Home / Browse projects / Pune, Maharashtra / VISHWAVIHAR
VISHWAVIHAR
By VISHWA DEVELOPER & PROMOTER
RG-MH-19700 · RERA P52100006484 · Last updated on MahaRERA portal: 25 Feb 2025
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Registration lapsed
- Possession 39 months past the filed date
Clear
- No litigation declared
- No complaints on record
- Completion date never moved
- Separate project account declared
- Allotment letter follows the model form
2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
VISHWAVIHAR is a Residential / Group Housing project by VISHWA DEVELOPER & PROMOTER in Pune, Maharashtra, registered with MahaRERA as P52100006484 on 14 Aug 2017. Possession was promised by 23 Jul 2023 and is now 39 months past that date.
At a glance
Project
- NameVISHWAVIHAR
- TypeResidential / Group Housing
- Location
- Manchar (CT)
- Ambegaon
- Pune
- 410503
- Pincode410503
- MapView location on Google Maps (as filed on RERA)
- RERA no.P52100006484
- ReraGenie IDRG-MH-19700
Key dates
Key facts
Registration and timeline
- StatusRegistration lapsed
- Registered on14 Aug 2017
- Promised completion23 Jul 2023
- Revised completionNone
- Buildings3 building records
- Documents filed89 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| WING A | NA | 5 | 4 | 0 | 0 | 0 |
| WING B | NA | 5 | 4 | 0 | 0 | 0 |
| WING C | NA | 5 | 4 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building3
As on 25 Feb 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
22 of 33 construction stages are filed complete across 3 buildings. The stage furthest along is Internal walls, at 60%.
WING A82%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
WING B82%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
WING C46%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 60% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 50% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Progress on shared amenities15
As on 25 Feb 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 100% |
| Water Supply | Yes | 100% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 100% |
| Storm Water Drains | Yes | 0% |
| Landscaping & Tree Planting | Yes | 25% |
| Street Lighting | Yes | 100% |
| Community Buildings | Yes | 0% |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 0% |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 15% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | No | Not applicable |
| Electrical meter room, sub-station, receiving station | Yes | 100% |
| Aggregate area of recreational Open Space | Yes | 80% |
| Open Parking | Yes | 80% |
Parking filed87
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Closed/Covered | Open Space | Total |
|---|---|---|---|
| WING A | 24 | 5 | 29 |
| WING B | 24 | 5 | 29 |
| WING C | 24 | 5 | 29 |
Land and ownership18
MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
| Landowner | Village | District |
|---|---|---|
| SUDAM THAKA THORAT | Manchar (CT) | Pune |
| VIDHYARANI SANTAJI THORAT | Manchar (CT) | Pune |
| NARENDRA SITARAM THORAT | Manchar (CT) | Pune |
| PRASANNA RAMJI THORAT | Manchar (CT) | Pune |
| BABURAO SAWALERAM THORAT | Manchar (CT) | Pune |
| THORAT BHAGWAN ANANTHA | Manchar (CT) | Pune |
| RAMESH SONU THORAT | Manchar (CT) | Pune |
| NANDU SONABA THORAT | Manchar (CT) | Pune |
| SATYAVAN SONABA THORAT | Manchar (CT) | Pune |
| THORAT GANGARAM SAWLERAM | Manchar (CT) | Pune |
| KAMLAKAR SONBA THORAT | Manchar (CT) | Pune |
| KISAN ANANTHA THORAT | Manchar (CT) | Pune |
| OMKAR RAVINDRA THORAT | Manchar (CT) | Pune |
| chandrakala ravindra thorat | Manchar (CT) | Pune |
| ANJALI RAMJI THORAT | Manchar (CT) | Pune |
| ARUN SONBA THORAT | Manchar (CT) | Pune |
| Kisan Anandrao Thorat | Mordewadi | Pune |
| Bhagwan Anantha thorat | Manchar (CT) | Pune |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners3
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | PAWAR NARSING NIVRUTI |
| Engineer | AVDHUT TUKARAM SHETE |
| Chartered Accountant | SATPUTE AND ASSOCIATES |
| Partner | Role in project |
|---|---|
| VISHWA DEVELOPER & PROMOTER | - |
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 29 Oct 2022 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 29 Jul 2017 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 29 Jul 2017 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 29 Jul 2017Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateOn the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
uploaded 25 Feb 2025
Documents filed89
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 89 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: OC verification.pdf | 25 Feb 2025 |
| Architect’s Certificate on Completion of Project (Form 4)File: FORM 4 VISHVAVIHAR.pdf | 21 Dec 2024 |
| Architect’s Certificate on Completion of Project (Form 4)File: form 4 vishvavihar.pdf | 5 Dec 2024 |
| Architect’s Certificate on Completion of Project (Form 4)File: Form -4 New.pdf | 3 Dec 2024 |
| Architect’s Certificate on Completion of Project (Form 4)File: FORM 4 VISHVAVIHAR.pdf | 26 Nov 2024 |
| Certificates of CA (Form 3)File: Form - 3 (2).pdf | 5 Nov 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 - Engineers Certificate Quality Assurance (P52100006484)Q2.pdf | 5 Nov 2024 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: OCCUPANCY CERTIFICATE A AND B.pdf | 5 Nov 2024 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: OCCUPANCY CERTIFICATE C.pdf | 5 Nov 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A 2024.pdf | 5 Nov 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architects Certificate.pdf | 15 Oct 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architects Certificate.pdf | 15 Oct 2024 |
| Disclosure of sold/ booked inventoryFile: Sold Unsold Inventory.pdf | 15 Oct 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architects Certificate Q1 (2024-25)-P52100006484.pdf | 16 Aug 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2.pdf | 16 Aug 2024 |
| Disclosure of sold/ booked inventoryFile: Sold Unsold Inventory compressed.pdf | 16 Aug 2024 |
| Certificates of CA (Form 3)File: Form - 3 compressed.pdf | 16 Aug 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate Form 2 Q4.pdf | 29 May 2024 |
| Certificates of CA (Form 3)File: Form - 3 Rera No(Q4)_compressed.pdf | 29 May 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form - 5 Rera No P52100006484 (2023-24).pdf | 29 May 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate Jan 24 to March 24.pdf | 27 Apr 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A - Engineers Certificate Quality Assurance (P52100006484)2023-24.pdf | 22 Apr 2024 |
| Disclosure of sold/ booked inventoryFile: Sold Unsold Inventory Rera No P52100006484 (Q4).pdf | 22 Apr 2024 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: Sold Unsold Inventory Rera No P52100006484 (Q4).pdf | 22 Apr 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate Form 2(Rera no P52100006484) Q3.pdf | 17 Feb 2024 |
| Certificates of CA (Form 3)File: Form 3 C A SATPUTE FINAL(P52100006484) Q3_compressed.pdf | 17 Feb 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architects Certificate Q3-P52100006484.pdf | 27 Jan 2024 |
| Disclosure of sold/ booked inventoryFile: Sold Unsold Inventory Rera No P52100006484.pdf | 27 Jan 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2-Engineers Certificate (P52100006484)_compressed.pdf | 3 Nov 2023 |
| Certificates of CA (Form 3)File: Form 3 CA (Rere No P52100006484)_compressed.pdf | 3 Nov 2023 |
| Disclosure of sold/ booked inventoryFile: Sold Unsold Inventory Rera NoP5210000684compressed.pdf | 2 Oct 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate Form 2(Rera no P52100006484)_compressed.pdf | 3 Jul 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Archtects Certificate(Rera No- P52100006484) Q1_compressed.pdf | 1 Jul 2023 |
| Certificates of CA (Form 3)File: C A Form 3-(P52100006484) Q1_compressed.pdf | 1 Jul 2023 |
| Disclosure of sold/ booked inventoryFile: Sold Unsold Inventory P52100006484 (April 23 to Jun 23)_compressed.pdf | 24 Jun 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Quality Assurance Certificate Form 2A -P52100006484.pdf | 17 Jun 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 FY 2022-23(P52100006484).pdf | 17 Jun 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form 5 FY 2020-21(P52100006484)Revised.pdf | 31 May 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5 FY 2022-23(P52100006484).pdf | 31 May 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate Jan-23 to March-23 -P52100006484.pdf | 20 Apr 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form-2 Engineers Certificate - P52100006484.pdf | 20 Apr 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Quality Assurance Certificate Form 2A -P52100006484.pdf | 20 Apr 2023 |
| Disclosure of sold/ booked inventoryFile: Sold,Unsold,Booked Inventory Jan 23 to mar23 P52100006484.pdf | 20 Apr 2023 |
| Certificates of CA (Form 3)File: C A Form 3 March-2023 P52100006484.pdf | 20 Apr 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Annual Report Form 5 2021-22.pdf | 25 Mar 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: GetUserDocumentFileContent.pdf | 15 Feb 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Form 2A 2019-20.pdf | 15 Feb 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2A 2020-21.pdf | 15 Feb 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2A 2021-22.pdf | 15 Feb 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: ilovepdf_merged (23)_compressed (1).pdf | 15 Feb 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: form 2.pdf | 6 Feb 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architects Certificate oct 22 to dec 22_compressed.pdf | 1 Feb 2023 |
| Disclosure of sold/ booked inventoryFile: Sold, Unsold, Booked Inventory Oct 22 to Dec22_compressed.pdf | 1 Feb 2023 |
| Certificates of CA (Form 3)File: Form 3-compressed.pdf | 1 Feb 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1- Architects Certificate 2017-2022_compressed.pdf | 12 Jan 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2- Engineers Certificate_compressed.pdf | 12 Jan 2023 |
| Disclosure of sold/ booked inventoryFile: Sold Unsold Inventory A B C.pdf | 12 Jan 2023 |
| Certificates of CA (Form 3)File: Form 3 CA Certificate_compressed.pdf | 12 Jan 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Form 5 (2017-2018)_compressed.pdf | 12 Jan 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Form 5 (2018-2019)_compressed.pdf | 12 Jan 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Form 5 (2019-2020)_compressed.pdf | 12 Jan 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form 5 (2020-2021)_compressed.pdf | 12 Jan 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form 5 (2021-2022)_compressed.pdf | 12 Jan 2023 |
| Copy of the legal title reportFile: Search Report in RERA format_compressed.pdf | 29 Oct 2022 |
| Certificates of CA (Form 5)File: AUDIT VISHWA DEVELOPER AND PROMOTER 31-3-2018 TO 31-10-2018.pdf | 11 Jan 2019 |
| Certificates of CA (Form 5)File: AUDIT VISHWA DEVELOPER AND PROMOTER 31-3-2018-ilovepdf-compressed.pdf | 11 Jan 2019 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Arc certification (2).pdf | 30 Jul 2017 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: engg certification-ilovepdf-compressed.pdf | 30 Jul 2017 |
| Certificates of CA (Form 3)File: CA certifate-ilovepdf-compressed.pdf | 30 Jul 2017 |
| Layout approvalFile: main 1-ilovepdf-compressed.pdf | 29 Jul 2017 |
| Building plan approvalFile: WING A 1 N 3.pdf | 29 Jul 2017 |
| Building plan approvalFile: WING A 2N4.pdf | 29 Jul 2017 |
| Building plan approvalFile: WING B 1 N 3 (2).pdf | 29 Jul 2017 |
| Building plan approvalFile: WING B 2N 4.pdf | 29 Jul 2017 |
| Building plan approvalFile: WING C 1N3.pdf | 29 Jul 2017 |
| Building plan approvalFile: WING C 2N4.pdf | 29 Jul 2017 |
| PAN CardFile: pan crad-ilovepdf-compressed.pdf | 29 Jul 2017 |
| Copy of the legal title reportFile: search report.pdf | 29 Jul 2017 |
| Details of encumbrancesFile: NO BHAR CERTIFICATE (1).pdf | 29 Jul 2017 |
| Copy of Layout Approval (in case of layout)File: main 1-ilovepdf-compressed.pdf | 29 Jul 2017 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Pune
Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.
Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 2 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 1 other registration and every project registered within 2 km, which the RERA portal never shows together
- All 89 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
- A watch tells you the moment that changes, including if the registration lapses or a complaint is filed
- But on this project's record so far, expect it to be quiet. You can also save this project free and keep it on your shortlist
Keep VISHWAVIHAR on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Manchar (CT)13,700+ in Pune
Filed coordinates, straight-line distance. 20 registered projects within 2 km.
Aurum Avenue
Poojan Developers
BSP PLAZA
BSP BUILDERS AND DEVELOPERS
The Central Park Phase-2
SUPREME INFRA
VISHWAVIHAR
VISHWA DEVELOPER & PROMOTER
MEGH MALHAR RESIDENCY
SUNGRACE INFRA PROJECTS
Aarambh Residency
SUPREME INFRA
Builder: VISHWA DEVELOPER & PROMOTER
VISHWA DEVELOPER & PROMOTER has 2 registrations on MahaRERA, including VISHWAVIHAR and VISHWAVIHAR. Its filings disclose 1 earlier MahaRERA project, none completed yet. Read the full track record. See more projects on the Pune district page.
Frequently asked questions
What does it mean that VISHWAVIHAR shows as registration lapsed on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if VISHWAVIHAR is delayed beyond 23 Jul 2023?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of VISHWAVIHAR?
The registered promoter entity is VISHWA DEVELOPER & PROMOTER, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in VISHWAVIHAR?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for VISHWAVIHAR?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at VISHWAVIHAR?
The professionals named in the filing: Architect: PAWAR NARSING NIVRUTI; Engineer: AVDHUT TUKARAM SHETE; Chartered Accountant: SATPUTE AND ASSOCIATES. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in VISHWAVIHAR?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback