Red flags
- 15 complaints at MahaRERA
Clear
- No litigation declared
- Completion date never moved
- Separate project account declared
- Allotment letter follows the model form
1 condition is on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
Vicenza Residency/Commercial is a Others project by SSV BUILDERS AND DEVELOPERS PVT LTD in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800011517 on 31 Aug 2017. Possession is promised by 1 Dec 2027. 15 complaints are on record with the regulator.
At a glance
Project
- NameVicenza Residency/Commercial
- TypeOthers
- Location
- MAHARASHTRA
- THANE
- Greater Mumbai (M Corp.) (Part) (802794)
- Mumbai
- Mumbai Suburban
- 400083
- Pincode400083
- MapView location on Google Maps (as filed on RERA)
- RERA no.P51800011517
- ReraGenie IDRG-MH-27096
Builder
- NameSSV BUILDERS AND DEVELOPERS PVT LTD
- Entity typeCompany
- ChairpersonHEMANT VINAYKANT PARIKH
- Managing DirectorsAmi Vipul Parikh, Hemant Vinaykant Parikh
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on31 Aug 2017
- Promised completion1 Dec 2027
- Revised completionNone
- Buildings7 building records
- Documents filed103 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| Vicenza Residency/Commercial A to F Wing | NA | 40 | 0 | 0 | 0 | 0 |
| Sanjivani CHS-Residence-Commercial-Sale/Rehab- Composite | NA | 23 | 0 | 0 | 0 | 0 |
| Shankar CHS-Residence-Commercial-Sale/Rehab Composite | NA | 23 | 0 | 0 | 0 | 0 |
| Swami Samartha CHS-Residence-Commercial-Sale/Rehab Composite | NA | 23 | 0 | 0 | 0 | 0 |
| Hindustan CHS / Sai Nath CHS/Gulistan CHS -Residece-Commercial-Sale/Rehab Composite | NA | 23 | 0 | 0 | 0 | 0 |
| Saishradhha CHS/Delux CHS-Residence-Commercial -Sale/Rehab Composite | NA | 23 | 0 | 0 | 0 | 0 |
| Shiv Chatrapati CHS-Residence-Commercial-Sale/Rehab Composite | NA | 23 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building7
As on 15 Feb 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
0 of 77 construction stages are filed complete across 7 buildings. The stage furthest along is Excavation, at 80%.
Vicenza Residency/Commercial A to F Wing20%
| Activity | Progress |
|---|---|
| Excavation | 80% |
| Basement (if any) | 50% |
| Podiums (if any) | 0% |
| Plinth | 50% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 5% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 30% |
Sanjivani CHS-Residence-Commercial-Sale/Rehab- Composite0%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Shankar CHS-Residence-Commercial-Sale/Rehab Composite0%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Swami Samartha CHS-Residence-Commercial-Sale/Rehab Composite0%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Hindustan CHS / Sai Nath CHS/Gulistan CHS -Residece-Commercial-Sale/Rehab Composite0%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Saishradhha CHS/Delux CHS-Residence-Commercial -Sale/Rehab Composite0%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Shiv Chatrapati CHS-Residence-Commercial-Sale/Rehab Composite0%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Progress on shared amenities15
As on 15 Feb 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 10% |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 30% |
| Storm Water Drains | Yes | 0% |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | Yes | 0% |
| Community Buildings | Yes | 0% |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 30% |
| Solid Waste Management And Disposal | Yes | 30% |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | Yes | 30% |
| Fire protection and fire safety requirements | Yes | 30% |
| Electrical meter room, sub-station, receiving station | Yes | 0% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | No | Not applicable |
Land and ownership8
MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
| Landowner | Village | District |
|---|---|---|
| HPA Spaces Pvt Ltd | Mumbai City | Mumbai City |
| SSV Realtors Pvt Ltd | Mumbai City | Mumbai City |
| Shiv Chatrapati CHS | Mumbai City | Mumbai City |
| Hindustan CHS | Mumbai City | Mumbai City |
| Sanjivani CHS | Mumbai City | Mumbai City |
| Shankar CHS | Mumbai City | Mumbai City |
| Swami Samarth CHS | Mumbai City | Mumbai City |
| Sai Shradhha CHS | Mumbai City | Mumbai City |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners2
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | HEMANT PARIKH & ASSOCIATES |
| Engineer | MAHIMTURA CONSULTANTS PVT LTD ( Dinesh Mahimtura ) |
| Partner | Role in project |
|---|---|
| SSV BUILDERS AND DEVELOPERS PVT LTD | - |
Litigation declared20
| Case | Court | Status |
|---|---|---|
| CC/16/417/2018 | STATE CONSUMER DISPUTES REDRESSAL COMMISSION MUMBA | Case disposed |
| CC/16/418/2018 | STATE CONSUMER DISPUTES REDRESSAL COMMISSION MUMBAI | Case disposed |
| CC/16/966/2018 | STATE CONSUMER DISPUTES REDRESSAL COMMISSION MUMBAI | Case disposed |
| CC/16/965/2018 | STATE CONSUMER DISPUTES REDRESSAL COMMISSION MUMBAI | Case disposed |
| 100438/2018 | City Sessions Court Mumbai | Case disposed |
| CC/17/327/2019 | STATE CONSUMER DISPUTES REDRESSAL COMMISSION MUMBAI | Case disposed |
| CC/17/139/2021 | STATE CONSUMER DISPUTES REDRESSAL COMMISSION MUMBAI | Case disposed |
| CC/16/1237/2021 | STATE CONSUMER DISPUTES REDRESSAL COMMISSION MUMBAI | Case disposed |
| CP IB - 4642/2019 /2019 | NCLT | pending |
| EA/19/49 , EA/19/50, EA/19/51, EA/19/52 /2021 | STATE CONSUMER DISPUTES REDRESSAL COMMISSION MUMBAI | Case disposed |
| CC/247/2019/2019 | STATE CONSUMER DISPUTES REDRESSAL COMMISSION MUMBAI | Case disposed |
| CC/16/956/2020 | STATE CONSUMER DISPUTES REDRESSAL COMMISSION MUMBAI | Case disposed |
| CC/16/957/2020 | STATE CONSUMER DISPUTES REDRESSAL COMMISSION MUMBAI | Case disposed |
| CC/16/954/2020 | STATE CONSUMER DISPUTES REDRESSAL COMMISSION MUMBAI | Case disposed |
| CC/17/339/2019 | STATE CONSUMER DISPUTES REDRESSAL COMMISSION MUMBAI | Case disposed |
| CC/16/977/2020 | STATE CONSUMER DISPUTES REDRESSAL COMMISSION MUMBAI | Case disposed |
| CC/16/953/2020 | STATE CONSUMER DISPUTES REDRESSAL COMMISSION MUMBAI | Case disposed |
| CC/16/955/2020 | STATE CONSUMER DISPUTES REDRESSAL COMMISSION MUMBAI | Case disposed |
| CC/16/976/2016 | STATE CONSUMER DISPUTES REDRESSAL COMMISSION MUMBAI | Case disposed |
| CR 71/2018/2021 | ADDL CHIEF METROPOLITAN MAGISTRATE Esplanade | bail |
Complaints filed with MahaRERA15
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CC006000000000878 | Nikhil Chopra | Hemant Vinaykant Parikh | 29/09/2017 |
| CC006000000001624 | FRANCISCA CARVALHO | SSV BUILDERS & DEVELOPERS PVT. LTD. | 02/11/2017 |
| CC006000000054661 | FRANCISCA CARVALHO | SSV BUILDERS AND DEVELOPERS PVT. LTD. | 27/05/2018 |
| CC006000000012419 | Vijay Mishra | Hemant Vinaykant Parikh | 08/01/2018 |
| CC006000000012735 | Joyson Richard Albuquerque | Jenninfer Albuquerque | 04/01/2018 |
| CC006000000023013 | Sai Estate Consultants Chembur Pvt Ltd | SSV Builders and Developers Pvt Ltd | 19/01/2018 |
| CC006000000023806 | Ravindran Palraj | Hemant Vinaykant parikh | 19/03/2018 |
| CC006000000193824 | Ravindran Palraj | Hemant Vinayak Parikh | 24/08/2020 |
| CC006000000078959 | Bharat N Shah and Rasila Shah | SSV Developers and Builders | 18/04/2019 |
| CC006000000078960 | Jigar Bharat Maishari | SSV Developers and Builders | 18/04/2019 |
| CC006000000078961 | Nilesh Dungarshi Dedhia | SSV Developers and Builders | 18/04/2019 |
| CC006000000090121 | Roland Pereira and Vanessa Pereira | S S V Developers and Builders | 14/07/2019 |
| CC006000000192366 | Vicenza Buyers Association ( Proposed ) | SSV Builders and Developers Pvt Ltd | 31/01/2020 |
| CC006000000396018 | Puja Sinha | SSV Developers & Builders Pvt. Ltd., | 09/06/2023 |
| CC12500310 | Wasim Akhtar Siddiqui | SSV BUILDERS AND DEVELOPERS PVT LTD | 28/01/2025 |
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 30 Jul 2017 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 17 Mar 2022 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 14 Feb 2025 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 30 Jul 2017Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot due yet
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
possession is promised for 1 Dec 2027
Documents filed103
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 103 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Certificates of CA (Form 3)File: ITR_SSV Developers and Builders PVT LTD_compressed.pdf | 15 Feb 2025 |
| Building plan approvalFile: new_submission_ssv_Developer_Mar_5__2024_6-44_PM.pdf | 14 Feb 2025 |
| Details of encumbrances concerned to FinanceFile: S S V Developers Vol 1 1-207_compressed_compressed_compressed-76-145.pdf | 14 Feb 2025 |
| Details of encumbrances concerned to FinanceFile: S S V Developers Vol 1 1-207_compressed_compressed_compressed-186-207.pdf | 14 Feb 2025 |
| Details of encumbrances concerned to FinanceFile: S S V Developers Vol 1 1-207_compressed_compressed_compressed-146-185.pdf | 14 Feb 2025 |
| Details of encumbrances concerned to FinanceFile: CIVIL WRIT PETITION NO 3328 OF 2021 - SSV DEVELOPER AND BUILDERS - HEMANT PAREKH_0001.pdf | 14 Feb 2025 |
| Details of encumbrances concerned to FinanceFile: DISPATCH COPY OF SERVICE LETTER DATED 13 05 2024 - WRIT PETITION [L] NO 3328 OF 2021.pdf | 14 Feb 2025 |
| Details of encumbrances concerned to FinanceFile: INTERIM APPLICATION NO 7214 OF 2024 IN CIVIL WRIT PETITION NO 3328 OF 2021 - SSV DEVELOPER | 14 Feb 2025 |
| Details of encumbrances concerned to FinanceFile: S S V Developers Vol 1 1-207_compressed_compressed_compressed-1-75.pdf | 14 Feb 2025 |
| Building Plan Approval (IOD)File: new_submission_ssv_Developer_Mar_5__2024_6-44_PM.pdf | 14 Feb 2025 |
| Details of encumbrances concerned to LegalFile: S S V Developers Vol 1 1-207_compressed_compressed_compressed-1-75.pdf | 14 Feb 2025 |
| Details of encumbrances concerned to LegalFile: S S V Developers Vol 1 1-207_compressed_compressed_compressed-76-145.pdf | 14 Feb 2025 |
| Details of encumbrances concerned to LegalFile: S S V Developers Vol 1 1-207_compressed_compressed_compressed-186-207.pdf | 14 Feb 2025 |
| Details of encumbrances concerned to LegalFile: S S V Developers Vol 1 1-207_compressed_compressed_compressed-146-185.pdf | 14 Feb 2025 |
| Details of encumbrances concerned to LegalFile: CIVIL WRIT PETITION NO 3328 OF 2021 - SSV DEVELOPER AND BUILDERS - HEMANT PAREKH_0001.pdf | 14 Feb 2025 |
| Details of encumbrances concerned to LegalFile: DISPATCH COPY OF SERVICE LETTER DATED 13 05 2024 - WRIT PETITION [L] NO 3328 OF 2021.pdf | 14 Feb 2025 |
| Details of encumbrances concerned to LegalFile: INTERIM APPLICATION NO 7214 OF 2024 IN CIVIL WRIT PETITION NO 3328 OF 2021 - SSV DEVELOPER | 14 Feb 2025 |
| Certificates of CA (Form 3)File: balancesheet n profit loss 2024.pdf | 9 Feb 2025 |
| Certificates of CA (Form 5)File: vicenza FORM 5.pdf | 26 Feb 2024 |
| Disclosure of sold/ booked inventoryFile: attachment 1-2.pdf | 22 Mar 2023 |
| Details of encumbrances concerned to FinanceFile: before apex 2017.pdf | 19 Mar 2023 |
| Details of encumbrances concerned to FinanceFile: before apex 2020.pdf | 19 Mar 2023 |
| Details of encumbrances concerned to FinanceFile: writ petition.pdf | 19 Mar 2023 |
| Details of encumbrances concerned to FinanceFile: DoE.pdf | 19 Mar 2023 |
| Details of encumbrances concerned to FinanceFile: EOW bail order.pdf | 19 Mar 2023 |
| Details of encumbrances concerned to LegalFile: before apex 2017.pdf | 19 Mar 2023 |
| Details of encumbrances concerned to LegalFile: before apex 2020.pdf | 19 Mar 2023 |
| Details of encumbrances concerned to LegalFile: writ petition.pdf | 19 Mar 2023 |
| Details of encumbrances concerned to LegalFile: DoE.pdf | 19 Mar 2023 |
| Details of encumbrances concerned to LegalFile: EOW bail order.pdf | 19 Mar 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: (Form 1)(Mandatory for only ongoing project) 2018.pdf | 19 Mar 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: (Form 1)(Mandatory for only ongoing project) 2019.pdf | 19 Mar 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: (Form 1)(Mandatory for only ongoing project) 2020.pdf | 19 Mar 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: (Form 1)(Mandatory for only ongoing project) 2022.pdf | 19 Mar 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: (Form 1)(Mandatory for only ongoing project) 2021.pdf | 19 Mar 2023 |
| Disclosure of sold/ booked inventoryFile: Booking list.pdf | 19 Mar 2023 |
| Certificates of CA (Form 3)File: ITR- FORM- SSV DEVELOPERS AND BUILDERS PVT LTD -2020.pdf | 16 Mar 2023 |
| Certificates of CA (Form 5)File: form 5 19-20.pdf | 16 Mar 2023 |
| Certificates of CA (Form 5)File: form 5 21-22.pdf | 16 Mar 2023 |
| Certificates of CA (Form 3)File: form 3 vicenza ay 21 22.pdf | 29 Jan 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: form1 vicenza.pdf | 20 Jan 2023 |
| Certificates of CA (Form 3)File: form 3 Form_pdf_830974360311221_compressed.pdf | 20 Jan 2023 |
| Certificates of CA (Form 3)File: form 3 ITR6_compressed.pdf | 20 Jan 2023 |
| Details of encumbrances concerned to FinanceFile: acquisition letter hindustan.pdf | 7 Jan 2023 |
| Details of encumbrances concerned to FinanceFile: written submission aqusition.pdf | 7 Jan 2023 |
| Details of encumbrances concerned to FinanceFile: IMG_2310.pdf | 7 Jan 2023 |
| Details of encumbrances concerned to LegalFile: acquisition letter hindustan.pdf | 7 Jan 2023 |
| Details of encumbrances concerned to LegalFile: written submission aqusition.pdf | 7 Jan 2023 |
| Details of encumbrances concerned to LegalFile: IMG_2310.pdf | 7 Jan 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: form 5 vicenza fy 21 22.pdf | 9 Dec 2022 |
| Building plan approvalFile: vicenza approval.pdf | 26 Mar 2022 |
| Building Plan Approval (IOD)File: vicenza approval.pdf | 26 Mar 2022 |
| Building plan approvalFile: Hindustan_chs__Application_For_revised_loi.pdf | 17 Mar 2022 |
| Layout approvalFile: Vighnahar___Sai_Dham_CHS_Ltd-Model.pdf | 17 Mar 2022 |
| Copy of Layout Approval (in case of layout)File: Vighnahar___Sai_Dham_CHS_Ltd-Model.pdf | 17 Mar 2022 |
| Building Plan Approval (IOD)File: Hindustan_chs__Application_For_revised_loi.pdf | 17 Mar 2022 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form no 5 20-21 Annual audit report.pdf | 14 Mar 2022 |
| OtherFile: IOB Letter_compressed.pdf | 6 Mar 2022 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1.pdf | 6 Dec 2020 |
| Certificates of CA (Form 5)File: FORM 5 2018-19.pdf | 6 Dec 2020 |
| Certificates of CA (Form 5)File: FORM 5 2019-20.pdf | 6 Dec 2020 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: ITR 3 FORM 2018-2019.pdf | 6 Dec 2020 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: ITR FORM SSV DEVELOPERS 2018-2019.pdf | 6 Dec 2020 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: ITR V HEMANTA VINAYAK PARIKH 2018-2019.pdf | 6 Dec 2020 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: ITR V SSV DEVELOPERS 2018-2019.pdf | 6 Dec 2020 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: ITR3 Form ( Hemant Parikh).pdf | 6 Dec 2020 |
| OtherFile: ami_resign.pdf | 6 Dec 2020 |
| Certificates of CA (Form 3)File: ITR3 Form ( Hemant Parikh).pdf | 5 Dec 2020 |
| OtherFile: news.pdf | 5 Dec 2020 |
| OtherFile: vicenza_compressed.pdf | 2 Nov 2020 |
| OtherFile: 2 Draft SSV 9 Societies Writ Petition copy.pdf | 2 Nov 2020 |
| Certificates of CA (Form 5)File: Form5 Vicenza.pdf | 25 Jul 2019 |
| OtherFile: annual report on statement.pdf | 27 May 2019 |
| Certificates of CA (Form 3)File: ITR V SSV DEVELOPERS.pdf | 25 May 2019 |
| Certificates of CA (Form 3)File: ITR FORM SSV DEVELOPERS.pdf | 25 May 2019 |
| OtherFile: vicenza.pdf | 25 May 2019 |
| OtherFile: vicenza.pdf | 25 May 2019 |
| OtherFile: SSVPL- Hindustan- Minutes of Decision.pdf | 19 May 2018 |
| Certificates of CA (Form 3)File: FORM NO- 3 CA.pdf | 10 Feb 2018 |
| OtherFile: LEGAL HINDUSTAN SRA ACK.pdf | 30 Dec 2017 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Mumbai Suburban
Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.
Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 1 condition on this project's record read and explained, with the clear checks alongside
- Joined against every project registered within 2 km, which the RERA portal never shows together
- All 103 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
- A watch tells you the moment that changes, including if the registration lapses or a complaint is filed
- But on this project's record so far, expect it to be quiet. You can also save this project free and keep it on your shortlist
Keep Vicenza Residency/Commercial on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near THANE6,700+ in Mumbai Suburban
Filed coordinates, straight-line distance. 175 registered projects within 2 km.
Cons 1221 MIG T/S and 100 Shops S. No. 113 (pt
Mumbai Housing And Area Development Board
Om Siddhivinayak CHS and Gurukrupa CHS
Shreeji Developers
AKASSH AMAZONIA TOWER 1
HEER MEHTA LANDMARK DEVELOPERS PRIVATE LIM
Ajmera Solis
Shree Yogi Realcon Private Limited
CENTRAL PARK
V LAXMI NURSES DEVELOPERS LLP
Swastik Platinum
SUVASYA BUILDERS AND DEVELOPERS LLP
See every Mumbai Suburban project, with the district possession charts
Builder: SSV BUILDERS AND DEVELOPERS PVT LTD
SSV BUILDERS AND DEVELOPERS PVT LTD has 1 registration on MahaRERA, including Vicenza Residency/Commercial. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Mumbai Suburban district page.
Frequently asked questions
What are my rights if Vicenza Residency/Commercial is delayed beyond 1 Dec 2027?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of Vicenza Residency/Commercial?
The registered promoter entity is SSV BUILDERS AND DEVELOPERS PVT LTD, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in Vicenza Residency/Commercial?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against Vicenza Residency/Commercial?
Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
How current is the construction progress shown for Vicenza Residency/Commercial?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at Vicenza Residency/Commercial?
The professionals named in the filing: Architect: HEMANT PARIKH & ASSOCIATES; Engineer: MAHIMTURA CONSULTANTS PVT LTD ( Dinesh Mahimtura ). Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Vicenza Residency/Commercial?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback