RG-KA-28576 · RERA PRM/KA/RERA/1251/309/PR/090523/005920 · Last updated on RERA Karnataka portal: 13 Jul 2026
Source: official RERA Karnataka filing
Red flags
- Completion date moved by 12 months
- 1 extension taken
Clear
- No litigation declared
- No complaints on record
- Separate project account declared
Saved.
Vruksha Greens is a Residential/Group Housing project by Vruksha Infra in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/309/PR/090523/005920 on 9 May 2023. Possession is promised by 30 Jun 2027. The completion date has moved by 12 months from the original filing. 24 of the 80 units on this registration are recorded sold or booked, and 6 of 16 construction stages are filed complete.
At a glance
Project
- NameVruksha Greens
- TypeResidential/Group Housing
- Location
- Bengaluru North
- Bengaluru Urban
- 560015
- Pincode560015
- MapView location on Google Maps (as filed on RERA)
- RERA no.PRM/KA/RERA/1251/309/PR/090523/005920
- ReraGenie IDRG-KA-28576
Builder
- NameVruksha Infra
- Entity typePartnership Firm
- Authorized SignatoryRajagopal Desu
Key dates
Key facts
Registration and timeline
- StatusRegistration approved
- Registered on9 May 2023
- Promised completion30 Jun 2027
- Revised completionRevised to 30 Jun 2027 (originally 30 Jun 2026)
- Buildings1 building record
- Documents filed133 files
Current status
Figures as on 13 Jul 2026, this project's latest RERA Karnataka filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| Vruksha Greens | - | - | - | 80 | 0 | 80 |
The full filing
Everything below is from the project's own RERA Karnataka filing, free to read.
Construction progress by building1
As on 13 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
6 of 16 construction stages are filed complete. The stage furthest along is Basic work of Water supply, at 98%.
Building: 63% average across the applicable activities
| Activity | Progress |
|---|---|
| Earth work and other leveling preparation work | 100% |
| Foundation footing work | 100% |
| Upto Plinth Level | 100% |
| Sub-structure flooring (Parking Floor, more than one floor below general ground level) | 95% |
| Retaining wall (All types) | 100% |
| RCC or MS Framed structure | 100% |
| Masonry Construction | 100% |
| Plastering inside , outside & Ceiling | 95% |
| Joinery: Doors, Windows, Ventilators etc | 0% |
| Basic work of Water supply, Sanitary and Electrification | 98% |
| Dadoing, Skirting, Flooring, Tiles work (All types) | 9% |
| Railing and Grill fixing | 88% |
| Electrification, Water supply and Sanitary Finishing | 0% |
| Painting | 7% |
| Fire prevention and fire fighting fitting and fixture with network | Not applicable |
| Weather Proof work(tile,concrete) | 0% |
| Wardrobe, Showcase, Kitchen cabinet, Puja work | Not applicable |
| Elevation work | 10% |
| Internal and External work including landscapes as per sanctioned drawings | Not applicable |
Progress on shared amenities40
As on 13 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Water Supply | Yes | 0% |
| Sewage and Drainage System | No | Not applicable |
| Water conservation/rain water harvesting/recharge of ground water | No | Not applicable |
| Energy management | No | Not applicable |
| Fire protection and fire safety requirements | No | Not applicable |
| Solid waste management and disposal | No | Not applicable |
| Emergency Evacuation services | No | Not applicable |
| Internal Roads & Footpaths | No | Not applicable |
| Electricity supply transformer and substation | Yes | 0% |
| Storm water drains | No | Not applicable |
| Use of renewable energy | No | Not applicable |
| Sewage Treatment Plant (STP) | Yes | 0% |
| Parks & Tree planting | Yes | 0% |
| Street Lighting | No | Not applicable |
| Electricity | Yes | 0% |
| Smart Home Automation | No | Not applicable |
| CCTV Surveillance | No | Not applicable |
| Club House | No | Not applicable |
| Community Hall | No | Not applicable |
| Outdoor Sports facility | No | Not applicable |
| Indoor Sports facility | No | Not applicable |
| Swimming Pool | No | Not applicable |
| Gym | No | Not applicable |
| Parks | No | Not applicable |
| Power Backup | Yes | 0% |
| Piped Gas | No | Not applicable |
| Water and Sanitation | Yes | 0% |
| Air Conditioning | No | Not applicable |
| Staircases | Yes | 0% |
| Lifts | Yes | 0% |
| Corridor/Lobbies | No | Not applicable |
| Fire escapes | No | Not applicable |
| Common entrance and exit for the building/common portico/foyer/verandah | No | Not applicable |
| Basement | Yes | 90% |
| Terrace | Yes | 50% |
| Outer Wall | No | Not applicable |
| Open parking areas | No | Not applicable |
| Provision for lodging of management staff and security staff | Yes | 0% |
| Water conservation and renewable energy | No | Not applicable |
| Common storage spaces | No | Not applicable |
Land and ownership1
This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
| Landowner | Village | District |
|---|---|---|
| S Suresh Kumar | - | - |
Project account and cost
70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Cost line | Estimated | Incurred |
|---|---|---|
| Estimated Cost of Construction as certified by Engineer | Rs 25.00 cr | Rs 9.66 cr |
| On-site expenditure-Site Overhead | - | Rs 4.69 cr |
| Payment of taxes | - | Rs 2.88 lakh |
| Principal sum and interest payable to financial institutions-Non Banking financial institution (NBFC) | - | Rs 1.44 cr |
Certifying professionals and partners3
Certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Mayur G Kulkarni |
| Engineer | Ramesh S |
| Chartered Accountant | A Yella Reddy |
Extensions applied for1
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterShortage of Labour
Complaints filed with RERA Karnataka
No complaints on record against this registration.
Documents filed133
As listed on the registration, under the names the promoter filed them with; the newest 80 of 133 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/309/PR/090523/005920 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Covering Letter - Letter HeadFile: 1 Covering Letter - Letter Head.pdf | 13 Jul 2026 |
| Engineer Certificate_New_Self AttestedFile: 2 Engineer Certificate_New_Self Attested.pdf | 13 Jul 2026 |
| NOC non renewal Affidavit and NOC'sFile: 3 NOC non renewal Affidavit.pdf | 13 Jul 2026 |
| Q4 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Form-4, CA V Greens Rera Q4-FY 25-26.pdf | 15 Apr 2026 |
| Q4 2025-26 Form-5 Certificate issued by ArchitectFile: Form-5, Architect V Greens Rera Q4-FY 25-26.pdf | 15 Apr 2026 |
| Q4 2025-26 Form-6 Certificate issued by Structural EngineerFile: Form-6, Engineer V Greens Rera Q4-FY 25-26.pdf | 15 Apr 2026 |
| Q4 2025-26 Water supply and sewage board | 15 Apr 2026 |
| Q4 2025-26 KSPCB- PCB (10 Acres to 125 Acres) | 15 Apr 2026 |
| Q4 2025-26 KPTCL- BESCOM | 15 Apr 2026 |
| Q3 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Form-4, CA V Greens Rera Q3-FY 25-26.pdf | 18 Feb 2026 |
| Q3 2025-26 Form-5 Certificate issued by ArchitectFile: VI_Form5_Arch-2025-26-Q3.pdf | 18 Feb 2026 |
| Q3 2025-26 Form-6 Certificate issued by Structural EngineerFile: Form-6, Engineer V Greens Rera Q3-FY 25-26.pdf | 18 Feb 2026 |
| Q3 2025-26 Water supply and sewage board | 18 Feb 2026 |
| Q3 2025-26 KSPCB- PCB (10 Acres to 125 Acres) | 18 Feb 2026 |
| Q3 2025-26 KPTCL- BESCOM | 18 Feb 2026 |
| BS & PL 19-20File: 19-20.pdf | 6 May 2023 |
| BS & PL 20-21File: 20-21.pdf | 6 May 2023 |
| BS & PL 21-22File: 21-22.pdf | 6 May 2023 |
| CA Certificate on Tax ReturnsFile: certifivate CA.pdf | 6 May 2023 |
| Shettihalli Mother DeedFile: Shettihalli Mother Deed.pdf | 6 May 2023 |
| SHETTIHALLI RTC1 22-23File: SHETTIHALLIU RTC 22-23 (1).pdf | 6 May 2023 |
| SHETTIHALLIU RTC2 22-23File: SHETTIHALLIU RTC 22-23.pdf | 6 May 2023 |
| Shettihalli AC ORDERFile: Shettihalli AC ORDER.pdf | 6 May 2023 |
| - JA cum DECLFile: 3 - JA cum DECL.pdf | 6 May 2023 |
| FORM BFile: 4 - Form-B.pdf | 6 May 2023 |
| Guidance ValueFile: Guidance Value.pdf | 6 May 2023 |
| ECFile: EC.pdf | 6 May 2023 |
| EC2File: 40-EC.pdf | 6 May 2023 |
| CDPFile: 3 - CDP Map_Settyhalli 28 LU V1.pdf | 6 May 2023 |
| Village mapFile: 4 - Village Map_Settyhalli 28 RC.pdf | 6 May 2023 |
| Architects certificateFile: 7-Architect RC.pdf | 6 May 2023 |
| Section 3(1) notarized affidavitFile: 4 - Affidavit 3(1).pdf | 6 May 2023 |
| Project specificationFile: 5 - Vruksha Greens - Project Specification.pdf | 6 May 2023 |
| BWSSB ClarificationFile: 6 - BWSSB - NA.pdf | 6 May 2023 |
| Borewell 1File: Borewell1.jpeg | 6 May 2023 |
| Borewell 2File: Borewell2.jpeg | 6 May 2023 |
| Brief estimateFile: 7 - Estimation-Constuction cost-Civil work.pdf | 6 May 2023 |
| BESCOM NOC Fee Paid ReceiptFile: 8 - Bescom NOC Fee Receipt.pdf | 6 May 2023 |
| STP design drawingFile: 9 STP design drawing.pdf | 6 May 2023 |
| STP demarcationFile: 9 STP Demarcation.pdf | 6 May 2023 |
| Floor PlanFile: 9 Floor Plan.pdf | 6 May 2023 |
| STP Location in the planFile: STP Location in the plan.pdf | 6 May 2023 |
| AOSFile: 86-Agreement of Sale Proforma.pdf | 6 May 2023 |
| RTC, survey 28/1 | - |
| Mutation, survey 28/1 | - |
| Encumbrance Certificate, survey 28/1 | - |
| Conversion/Alienation Order, survey 28/1 | - |
| Sale/Title/Gift Deed, survey 28/1 | - |
| JDA, survey 28/1 | - |
| Khatha, survey 28/1 | - |
| Registration CertificateFile: 01-Vruksha Partnership RC.pdf | - |
| Partnership DeedFile: 17-Vruksha Partnershipdeed.pdf | - |
| Partner Details | - |
| Partner Details | - |
| Partner Details | - |
| Certificate issued by CA Form 1File: 56, 57 -Form 1 - CA Certificate.pdf | - |
| Certificate issued by Architect Form 2File: 59-Form 2 - Architect.pdf | - |
| Certificate issued by Engineer Form 3File: 58-Form 3 - Engineer.pdf | - |
| Project Chartered Accountant | - |
| Project Engineer | - |
| Project Architect | - |
| AffidavitFile: 45-Non-Litidation Affidavit.pdf | - |
| Certificate from Chartered AccountFile: 56, 57 -Form 1 - CA Certificate.pdf | - |
| Balance Sheet 2021 - 2022File: 60-Balance Sheet-NA.pdf | - |
| Balance Sheet 2020 - 2021File: 60-Balance Sheet-NA.pdf | - |
| Balance Sheet 2019 - 2020File: 60-Balance Sheet-NA.pdf | - |
| Audited Profit and Loss Statement 2021 - 2022File: 61-Audited P&L.pdf | - |
| Audited Profit and Loss Statement 2020 - 2021File: 61-Audited P&L.pdf | - |
| Audited Profit and Loss Statement 2019 - 2020File: 61-Audited P&L.pdf | - |
| Director's Report 2021 - 2022File: 62-Directors Report-NA.pdf | - |
| Director's Report 2020 - 2021File: 62-Directors Report-NA.pdf | - |
| Director's Report 2019 - 2020File: 62-Directors Report-NA.pdf | - |
| Cash Flow Statement 2021 - 2022File: 63-Cash Flow Statement-NA.pdf | - |
| Cash Flow Statement 2020 - 2021File: 63-Cash Flow Statement-NA.pdf | - |
| Auditor's Report 2021 - 2022File: 64-Auditors Report-NA.pdf | - |
| Auditor's Report 2020 - 2021File: 64-Auditors Report-NA.pdf | - |
| Auditor's Report 2019 - 2020File: 64-Auditors Report-NA.pdf | - |
| Income Tax Return Acknowledgement 2021 - 2022File: 65-IT Returs Ack-NA.pdf | - |
| Income Tax Return Acknowledgement 2020 - 2021File: 65-IT Returs Ack-NA.pdf | - |
| Income Tax Return Acknowledgement 2019 - 2020File: 65-IT Returs Ack-NA.pdf | - |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Bengaluru Urban
Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.
Keep Vruksha Greens on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Bengaluru Urban4,100+ in Bengaluru Urban
Filed coordinates, straight-line distance. 5 registered projects within 2 km.
Prestige Park Grove
PRESTIGE PROJECTS PRIVATE LIMITED
Prestige Lakeside Habitat
Prestige Habitat Ventures
LivingTree by Kalyani Developers
Kalyani Tech Park Private Limited
PRESTIGE FALCON CITY
PRESTIGE NOTTINGHILL INVESTMENTS
SATTVA CITY
SATTVA CITY PRIVATE LIMITED
GM AMBITIOUS ENCLAVE
M/s. Allam Infinite India Private Limited
See every Bengaluru Urban project, with the district possession charts
Builder: Vruksha Infra
Vruksha Infra has 1 registration on RERA Karnataka, including Vruksha Greens. Its filings disclose no earlier RERA Karnataka projects. Read the full track record. See more projects on the Bengaluru Urban district page.
Frequently asked questions
What are my rights if Vruksha Greens is delayed beyond 30 Jun 2027?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.
How do I verify and contact the developer of Vruksha Greens?
The registered promoter entity is Vruksha Infra, a partnership firm as per the filing. Neither this filing nor this promoter's other RERA Karnataka registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.
Is my payment protected in Vruksha Greens?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
Who certifies construction progress at Vruksha Greens?
The professionals named in the filing: Architect: Mayur G Kulkarni; Engineer: Ramesh S; Chartered Accountant: A Yella Reddy. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Vruksha Greens?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.
Report an error Share feedback