Red flags

  • Completion date moved by 3 months
  • 1 extension taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
Apr 2025Possession promisedmoved 3 months from the original
0Complaints at RERA Karnatakaon this registration
Jump to the 164 documents Report an error

Vaishnavi AT-One Sushruta is a Commercial project by VAISHNAVI PROPERTIES AND SHELTERS in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/310/PR/120522/004881 on 12 May 2022. Possession is promised by 30 Apr 2025. The completion date has moved by 3 months from the original filing.

At a glance

Project

  • NameVaishnavi AT-One Sushruta
  • TypeCommercial
  • Location
    • Bengaluru South
    • Bengaluru Urban
    • 560062
  • Pincode560062
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PRM/KA/RERA/1251/310/PR/120522/004881
  • ReraGenie IDRG-KA-26944

Builder

  • NameVAISHNAVI PROPERTIES AND SHELTERS
  • Entity typePartnership Firm
  • GSTIN29AAGFV0632D1ZD
  • Authorized SignatoryKR Shoban Babu
  • Declared earlier projects2 →

Key dates

this monthRegisteredMay 2022First promiseJan 2025Revised toApr 2025

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on12 May 2022
  • Promised completion30 Apr 2025
  • Revised completionRevised to 30 Apr 2025 (originally 15 Jan 2025)
  • Buildings1 building record
  • Documents filed164 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Vaishnavi Sushruta---099

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 29 Jul 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

Building:

ActivityProgress
Earth work and other leveling preparation work-
Foundation footing work-
Retaining wall (All types)-
Plinth level Beam-
Sub-structure flooring (Parking Floor, more than one floor below general ground level)-
RCC or MS Framed structure-
Masonry construction: Bricks, Concrete blocks etc-
Plastering inside , outside & Ceiling-
Joinery: Doors, Windows, Ventilators etc-
Basic work of Water supply, Sanitary and Electrification-
Dadoing, Skirting, Flooring, Tiles work (All types)-
Railing and Grill fixing-
Electrification, Water supply and Sanitary Finishing-
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Fire prevention and fire fighting fitting and fixture with network-
Weather Proof work(tile,concrete)-
Painting-
Elevation work-
Internal and External work including landscapes as per santioned drawings-

Progress on shared amenities41

As on 29 Jul 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes-
Internal Roads & FootpathsNoNot applicable
Sewage and Drainage SystemYes-
Parks & Tree plantingNoNot applicable
Street LightingYes-
Provision for community buildings and for treatment and disposal of sewage and sullage waterNoNot applicable
Solid waste management and disposalYes-
Water conservationNoNot applicable
Energy managementYes-
Fire protection and fire safety requirementsNoNot applicable
Education/Health/Other public amenitiesYes-
Electricity supply transformer and substationYes-
Emergency Evacuation servicesYes-
Storm water drainsYes-
Use of renewable energyYes-
Water conservation/rain water harvesting/recharge of ground waterYes-
ElectricityYes-
Smart Home AutomationNoNot applicable
CCTV SurveillanceYes-
Club HouseNoNot applicable
Community HallNoNot applicable
Outdoor Sports facilityNoNot applicable
Indoor Sports facilityNoNot applicable
Swimming PoolNoNot applicable
GymNoNot applicable
ParksNoNot applicable
Power BackupYes-
GasNoNot applicable
Water and SanitationYes-
Air Conditioning And incerntionYes-
StaircasesYes-
LiftsYes-
Staircases and Lift lobbies, corridor,lobbies, corridorYes-
Fire escapesYes-
Common entrance and exit for the building / common portico/foyer/verandahYes-
BasementYes-
TerraceYes-
Outer WallYes-
Open parking areas and common storage spacesYes-
Provision for lodging of management staff and security staffYes-
Water conservation and renewable energyYes-

Land and ownership6

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area5,941 sq m
Named landowners6
LandownerVillageDistrict
Tanisha Umesh Raju--
Chandni C Raju--
Tejas C Raju--
A C Chandrashekar Raju--
Akila C Raju--
Yeshoda Chandrashekar Raju--

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 127.83 cr
Cost lineEstimatedIncurred
Estimated Cost of Construction as certified by EngineerRs 107.26 cr-
Payment of taxesRs 17.16 cr-
On-site expenditure-Consultants FeesRs 2.90 cr-
Interest on BorrowingRs 50.27 lakh-

Certifying professionals and partners3

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectAnand. S
EngineerHareesh Gowda
Chartered AccountantS. P. Krishnamurthy & Co

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EX/PRM/KA/RERA/1251/310/PR/250908/004881Jan 2025 → Apr 2025

Reason as filed by the promoterShortage of Labour

Complaints filed with RERA Karnataka

No complaints on record against this registration.

Documents filed164

As listed on the registration, under the names the promoter filed them with; the newest 80 of 164 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/310/PR/120522/004881 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
RERA letterFile: RERA letter with the enclosure.pdf29 Jul 2025
Occupancy CertificateFile: OC - Vaishnavi AT-One Sushruta.pdf29 Jul 2025
Uploaded and Submitted the Annual Audit ReportFile: SUBMISSION CONFIRMATION - 2024.pdf21 Mar 2025
Uploaded the Form BFile: Form B - New extension.pdf21 Mar 2025
Uploaded the Sanction PlanFile: Modification plan - hospital.pdf21 Mar 2025
Uploaded the Building LicenceFile: Building Licence.pdf21 Mar 2025
Uploaded Commencement certificateFile: Commencement certificate - V Sushruta.pdf21 Mar 2025
Audited financial statement for 2018-19 with CAUDINFile: Balance Sheet FY 18-19.pdf4 May 2022
Advocate Search ReportFile: Title Report Adv Search Report.pdf4 May 2022
Proforma of Allotment LetterFile: Propforma Allottment Letter.pdf4 May 2022
Agreement of Sale (AOS)File: Proforma ATS.pdf4 May 2022
Certified Extract of Master PlanFile: CDP_mapA.pdf4 May 2022
Attested copy of BWSSB NOCFile: BWSSB NOC.pdf4 May 2022
Attested copy of BESCOM NOCFile: BESCOM NOC.pdf4 May 2022
Section 3(1) Notarized AffidavitFile: Notarized Affidavit 1.pdf4 May 2022
Attested copy of Airport NOCFile: Airport-Manipal.pdf4 May 2022
BESCOM Fee RecieptFile: Bescom Fee Receipt.jpg4 May 2022
Highlighted STP demarcation along with STP design drawingsFile: STP Location _Third Basement Floor Plan.pdf4 May 2022
BSNL NOCFile: NA Blank.pdf4 May 2022
Signed copy of project specificationFile: Project Specification Scope of Work.pdf4 May 2022
Registration CertificateFile: Certificate of Registration-VPS attested.pdf-
Partnership DeedFile: VPS-PARTNERSHIP DEED-20-11-2008.pdf-
Partner Details-
Partner Details-
Certificate issued by CA Form 1File: POST REGISTRATION Form-1 Chartered Accountant Certificate (PR).pdf-
Certificate issued by Architect Form 2File: Form 5 - Architect certificate.pdf-
Certificate issued by Engineer Form 3File: Form 6 Engg certificate.pdf-
TDR Purchase Deed / Sale DeedFile: TDR.pdf-
Project Chartered Accountant-
Project Engineer-
Project Architect-
AffidavitFile: No Litigation Affidavit.pdf-
Certificate from Chartered AccountFile: CA certificate.pdf-
Certificate from Chartered AccountFile: CA certificate.pdf-
Balance Sheet 2020 - 2021File: FY 2021-22 Under Progress.pdf-
Balance Sheet 2019 - 2020File: Balance Sheet FY 20-21.pdf-
Balance Sheet 2018 - 2019File: Balance Sheet FY 19-20.pdf-
Audited Profit and Loss Statement 2020 - 2021File: FY 2021-22 Under Progress.pdf-
Audited Profit and Loss Statement 2019 - 2020File: P & L FY 20-21_compressed.pdf-
Audited Profit and Loss Statement 2018 - 2019File: P & L FY 19-20.pdf-
Director's Report 2020 - 2021File: NA Partnership Firm.pdf-
Director's Report 2019 - 2020File: NA Partnership Firm.pdf-
Director's Report 2018 - 2019File: NA Partnership Firm.pdf-
Cash Flow Statement 2020 - 2021File: CFS- NA as this is LLP.pdf-
Cash Flow Statement 2019 - 2020File: CFS- NA as this is LLP.pdf-
Auditor's Report 2020 - 2021File: Audit Report NA FY 21 - 22.PDF-
Auditor's Report 2019 - 2020File: Audit Report NA FY 20 - 21.PDF-
Auditor's Report 2018 - 2019File: Audit Report NA FY 19 - 20.PDF-
Income Tax Return Acknowledgement 2020 - 2021File: FY 2021-22 Under Progress.pdf-
Income Tax Return Acknowledgement 2019 - 2020File: VPS ITR ACKNOWLEDGEMENT AY 2021.pdf-
Income Tax Return Acknowledgement 2018 - 2019File: VPS ITR ACKNOWLEDGEMENT AY 2020.pdf-
NA Blank-
BESCOM NOC-
BWSSB NOC compressed-
NA Blank-
Project plan-
NA Blank-
NA Blank-
NA Blank-
Project Specification Scope of Work-
Elevation & Section compressed-
NA Blank-
Form 3 Engineers Certificate-
Title Report Adv Search Report-
NA Blank-
JDA-
CONVERSION ORDERcompressed-
CONVERSION ORDERcompressed-
NA Blank-
release deed-
Proforma ATS-
Proforma ATS-
Vaishnavi Sushruta - Brochure-
Form B Declaration compressed-
Notarized Affidavit 1 compressed-
Joint Affidavit compressed-
BESCOM NOC-
BWSSB NOC compressed-
NA Blank-
NA Blank-

Promoter's earlier projects2

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

2 declared completed, no finish date filed
ProjectLocationStatusPromisedDelivered
Vaishnavi SolitaireNo 3/A, 3rd Block, KoramangalaCompleted-No date filed
Vaishnavi MeridianNo 12, PID No. 78-1-12, Infantry Rd, Shivaji Nagar,Completed-No date filed

How this compares with Bengaluru Urban

34%of Bengaluru Urban projects moved their completion datethis one moved by 3 months
1%of Bengaluru Urban registrations are shown as withdrawn or revokedthis one is not

Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.

Keep Vaishnavi AT-One Sushruta on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bengaluru Urban4,100+ in Bengaluru Urban

2 kmVaishnavi AT-One SushrutOther 17Dot size: filed unitsN

Filed coordinates, straight-line distance. 17 registered projects within 2 km.

Builder: VAISHNAVI PROPERTIES AND SHELTERS

VAISHNAVI PROPERTIES AND SHELTERS has 1 registration on RERA Karnataka, including Vaishnavi AT-One Sushruta. Its filings declare 2 earlier projects, 2 of them declared completed. Read the full track record. See more projects on the Bengaluru Urban district page.

Frequently asked questions

What are my rights if Vaishnavi AT-One Sushruta is delayed beyond 30 Apr 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of Vaishnavi AT-One Sushruta?

The registered promoter entity is VAISHNAVI PROPERTIES AND SHELTERS, a partnership firm as per the filing. Its GSTIN 29AAGFV0632D1ZD can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in Vaishnavi AT-One Sushruta?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at Vaishnavi AT-One Sushruta?

The professionals named in the filing: Architect: Anand. S; Engineer: Hareesh Gowda; Chartered Accountant: S. P. Krishnamurthy & Co. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Vaishnavi AT-One Sushruta?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Vaishnavi AT-One Sushruta. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Vaishnavi AT-One Sushruta to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.