ReraGenieLog inGet a buyer report

Home / Browse projects / Bengaluru Urban, Karnataka / VASUNDRA KRISHNASHREYA

Registration approved Residential/Group Housing project

VASUNDRA KRISHNASHREYA

By VASUNDRA BUILDER

RG-KA-06809 · RERA PRM/KA/RERA/1251/309/PR/180425/001562

Source: official RERA Karnataka filing

Red flags

  • No red flags in this filing

Clear

  • No complaints on record
  • Completion date never moved
  • Separate project account declared
Jun 2019Possession promisedno revision filed
0Complaints at RERA Karnatakaon this registration
Jump to the 46 documents Report an error

VASUNDRA KRISHNASHREYA is a Residential/Group Housing project by VASUNDRA BUILDER in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/309/PR/180425/001562 on 25 Apr 2018. Possession is promised by 23 Jun 2019.

At a glance

Project

  • NameVASUNDRA KRISHNASHREYA
  • TypeResidential/Group Housing
  • Location
    • Bengaluru North
    • Bengaluru Urban
  • PincodeNot stated
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PRM/KA/RERA/1251/309/PR/180425/001562
  • ReraGenie IDRG-KA-06809

Builder

  • NameVASUNDRA BUILDER
  • Entity typePartnership Firm
  • Authorized SignatoryC SUBRAMANI
  • OthersGNYANAKUMARI, V UMASHANKAR
  • Declared earlier projects1 →

Key dates

this monthRegisteredApr 2018PromisedJun 2019

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on25 Apr 2018
  • Promised completion23 Jun 2019
  • Revised completionNone
  • Buildings1 building record
  • Documents filed46 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
VASUNDRA KRISHNASHREYA---56056

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

Building:

ActivityProgress
Earth work and other leveling preparation work-
Foundation footing work-
Retaining wall (All types)-
Plinth level Beam-
Sub-structure flooring (Parking Floor, more than one floor below general ground level)-
RCC or MS Framed structure-
Masonry construction: Bricks, Concrete blocks etc-
Plastering inside , outside & Ceiling-
Joinery: Doors, Windows, Ventilators etc-
Basic work of Water supply, Sanitary and Electrification-
Dadoing, Skirting, Flooring, Tiles work (All types)-
Railing and Grill fixing-
Electrification, Water supply and Sanitary Finishing-
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Fire prevention and fire fighting fitting and fixture with networkNot applicable
Weather Proof work(tile,concrete)-
Painting-
Elevation work-
Internal and External work including landscapes as per santioned drawingsNot applicable

Progress on shared amenities41

Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes-
Internal Roads & FootpathsNoNot applicable
Sewage and Drainage SystemYes-
Parks & Tree plantingYes-
Street LightingNoNot applicable
Provision for community buildings and for treatment and disposal of sewage and sullage waterYes-
Solid waste management and disposalYes-
Water conservationNoNot applicable
Energy managementNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Education/Health/Other public amenitiesNoNot applicable
Electricity supply transformer and substationNoNot applicable
Emergency Evacuation servicesNoNot applicable
Storm water drainsNoNot applicable
Use of renewable energyNoNot applicable
Water conservation/rain water harvesting/recharge of ground waterYes-
ElectricityYes-
Smart Home AutomationNoNot applicable
CCTV SurveillanceYes-
Club HouseNoNot applicable
Community HallYes-
Outdoor Sports facilityNoNot applicable
Indoor Sports facilityNoNot applicable
Swimming PoolNoNot applicable
GymYes-
ParksNoNot applicable
Power BackupYes-
GasNoNot applicable
Water and SanitationYes-
Air Conditioning And incerntionNoNot applicable
StaircasesYes-
LiftsYes-
Staircases and Lift lobbies, corridor,lobbies, corridorYes-
Fire escapesNoNot applicable
Common entrance and exit for the building / common portico/foyer/verandahYes-
BasementYes-
TerraceYes-
Outer WallYes-
Open parking areas and common storage spacesNoNot applicable
Provision for lodging of management staff and security staffYes-
Water conservation and renewable energyNoNot applicable

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area2,613 sq m
Named landownersNone

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 14.06 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectYUKTI CONSULTANTS
EngineerINDIGO CONSULTANTS

Complaints filed with RERA Karnataka

No complaints on record against this registration.

Documents filed46

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/309/PR/180425/001562 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
CertificateFile: Memorandum acknowledging receipt.pdf-
Commencement certificate-
First to Third & Terras Floor Plan (w&B)-
Site, Stilt & Front Elevation Plan(W&B)-
PROFORMA OF AGREEMENT OF SALE-
PROFORMA OF AGREEMENT OF SALE-
sale deed-
Ground Floor Plan (W&B)-
Site, Stilt & Front Elevation Plan(W&B)-
Allotment Letter PDF-
Krishnashreya Brochure-
SPECIFICATION-
EC - 1 apr 2001 to 12 oct 2017-
Khatha certificate & Extract-
Joint Development Agreement-
Convertion order-
NOC from Pollution control board-
CHANGE OF LAND-
CHANGE OF LAND-
CHANGE OF LAND-
Legal Report vasundra-
Balance Sheet 2016 - 2017File: Balance sheet.pdf-
Balance Sheet 2015 - 2016File: Balance sheet.pdf-
Balance Sheet 2014 - 2015File: Balance sheet.pdf-
Audited Profit and Loss Statement 2016 - 2017File: Profit & Loss account.pdf-
Audited Profit and Loss Statement 2015 - 2016File: Profit & Loss account.pdf-
Audited Profit and Loss Statement 2014 - 2015File: Profit and Loss account.pdf-
Director's Report 2016 - 2017File: Partners capital account.pdf-
Director's Report 2015 - 2016File: Partners capital account.pdf-
Director's Report 2014 - 2015File: Partners capital account.pdf-
Cash Flow Statement 2016 - 2017File: Partners capital account.pdf-
Cash Flow Statement 2015 - 2016File: Partners capital account.pdf-
Auditor's Report 2016 - 2017File: AUDIT REPORT 17-18.pdf-
Auditor's Report 2015 - 2016File: AUDIT REPORT 16-17.pdf-
Auditor's Report 2014 - 2015File: AUDIT REPORT CLARIFICATION (1).pdf-
Income Tax Return Acknowledgement 2016 - 2017File: ITR COPY.pdf-
Income Tax Return Acknowledgement 2015 - 2016File: Tax return.pdf-
Income Tax Return Acknowledgement 2014 - 2015File: Tax return.pdf-
Declaration of form B 2-
Prospectus/BrochureFile: Krishnashreya Brochure.pdf-
Advertisement Copy 1File: Krishnashreya Brochure.pdf-
Tower Excel SheetFile: excel sheet rera.xlsx-
Occupancy CertificateFile: Occupancy Certificate 1.pdf-
Completion certificate issued by the competent authorityFile: compleation certificate.pdf-
Registered Agreement of SaleFile: Sale agreement SCANED.pdf-
Registered conveyance deed for an individual unitFile: SALE DEED vk.pdf-

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 declared completed, no finish date filed
ProjectLocationStatusPromisedDelivered
VASUNDRA HEIGHTS-Completed-No date filed

How this compares with Bengaluru Urban

34%of Bengaluru Urban projects moved their completion datethis one has not
1%of Bengaluru Urban registrations are shown as withdrawn or revokedthis one is not

Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.

Keep VASUNDRA KRISHNASHREYA on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bengaluru Urban4,100+ in Bengaluru Urban

2 kmVASUNDRA KRISHNASHREYAOther 5Dot size: filed unitsN

Filed coordinates, straight-line distance. 5 registered projects within 2 km.

Builder: VASUNDRA BUILDER

VASUNDRA BUILDER has 1 registration on RERA Karnataka, including VASUNDRA KRISHNASHREYA. Its filings declare 1 earlier project, 1 of them declared completed. Read the full track record. See more projects on the Bengaluru Urban district page.

Frequently asked questions

What are my rights if VASUNDRA KRISHNASHREYA is delayed beyond 23 Jun 2019?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of VASUNDRA KRISHNASHREYA?

The registered promoter entity is VASUNDRA BUILDER, a partnership firm as per the filing. Neither this filing nor this promoter's other RERA Karnataka registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in VASUNDRA KRISHNASHREYA?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at VASUNDRA KRISHNASHREYA?

The professionals named in the filing: Architect: YUKTI CONSULTANTS; Engineer: INDIGO CONSULTANTS. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in VASUNDRA KRISHNASHREYA?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About VASUNDRA KRISHNASHREYA. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save VASUNDRA KRISHNASHREYA to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.