | No | Not applicable |
| Energy management | Yes | - |
| Fire protection and fire safety requirements | No | Not applicable |
| Education/Health/Other public amenities | Yes | - |
| Electricity supply transformer and substation | Yes | - |
| Emergency Evacuation services | No | Not applicable |
| Storm water drains | Yes | - |
| Use of renewable energy | No | Not applicable |
| Water conservation/rain water harvesting/recharge of ground water | Yes | - |
| Electricity | Yes | - |
| Smart Home Automation | Yes | - |
| CCTV Surveillance | Yes | - |
| Club House | No | Not applicable |
| Community Hall | No | Not applicable |
| Outdoor Sports facility | No | Not applicable |
| Indoor Sports facility | No | Not applicable |
| Swimming Pool | No | Not applicable |
| Gym | Yes | - |
| Parks | No | Not applicable |
| Power Backup | Yes | - |
| Gas | No | Not applicable |
| Water and Sanitation | Yes | - |
| Air Conditioning And incerntion | No | Not applicable |
| Staircases | Yes | - |
| Lifts | Yes | - |
| Staircases and Lift lobbies, corridor,lobbies, corridor | Yes | - |
| Fire escapes | Yes | - |
| Common entrance and exit for the building / common portico/foyer/verandah | Yes | - |
| Basement | Yes | - |
| Terrace | Yes | - |
| Outer Wall | Yes | - |
| Open parking areas and common storage spaces | No | Not applicable |
| Provision for lodging of management staff and security staff | No | Not applicable |
| Water conservation and renewable energy | Yes | - |
Land and ownership
This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Project account and cost
70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners2
Certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | 1 LeapingFrog Studio |
| Engineer | Rajesh Consultants |
Extensions applied for2
A revised date filed with the regulator does not change the possession date in your agreement for sale.
No reason recorded in the filing
Reason as filed by the promoterShortage of Building Materials, Concrete, Jalli etc
Complaints filed with RERA Karnataka
No complaints on record against this registration.
Documents filed56
As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/309/PR/190809/002762 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| CertificateFile: Fresh Certificate of Incorporation Consequent upon Change of Name-060213.pdf | - |
| Architect Certificate for Work Completion Schedule till DateFile: Signed _ Architect's Certificate Form 1.pdf | - |
| Engineer Certificate for Work Completion Schedule till DateFile: Signed _ Engineer's Certificate Form 5.PDF | - |
| CA Certificate for Funds UtilizationFile: Form Ex3 _Project Ohana_dtd 28-02-23_Signed.pdf | - |
| Architect Certificate for Pending Work Completion Schedule.File: Signed _ Architect's Certificate Form 2.pdf | - |
| Engineer Certificate for Pending Work Completion Schedule.File: Signed _ Engineer's Certificate Form 6.PDF | - |
| CA Certificate for Funds required for Project CompletionFile: Form Ex4 _Project Ohana_dtd 28-02-23-Signed.pdf | - |
| AffidavitFile: FROM - EX7 (1).pdf | - |
| Latest Encumbrance CertificateFile: EC (1) (1).pdf | - |
| Details Of Sold/ Un-sold UnitsFile: OHANA.xlsx | - |
| Document 1File: Clarification - Consent of Land Owners.pdf | - |
| Document 2File: FORM B.pdf | - |
| Commencement Certificate | - |
| BUILDING SANCTION PLAN | - |
| BUILDING SANCTION PLAN | - |
| Proforma - SALE DEED | - |
| Proforma - AOS & CA | - |
| Title Documents | - |
| Receipt & Letter for Ohana Plan Sanction - Jan 2019 | - |
| BUILDING SANCTION PLAN | - |
| Allotment Letter | - |
| White Lotus Ohana Brochure - Small Size | - |
| Specifications - Ohana @ Wellington Street, Richmond Road | - |
| EC | - |
| Section 3 - Affidavit | - |
| KATHA | - |
| JDAs | - |
| NOC - AIRPORT | - |
| NOC - BESCOM | - |
| NOC - BWSSB | - |
| NOC - KSPCB | - |
| BUILDING SANCTION PLAN | - |
| BUILDING SANCTION PLAN | - |
| Change of Land Use - OHANA | - |
| Legal Opinion | - |
| Balance Sheet 2017 - 2018File: BS 18.pdf | - |
| Balance Sheet 2016 - 2017File: BS 17.pdf | - |
| Balance Sheet 2015 - 2016File: BS 16.pdf | - |
| Audited Profit and Loss Statement 2017 - 2018File: PL 18.pdf | - |
| Audited Profit and Loss Statement 2016 - 2017File: PL 17.pdf | - |
| Audited Profit and Loss Statement 2015 - 2016File: PL 16.pdf | - |
| Director's Report 2017 - 2018File: DR 18.pdf | - |
| Director's Report 2016 - 2017File: DR 17.pdf | - |
| Director's Report 2015 - 2016File: DR 16.pdf | - |
| Cash Flow Statement 2017 - 2018File: Cash Flow - 18.pdf | - |
| Cash Flow Statement 2016 - 2017File: Cash Flow - 17.pdf | - |
| Auditor's Report 2017 - 2018File: AR 18.pdf | - |
| Auditor's Report 2016 - 2017File: AR 17.pdf | - |
| Auditor's Report 2015 - 2016File: AR 16.pdf | - |
| Income Tax Return Acknowledgement 2017 - 2018File: ITR 18.pdf | - |
| Income Tax Return Acknowledgement 2016 - 2017File: ITR 17.pdf | - |
| Income Tax Return Acknowledgement 2015 - 2016File: ITR 16.pdf | - |
| Form B - Declaration | - |
| Prospectus/BrochureFile: White Lotus Ohana Brochure - Small Size.pdf | - |
| Advertisement Copy 1File: White Lotus Ohana Brochure - Small Size.pdf | - |
| Tower Excel SheetFile: PRM_KA_RERA_1251_309_PR_190809_002762.xlsx | - |
Promoter's earlier projects1
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Status | Promised | Delivered |
|---|---|---|---|---|
| WHITE LOTUS KALPAVRIKSHA | - | Ongoing | Jun 2021 | Not delivered |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Bengaluru Urban
Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.
Keep WHITE LOTUS OHANA on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Bengaluru Urban4,100+ in Bengaluru Urban
Filed coordinates, straight-line distance. 14 registered projects within 2 km.
Prestige Park Grove
PRESTIGE PROJECTS PRIVATE LIMITED
Prestige Lakeside Habitat
Prestige Habitat Ventures
LivingTree by Kalyani Developers
Kalyani Tech Park Private Limited
PRESTIGE FALCON CITY
PRESTIGE NOTTINGHILL INVESTMENTS
SATTVA CITY
SATTVA CITY PRIVATE LIMITED
GM AMBITIOUS ENCLAVE
M/s. Allam Infinite India Private Limited
See every Bengaluru Urban project, with the district possession charts
Builder: WHITE LOTUS LIFESCAPES PRIVATE LIMITED
WHITE LOTUS LIFESCAPES PRIVATE LIMITED has 1 registration on RERA Karnataka, including WHITE LOTUS OHANA. Its filings declare 1 earlier project, none of them declared completed. Read the full track record. See more projects on the Bengaluru Urban district page.
Frequently asked questions
What are my rights if WHITE LOTUS OHANA is delayed beyond 30 Jan 2024?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.
How do I verify and contact the developer of WHITE LOTUS OHANA?
The registered promoter entity is WHITE LOTUS LIFESCAPES PRIVATE LIMITED, a company as per the filing. Its CIN U45201KA2010PTC056108 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.
Is my payment protected in WHITE LOTUS OHANA?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
Who certifies construction progress at WHITE LOTUS OHANA?
The professionals named in the filing: Architect: 1 LeapingFrog Studio; Engineer: Rajesh Consultants. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in WHITE LOTUS OHANA?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.