Vijaya Aquagreen

By H B Shivakumar

RG-KA-35441 · RERA PRM/KA/RERA/1251/309/PR/180217/002704 · Last updated on RERA Karnataka portal: 20 Jun 2022

Source: official RERA Karnataka filing

Red flags

  • Registration withdrawn
  • Completion date moved by 9 months
  • 1 extension taken

Clear

  • No complaints on record
  • Separate project account declared
Apr 2022Possession promisedmoved 9 months from the original
0Complaints at RERA Karnatakaon this registration
Jump to the 69 documents Report an error

Vijaya Aquagreen is a Residential/Group Housing project by H B Shivakumar in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/309/PR/180217/002704 on 17 Feb 2018. Possession is promised by 15 Apr 2022. The completion date has moved by 9 months from the original filing.

At a glance

Project

  • NameVijaya Aquagreen
  • TypeResidential/Group Housing
  • Location
    • Bengaluru North
    • Bengaluru Urban
  • PincodeNot stated
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PRM/KA/RERA/1251/309/PR/180217/002704
  • ReraGenie IDRG-KA-35441

Builder

  • NameH B Shivakumar

Key dates

this monthRegisteredFeb 2018First promiseJul 2021Revised toApr 2022

Key facts

Registration and timeline

  • StatusRegistration withdrawn
  • Registered on17 Feb 2018
  • Promised completion15 Apr 2022
  • Revised completionRevised to 15 Apr 2022 (originally 15 Jul 2021)
  • Buildings1 building record
  • Documents filed69 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
VIJAYA AQUAGREEN---1960196

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 20 Jun 2022, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

Building:

ActivityProgress
Earth work and other leveling preparation work-
Foundation footing work-
Retaining wall (All types)Not applicable
Plinth level Beam-
Sub-structure flooring (Parking Floor, more than one floor below general ground level)Not applicable
RCC or MS Framed structure-
Masonry construction: Bricks, Concrete blocks etc-
Plastering inside , outside & Ceiling-
Joinery: Doors, Windows, Ventilators etc-
Basic work of Water supply, Sanitary and Electrification-
Dadoing, Skirting, Flooring, Tiles work (All types)-
Railing and Grill fixing-
Electrification, Water supply and Sanitary Finishing-
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Fire prevention and fire fighting fitting and fixture with networkNot applicable
Weather Proof work(tile,concrete)-
Painting-
Elevation work-
Internal and External work including landscapes as per santioned drawings-

Progress on shared amenities41

As on 20 Jun 2022, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes-
Internal Roads & FootpathsYes-
Sewage and Drainage SystemYes-
Parks & Tree plantingYes-
Street LightingYes-
Provision for community buildings and for treatment and disposal of sewage and sullage waterYes-
Solid waste management and disposalYes-
Water conservationNoNot applicable
Energy managementNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Education/Health/Other public amenitiesYes-
Electricity supply transformer and substationYes-
Emergency Evacuation servicesNoNot applicable
Storm water drainsYes-
Use of renewable energyNoNot applicable
Water conservation/rain water harvesting/recharge of ground waterYes-
ElectricityYes-
Smart Home AutomationNoNot applicable
CCTV SurveillanceYes-
Club HouseYes-
Community HallNoNot applicable
Outdoor Sports facilityNoNot applicable
Indoor Sports facilityYes-
Swimming PoolYes-
GymYes-
ParksNoNot applicable
Power BackupYes-
GasNoNot applicable
Water and SanitationYes-
Air Conditioning And incerntionNoNot applicable
StaircasesYes-
LiftsYes-
Staircases and Lift lobbies, corridor,lobbies, corridorYes-
Fire escapesNoNot applicable
Common entrance and exit for the building / common portico/foyer/verandahYes-
BasementNoNot applicable
TerraceYes-
Outer WallYes-
Open parking areas and common storage spacesYes-
Provision for lodging of management staff and security staffNoNot applicable
Water conservation and renewable energyNoNot applicable

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area9,105 sq m
Named landownersNone

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 37.00 cr

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

ExtensionJul 2021 → Apr 2022

No reason recorded in the filing

Complaints filed with RERA Karnataka

No complaints on record against this registration.

Documents filed69

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/309/PR/180217/002704 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
CA CertificateFile: Quarterly Update_CA Cert_compressed.pdf20 Jun 2022
Architect CertificateFile: Architect Certificate.pdf20 Jun 2022
Project Contractors detailsFile: project COntractors details.png20 Jun 2022
Project Engineers DetailsFile: project engineers details.png20 Jun 2022
Noc clarificationFile: BESCOM NOC CRITERIA.png20 Jun 2022
quarterly update CA certificateFile: Quarterly Update_CA Cert_compressed.pdf2 Jun 2022
Extension Certificate till 15-04-2022File: Extension Certificate.pdf2 Jun 2022
Architects CertificateFile: Architect Certificate Scanned Copy.PDF2 Jun 2022
Affidivate for extensionFile: Affidavit seeking Extension.pdf2 Jun 2022
Compensation delay explanationFile: COmpensarion delay explanation.png2 Jun 2022
BHk Wise break up development detailsFile: BHK wise-pages-deleted (1).xlsx2 Jun 2022
Structural Safety CertificateFile: structral safety aqgr.jpg2 Jun 2022
Stp Demarcation planFile: STP Demarcation.pdf2 Jun 2022
Proforma of allotment letterFile: Proforma of Allotment Letter aquagreen.pdf2 Jun 2022
Designated upto date Bank StatementFile: bank statement.jpg2 Jun 2022
Proforma Of agreement of saleFile: Sale Agreement_draft.pdf2 Jun 2022
BrochureFile: Brochure.pdf2 Jun 2022
Bescom Noc Not ApplicableFile: BESCOM NOC_NA.pdf2 Jun 2022
Bwssb Noc Not applicableFile: BWSSB NOC_NA.pdf2 Jun 2022
Architect Certificate for Work Completion Schedule till DateFile: Form-Ex1_Architect.pdf-
Engineer Certificate for Work Completion Schedule till DateFile: Form-Ex5_Engineer.pdf-
CA Certificate for Funds UtilizationFile: Form-B.pdf-
Architect Certificate for Pending Work Completion Schedule.File: Form-Ex2_Architect.pdf-
Engineer Certificate for Pending Work Completion Schedule.File: Form-Ex6_Engineer.pdf-
CA Certificate for Funds required for Project CompletionFile: Form-Ex4_Chartered Accountant.pdf-
AffidavitFile: RERA_Registration Cert.pdf-
Latest Encumbrance CertificateFile: EC's.pdf-
Details Of Sold/ Un-sold UnitsFile: SoldUnsoldDetails.xlsx-
License BDA-
Sanction Plan_Jan 2018-ilovepdf-compressed-
Sale Deed-
Sale Agreement_draft-
Sale Deed & RTC-
Sanction Plan_Sheet 03 of 03-
Sanction Plan_Jan 2018-ilovepdf-compressed-
Allotment Letter-
Brochure-
Specifications-
EC's-
Khatha & TPR-
LLP Agreement-
Conversion Order-
BDA NOC-
KSPCB NOC-
Sanction Plan_Sheet 01 of 03-
Sanction Plan_Sheet 03 of 03-
Conversion Order-
Legal Opinion-
Balance Sheet 2016 - 2017File: NA_Financial.jpg-
Balance Sheet 2015 - 2016File: NA_Financial.jpg-
Balance Sheet 2014 - 2015File: NA_Financial.jpg-
Audited Profit and Loss Statement 2016 - 2017File: NA_Financial.jpg-
Audited Profit and Loss Statement 2015 - 2016File: NA_Financial.jpg-
Audited Profit and Loss Statement 2014 - 2015File: NA_Financial.jpg-
Director's Report 2016 - 2017File: NA_Financial.jpg-
Director's Report 2015 - 2016File: NA_Financial.jpg-
Director's Report 2014 - 2015File: NA_Financial.jpg-
Cash Flow Statement 2016 - 2017File: NA_Financial.jpg-
Cash Flow Statement 2015 - 2016File: NA_Financial.jpg-
Auditor's Report 2016 - 2017File: NA_Financial.jpg-
Auditor's Report 2015 - 2016File: NA_Financial.jpg-
Auditor's Report 2014 - 2015File: NA_Financial.jpg-
Income Tax Return Acknowledgement 2016 - 2017File: NA_Financial.jpg-
Income Tax Return Acknowledgement 2015 - 2016File: NA_Financial.jpg-
Income Tax Return Acknowledgement 2014 - 2015File: NA_Financial.jpg-
Form-B-
Prospectus/BrochureFile: e-brochure.pdf-
Advertisement Copy 1File: Advertisement.jpg-
Tower Excel SheetFile: PRM_KA_RERA_1251_309_PR_180217_002704.xlsx-

How this compares with Bengaluru Urban

34%of Bengaluru Urban projects moved their completion datethis one moved by 9 months
1%of Bengaluru Urban registrations are shown as withdrawn or revokedthis one is among them

Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.

Keep Vijaya Aquagreen on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bengaluru Urban4,100+ in Bengaluru Urban

2 kmVijaya AquagreenOther 3Dot size: filed unitsN

Filed coordinates, straight-line distance. 3 registered projects within 2 km.

Builder: H B Shivakumar

H B Shivakumar has 1 registration on RERA Karnataka, including Vijaya Aquagreen. Its filings disclose no earlier RERA Karnataka projects. Read the full track record. See more projects on the Bengaluru Urban district page.

Frequently asked questions

What does it mean that Vijaya Aquagreen shows as registration withdrawn on RERA Karnataka?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the RERA Karnataka portal, and take legal advice before paying any further instalment.

What are my rights if Vijaya Aquagreen is delayed beyond 15 Apr 2022?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of Vijaya Aquagreen?

The registered promoter entity is H B Shivakumar. Neither this filing nor this promoter's other RERA Karnataka registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in Vijaya Aquagreen?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

What should I check before booking in Vijaya Aquagreen?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Vijaya Aquagreen. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Vijaya Aquagreen to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.