ReraGenieLog inGet a buyer report

Home / Browse projects / Mumbai Suburban, Maharashtra / VIKAS ORNATE

Registered No litigation declared Residential / Group Housing project

VIKAS ORNATE

By ARICIA CONSTRUCTION

RG-MH-96028 · RERA P51800032578 · Last updated on MahaRERA portal: 20 Jul 2026

Source: official MahaRERA filing

Red flags

  • Completion date moved by 19 months
  • 1 extension taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Dec 2026Possession promisedmoved 19 months from the original
8 of 22Construction stages doneacross 2 buildings; furthest along: Slabs of Super Structure, 87%
105 of 112Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 110 documents Report an error

VIKAS ORNATE is a Residential / Group Housing project by ARICIA CONSTRUCTION in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800032578 on 11 Jan 2022. Possession is promised by 31 Dec 2026. The completion date has moved by 19 months from the original filing. 7 of the 112 units on this registration are recorded sold or booked, and 8 of 22 construction stages are filed complete.

At a glance

Project

  • NameVIKAS ORNATE
  • TypeResidential / Group Housing
  • Location
    • RAJAWADI ROAD NO 01
    • GHATKOPAR EAST
    • Kurla
    • Mumbai Suburban
    • 400077
  • Pincode400077
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51800032578
  • ReraGenie IDRG-MH-96028

Builder

  • NameARICIA CONSTRUCTION
  • Entity typePartnership
  • PartnersVALLABHJI BHANJI GADA, KETAN VALLABHJI GADA

Key dates

this monthRegisteredJan 2022First promiseMay 2025Revised toDec 2026

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on11 Jan 2022
  • Promised completion31 Dec 2026
  • Revised completionRevised to 31 Dec 2026 (originally 31 May 2025)
  • Buildings2 building records
  • Documents filed110 files

Current status

6%7 of 112 units booked
43.6%Work done, per cost certificate

Figures as on 20 Jul 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
WING ANA211552052
WING BNA21060060

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building2

As on 20 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

8 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Slabs of Super Structure, at 87%.

WING A49%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure87%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises50%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
WING B49%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure87%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises50%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 20 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes85%
Storm Water DrainsYes75%
Landscaping & Tree PlantingNoNot applicable
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes30%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceYes0%
Open ParkingNoNot applicable

Parking filed184

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots184
Closed/Covered184
BuildingClosed/CoveredTotal
WING A9292
WING B9292

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area1,946 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Sanctioning authoritySlum Rehabiliation authority
Permissible FSI10505.7
Proposed, not sanctioned10,151 sq m
Buildings approved2
Buildings sanctioned2

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchMARATHON MAX, JUNCTION OF LBS ROAD AND MULUND GOREGAON LINK ROAD, MULUND WEST, MUMBAI 400080
Estimated costRs 117.80 cr
Cost incurredRs 51.39 cr
Work done43.63%
BuildingWingEstimatedIncurred
WING ANARs 44.17 crRs 25.48 cr
WING BNARs 44.17 crRs 25.48 cr
-NARs 29.45 crRs 42.08 lakh

Certifying professionals and partners6

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectHARDIK SHROFF shard shroff
EngineerJ J REALIS
Engineerkaushik shantilal shah
Chartered AccountantUmang Dedhia & Co.
Chartered AccountantPRAVIN SHAH AND ASSOCIATES hirji shah
Chartered AccountantHarshal Doshi & Associates
PartnerRole in project
ARICIA CONSTRUCTION-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EA15052501130May 2025 → Dec 2026

Reason as filed by the promoterWe have started the excavation & piling work on time but the basement construction took more than expected time due to road issue and site constraints to carry on the excavation as well as concrete work hence we request to grant us the extension.

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 27 Dec 2021
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 26 May 2025
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 26 May 2025
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 20 Jul 2026Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2026

Documents filed110

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 110 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Commencement certificateFile: CC FURTHER OF VIKAS ORNATE.pdf20 Jul 2026
Withdrawal Update Form 1File: Aricia Construction - Architect Certificate.pdf20 Jul 2026
Withdrawal Update Form 2File: Aricia Construction - Engineer Certificate.pdf20 Jul 2026
Withdrawal Update Form 3File: Aricia Construction - CA Certificate.pdf20 Jul 2026
Withdrawal Update Form 1File: ARCHITECTS CERTIFICATEQ4ARICIA.pdf8 May 2026
Withdrawal Update Form 2File: ENGINEERS CERTIFICATEQ4ARICIA.pdf8 May 2026
Withdrawal Update Form 3File: CA CERTIFICATEQ4 ARICIA.pdf8 May 2026
Withdrawal Update Form 1File: form 1.pdf9 Feb 2026
Withdrawal Update Form 2File: Engineer Certificate dec 2025.pdf9 Feb 2026
Withdrawal Update Form 3File: Form 3 .pdf9 Feb 2026
Form 1File: ARCHITECT CERTIFICATE.pdf17 Jan 2026
Form 2File: ENGINEER CEERTIFICATE 31032025.pdf17 Jan 2026
Form 3File: Revised Form 3 31032025.pdf17 Jan 2026
Disclosure of Sold and Booked InventoryFile: Sold and Unsold Inventories.pdf17 Jan 2026
Withdrawal Update Form 1File: Architect Certificate Q1.pdf17 Jan 2026
Withdrawal Update Form 1File: Architect Certificate Q2.pdf17 Jan 2026
Withdrawal Update Form 2File: Engineer Certificate Q1.pdf17 Jan 2026
Withdrawal Update Form 2File: Engineer Certificate Sept 2025.pdf17 Jan 2026
Withdrawal Update Form 3File: Aricia Form 3 Q1 FY 2025-26 .pdf17 Jan 2026
Withdrawal Update Form 3File: CA Certificate Sept 2025.pdf17 Jan 2026
Form 1File: Architect Certificate June 2024 AC.pdf17 Jun 2025
Form 2File: Engineer Certificate June 2024 AC.pdf17 Jun 2025
Form 3File: CA Certificate June 2024.pdf17 Jun 2025
Disclosure of Sold and Booked InventoryFile: Sold and Unsold Inventories.pdf17 Jun 2025
Form 1File: Architect Certificate Sept 2024.pdf17 Jun 2025
Form 2File: Engineer Certificate Sept 2024.pdf17 Jun 2025
Form 3File: CA Certificate ARICIA CONSTRUCTION.pdf17 Jun 2025
Disclosure of Sold and Booked InventoryFile: Sold and Unsold Inventories.pdf17 Jun 2025
Form 3File: CA Certificate Aricia Construction Dec 2024.pdf17 Jun 2025
Form 2File: Engineer Certificate Dec 2024 Aricia Construction.pdf17 Jun 2025
Disclosure of Sold and Booked InventoryFile: Sold and Unsold Inventories.pdf17 Jun 2025
Form 1File: Architect Certificate Dec2024-1-3.pdf17 Jun 2025
Form 5 (FY 2024-2025)File: Form 5 2024-25 Aricia.pdf17 Jun 2025
Layout approvalFile: Layout Plans.pdf26 May 2025
Building plan approvalFile: Appoved Plans-1.pdf26 May 2025
Building plan approvalFile: Appoved Plans-2.pdf26 May 2025
Building plan approvalFile: Appoved Plans-3.pdf26 May 2025
Building plan approvalFile: Appoved Plans-4.pdf26 May 2025
Building plan approvalFile: Appoved Plans-5.pdf26 May 2025
Building plan approvalFile: Appoved Plans-6.pdf26 May 2025
Building plan approvalFile: Appoved Plans-7.pdf26 May 2025
Form 2A (FY 2024-2025)File: FORM 2A (2).pdf26 May 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate Dec2024.pdf31 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate Aricia Construction Dec 2024.pdf31 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate Dec 2024 Aricia Construction.pdf31 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate ARICIA CONSTRUCTION.pdf22 Nov 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate June 2024 AC.pdf19 Nov 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate Sept 2024.pdf19 Nov 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate June 2024.pdf19 Nov 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate June 2024 AC.pdf19 Nov 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate Vikas Ornate Sept 24.pdf19 Nov 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A-Aricia Construction.pdf19 Nov 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Aricia Construction Form 5 FY 2023-24.pdf19 Nov 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate.pdf17 Jun 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: aricia construction engineer ccertificate march 31, 2024.pdf17 Jun 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3.pdf17 Jun 2024
Details of encumbrancesFile: Aricia Condtruction and KMIL.pdf17 May 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architects certificate- Vikas Ornate- 31st Dec_compressed.pdf24 Jan 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer certificate.pdf20 Jan 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate.pdf20 Jan 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architects certificate- Vikas Ornate- 30th Sept 2023_compressed.pdf9 Nov 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Vikas Ornate Engineer Certificate- Sept 2023 (2).pdf9 Nov 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: FORM 2A FY 2022-23 AC.pdf9 Nov 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate Sept 2023.pdf9 Nov 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Aricia Construction form 5.pdf9 Nov 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate June 2023 (2)_compressed (1).pdf25 Sep 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate.pdf12 Sep 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Aricia Construction- Engineer certificate- June 23 (3).pdf12 Sep 2023
Commencement Certificates / NA Order for plotted developmentFile: Plinth CC.pdf6 Jun 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architech Certificate Q4.pdf6 Jun 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certiifcate Q4.pdf6 Jun 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: FORM 2A FY 2022-23 AC.pdf6 Jun 2023
Disclosure of sold/ booked inventoryFile: DISCLOUSER OF SOLD and BOOKED INVENTORY.pdf6 Jun 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA CERTIFICATE Q4 AC.pdf6 Jun 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCHITECT CERTIFICATE Q2.pdf24 Apr 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCHITECH CERTIFICATE Q3.pdf24 Apr 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGINEER CERTIFICATE Q2.pdf24 Apr 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Vikas Ornate- Engineer Certificate- Dec 2022.pdf24 Apr 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 Q2_11zon.pdf24 Apr 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FROM 3 Q3.pdf24 Apr 2023

How this compares with Mumbai Suburban

6%of this project is bookeddistrict median 30%
33%of Mumbai Suburban projects moved their completion datethis one moved by 19 months
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is on the register

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep VIKAS ORNATE on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near GHATKOPAR EAST6,700+ in Mumbai Suburban

2 kmVIKAS ORNATECompleted 140Lapsed / revoked 110Other 147Dot size: filed unitsN

Filed coordinates, straight-line distance. 397 registered projects within 2 km.

Builder: ARICIA CONSTRUCTION

ARICIA CONSTRUCTION has 1 registration on MahaRERA, including VIKAS ORNATE. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What are my rights if VIKAS ORNATE is delayed beyond 31 Dec 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of VIKAS ORNATE?

The registered promoter entity is ARICIA CONSTRUCTION, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in VIKAS ORNATE?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for VIKAS ORNATE?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at VIKAS ORNATE?

The professionals named in the filing: Architect: HARDIK SHROFF shard shroff; Engineer: J J REALIS; Engineer: kaushik shantilal shah; Chartered Accountant: Umang Dedhia & Co.; Chartered Accountant: PRAVIN SHAH AND ASSOCIATES hirji shah; Chartered Accountant: Harshal Doshi & Associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in VIKAS ORNATE?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About VIKAS ORNATE. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save VIKAS ORNATE to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.