Home / Browse projects / Thane, Maharashtra / VISHWAJEET PARADISE
VISHWAJEET PARADISE
RG-MH-12472 · RERA P51700008406 · Last updated on MahaRERA portal: 7 Jun 2023
Source: official MahaRERA filing
Red flags
- 1 complaint at MahaRERA
- Completion date moved by 12 months
- 1 extension taken
Clear
- No litigation declared
- Separate project account declared
- Allotment letter follows the model form
- Recorded completed on MahaRERA
3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Thane registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
VISHWAJEET PARADISE is a Residential / Group Housing project by KOHINOOR INFRA DEVELOPMENT in Thane, Maharashtra, registered with MahaRERA as P51700008406 on 18 Aug 2017. The registration is recorded completed; possession was promised by 30 Sep 2019. The completion date has moved by 12 months from the original filing. 1 complaint is on record with the regulator.
At a glance
Project
- NameVISHWAJEET PARADISE
- TypeResidential / Group Housing
- Location
- Ambarnath (R)
- Ambarnath
- Thane
- 421505
- Pincode421505
- MapView location on Google Maps (as filed on RERA)
- RERA no.P51700008406
- ReraGenie IDRG-MH-12472
Builder
- NameKOHINOOR INFRA DEVELOPMENT
- Entity typePartnership
- PartnersGULABRAO BABURAO KARANJULE, VISHWAJEET GULABRAO KARANJULE, ABHIJEET GULABRAO KARANJULE, SANTOSH MANOHARLAL RAMCHANDANI, AMIT ANIL HOTCHANDANI
- Declared earlier projects1 →
Key dates
Key facts
Registration and timeline
- StatusCompleted
- Registered on18 Aug 2017
- Promised completion30 Sep 2019
- Revised completionRevised to 30 Sep 2019 (originally 30 Sep 2018)
- Buildings4 building records
- Documents filed22 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| BUILDING - 1 MAJESTIC | NA | 13 | 0 | 0 | 0 | 0 |
| BUILDING - 2 BLISS | NA | 13 | 0 | 0 | 0 | 0 |
| BUILDING - 3 SERENE | NA | 10 | 0 | 0 | 0 | 0 |
| BUILDING -4 ORION | NA | 5 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building4
As on 7 Jun 2023, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
36 of 44 construction stages are filed complete across 4 buildings. The stage furthest along is Podiums (if any), at 0%.
BUILDING - 1 MAJESTIC82%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
BUILDING - 2 BLISS82%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
BUILDING - 3 SERENE82%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
BUILDING -4 ORION82%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Progress on shared amenities15
As on 7 Jun 2023, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 0% |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 0% |
| Storm Water Drains | Yes | 0% |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | Yes | 0% |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | Yes | 0% |
| Electrical meter room, sub-station, receiving station | Yes | 0% |
| Aggregate area of recreational Open Space | Yes | 0% |
| Open Parking | Yes | 0% |
Parking filed40
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Open Space | Total |
|---|---|---|
| BUILDING - 1 MAJESTIC | 10 | 10 |
| BUILDING - 2 BLISS | 10 | 10 |
| BUILDING - 3 SERENE | 10 | 10 |
| BUILDING -4 ORION | 10 | 10 |
Land and ownership1
MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
| Landowner | Village | District |
|---|---|---|
| MADHU K ACHHRA (HUF) | Ulhasnagar (M Corp.) | Thane |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners2
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | KAMELSH V GURAV |
| Engineer | ATUL KUDTARKAR |
| Partner | Role in project |
|---|---|
| KOHINOOR INFRA DEVELOPMENT | - |
Extensions applied for1
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterOur project being located in mofussil area i.e. Outskirts of Badlapur City, the quality of manpower and Material required for such type of construction is not available in abundance. Due to lack of supply of man power and Material, and the available manpower and material being not sufficient, we are facing very much difficulties in completion of our project on the proposed date of completion.
Complaints filed with MahaRERA1
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CC006000000210184 | MADHU KACHHRAM ACHHRA | KOHINOOR INFRA DEVELOPMENT | 26/02/2022 |
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 22 Jul 2017 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 22 Jul 2017 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 29 Jul 2017 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 29 Jul 2017Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateOn the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
uploaded 27 Sep 2019
Documents filed22
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Architect’s Certificate on Completion of Project (Form 4)File: Form 4.pdf | 7 Jun 2023 |
| Certificates of CA (Form 5)File: Rera Form 5.pdf | 4 Jan 2021 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Form 5 Infra.PDF | 25 Nov 2019 |
| Architect’s Certificate on Completion of Project (Form 4)File: Architect Certificate.pdf | 25 Nov 2019 |
| Certificates of CA (Form 5)File: Form 5 Infra.PDF | 4 Nov 2019 |
| Status of Formation of Legal Entity (Society/Co Op etc.)File: Society Formation.pdf | 30 Sep 2019 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: OC Copy.pdf | 27 Sep 2019 |
| Certificates of CA (Form 5)File: Form 5.PDF | 24 Oct 2018 |
| Building plan approvalFile: Commencement Certificate.pdf | 29 Jul 2017 |
| Building Plan Approval (IOD)File: Commencement Certificate.pdf | 29 Jul 2017 |
| Commencement Certificates / NA Order for plotted developmentFile: Commencement Certificate.pdf | 29 Jul 2017 |
| Certificates of CA (Form 3)File: CA Certificate.pdf | 29 Jul 2017 |
| Proforma of Allotment letterFile: VISHWAJEET PARADISE-DRAFT AGREEMENT UPDATE.pdf | 29 Jul 2017 |
| OtherFile: Patners Declaration.pdf | 29 Jul 2017 |
| Details of encumbrancesFile: No Encumbrance Certificate.pdf | 28 Jul 2017 |
| Declaration in FORM BFile: FORM B.pdf | 28 Jul 2017 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCHITECT CERTIFICATE UK ASSOCIATES.pdf | 28 Jul 2017 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineers Certificate of Atul Kudtarkar.pdf | 28 Jul 2017 |
| Layout approvalFile: MYSCAN_20170717_0017.PDF | 22 Jul 2017 |
| PAN CardFile: PAN CARD.pdf | 22 Jul 2017 |
| Copy of the legal title reportFile: TITLE CERTIFICATE.pdf | 22 Jul 2017 |
| Copy of Layout Approval (in case of layout)File: MYSCAN_20170717_0017.PDF | 22 Jul 2017 |
Promoter's earlier projects1
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Flats | Status | Promised | Delivered |
|---|---|---|---|---|---|
| KOHINOOR MAXCITY | Plot bearing survey no. 144 Hissa no. 03 survey no. 143 Hissa no. 04 and 6B survey no. 140 Hissa no. 02 and 3 survey no. 142 Hissa no. 05 Village Chikhloli Ambernath | 126 | Completed | Oct 2014 | Late, May 2015 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Thane
Computed across the 7,600+ Thane projects on ReraGenie, from their own filings.
Free monthly report: Thane on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Useful on a completed registration when you are buying resale, or checking what was promised against what was delivered.
- 3 conditions on this project's record read and explained, with the clear checks alongside
- Joined against every project registered within 2 km, which the RERA portal never shows together
- All 22 filed documents as one ZIP, foldered, with a manifest
Keep VISHWAJEET PARADISE on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Ambarnath (R)7,600+ in Thane
Filed coordinates, straight-line distance. 158 registered projects within 2 km.
MATOSHREE NAGAR EXCELLENCY BLDG SAPPHIRE A AND
MATOSHREE SHELTERS (INDIA) PRIVATE LIMITED
NIDHI RESIDENCY
ADITYA YASH BUILDERS
MIDTOWN B AND C WING
SIDDHIVINAYAK GROUP NX
PATELS LEGACY
RAPID CORPORATION
PATELS ETERNITY
OMKAR INFRASTRUCTURE
Harishree Celestial-1
HARISHREE CREATIONS
See every Thane project, with the district possession charts
Builder: KOHINOOR INFRA DEVELOPMENT
KOHINOOR INFRA DEVELOPMENT has 1 registration on MahaRERA, including VISHWAJEET PARADISE. Its filings disclose 1 earlier MahaRERA project: declares 0 of 1 past projects completed on time. Read the full track record. See more projects on the Thane district page.
Frequently asked questions
What are my rights if VISHWAJEET PARADISE is delayed beyond 30 Sep 2019?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of VISHWAJEET PARADISE?
The registered promoter entity is KOHINOOR INFRA DEVELOPMENT, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in VISHWAJEET PARADISE?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against VISHWAJEET PARADISE?
Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
How current is the construction progress shown for VISHWAJEET PARADISE?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at VISHWAJEET PARADISE?
The professionals named in the filing: Architect: KAMELSH V GURAV; Engineer: ATUL KUDTARKAR. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in VISHWAJEET PARADISE?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.