Home / Browse projects / Bengaluru Urban, Karnataka / CASAGRAND CASABLANCA
CASAGRAND CASABLANCA
By CASAGRAND LOTUS PRIVATE LIMITED
RG-KA-62614 · RERA PRM/KA/RERA/1251/310/PR/040524/006862 · Last updated on RERA Karnataka portal: 14 Oct 2026
Source: official RERA Karnataka filing
Red flags
- 4 complaints at RERA Karnataka
Clear
- No litigation declared
- Completion date never moved
- Separate project account declared
Saved.
CASAGRAND CASABLANCA is a Residential/Group Housing project by CASAGRAND LOTUS PRIVATE LIMITED in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/310/PR/040524/006862 on 4 May 2024. Possession is promised by 4 May 2029. 790 of the 805 units on this registration are recorded sold or booked, and 5 of 19 construction stages are filed complete. 4 complaints are on record with the regulator.
At a glance
Project
- NameCASAGRAND CASABLANCA
- TypeResidential/Group Housing
- Location
- Bengaluru South
- Bengaluru Urban
- 560062
- Pincode560062
- MapView location on Google Maps (as filed on RERA)
- RERA no.PRM/KA/RERA/1251/310/PR/040524/006862
- ReraGenie IDRG-KA-62614
Builder
- NameCASAGRAND LOTUS PRIVATE LIMITED
- Entity typeCompany
- CINU70109TN2022PTC153057
- GSTIN29AAKCC3896R1ZH
- Authorized SignatorySethupathy G
- MdARUN M N
- DirectorsCG SATHISH, ARUN M N, T Jagmohan
- Project HeadRobert Singh F
Key dates
Key facts
Registration and timeline
- StatusRegistration approved
- Registered on4 May 2024
- Promised completion4 May 2029
- Revised completionNone
- Buildings4 building records
- Documents filed194 files
Current status
Figures as on 14 Oct 2026, this project's latest RERA Karnataka filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| Tower 1 | - | - | - | 227 | 0 | 227 |
| Tower 2 | - | - | - | 227 | 0 | 227 |
| Tower 3 | - | - | - | 64 | 0 | 64 |
| Tower 4 | - | - | - | 287 | 0 | 287 |
The full filing
Everything below is from the project's own RERA Karnataka filing, free to read.
Construction progress by building1
As on 14 Oct 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
5 of 19 construction stages are filed complete. The stage furthest along is RCC or MS Framed structure, at 60%.
Building: 37% average across the applicable activities
| Activity | Progress |
|---|---|
| Earth work and other leveling preparation work | 100% |
| Foundation footing work | 100% |
| Upto Plinth Level | 100% |
| Sub-structure flooring (Parking Floor, more than one floor below general ground level) | 100% |
| Retaining wall (All types) | 100% |
| RCC or MS Framed structure | 60% |
| Masonry Construction | 60% |
| Plastering inside , outside & Ceiling | 20% |
| Joinery: Doors, Windows, Ventilators etc | 0% |
| Basic work of Water supply, Sanitary and Electrification | 0% |
| Dadoing, Skirting, Flooring, Tiles work (All types) | 0% |
| Railing and Grill fixing | 0% |
| Electrification, Water supply and Sanitary Finishing | 10% |
| Painting | 10% |
| Fire prevention and fire fighting fitting and fixture with network | 10% |
| Weather Proof work(tile,concrete) | 10% |
| Wardrobe, Showcase, Kitchen cabinet, Puja work | 10% |
| Elevation work | 10% |
| Internal and External work including landscapes as per sanctioned drawings | 10% |
Progress on shared amenities40
As on 14 Oct 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Water Supply | Yes | 10% |
| Sewage and Drainage System | Yes | 10% |
| Water conservation/rain water harvesting/recharge of ground water | Yes | 10% |
| Energy management | No | Not applicable |
| Fire protection and fire safety requirements | Yes | 10% |
| Solid waste management and disposal | Yes | 10% |
| Emergency Evacuation services | No | Not applicable |
| Internal Roads & Footpaths | Yes | 10% |
| Electricity supply transformer and substation | Yes | 10% |
| Storm water drains | Yes | 10% |
| Use of renewable energy | No | Not applicable |
| Sewage Treatment Plant (STP) | Yes | 10% |
| Parks & Tree planting | Yes | 10% |
| Street Lighting | Yes | 10% |
| Electricity | Yes | 10% |
| Smart Home Automation | No | Not applicable |
| CCTV Surveillance | Yes | 10% |
| Club House | Yes | 10% |
| Community Hall | Yes | 10% |
| Outdoor Sports facility | Yes | 10% |
| Indoor Sports facility | Yes | 10% |
| Swimming Pool | Yes | 10% |
| Gym | Yes | 10% |
| Parks | Yes | 10% |
| Power Backup | Yes | 10% |
| Piped Gas | Yes | 10% |
| Water and Sanitation | Yes | 10% |
| Air Conditioning | No | Not applicable |
| Staircases | Yes | 10% |
| Lifts | Yes | 10% |
| Corridor/Lobbies | Yes | 10% |
| Fire escapes | Yes | 10% |
| Common entrance and exit for the building/common portico/foyer/verandah | Yes | 10% |
| Basement | No | Not applicable |
| Terrace | Yes | 10% |
| Outer Wall | Yes | 10% |
| Open parking areas | Yes | 10% |
| Provision for lodging of management staff and security staff | Yes | 10% |
| Water conservation and renewable energy | Yes | 10% |
| Common storage spaces | Yes | 10% |
Land and ownership8
This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
| Landowner | Village | District |
|---|---|---|
| CASAGRAND LOTUS PRIVATE LIMITED | - | - |
| CASAGRAND LOTUS PRIVATE LIMITED | - | - |
| CASAGRAND LOTUS PRIVATE LIMITED | - | - |
| CASAGRAND LOTUS PRIVATE LIMITED | - | - |
| CASAGRAND LOTUS PRIVATE LIMITED | - | - |
| CASAGRAND LOTUS PRIVATE LIMITED | - | - |
| CASAGRAND LOTUS PRIVATE LIMITED | - | - |
| CASAGRAND LOTUS PRIVATE LIMITED | - | - |
Project account and cost
70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Cost line | Estimated | Incurred |
|---|---|---|
| Estimated Cost of Construction as certified by Engineer | Rs 475.34 cr | Rs 13.21 cr |
| Principal sum and interest payable to financial institutions-Money Lenders on construction funding or money borrowed for construction | Rs 100.00 cr | - |
| Payment of taxes | Rs 75.00 cr | - |
| Administrative Costs | Rs 30.00 cr | - |
| On-site expenditure-Consultants Fees | Rs 8.00 cr | - |
Certifying professionals and partners3
Certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | P S NAGESH |
| Engineer | Shivaraj G Naik |
| Chartered Accountant | NARAYANA RAO M |
Complaints filed with RERA Karnataka4
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| 01212/2024 | - | CASAGRAND LOTUS PRIVATE LIMITED | 19/11/2024 |
| 00924/2025 | - | CASAGRAND LOTUS PRIVATE LIMITED | 11/07/2025 |
| 00876/2026 | - | CASAGRAND LOTUS PRIVATE LIMITED | 27/07/2026 |
| 00877/2026 | - | CASAGRAND LOTUS PRIVATE LIMITED | 27/07/2026 |
Documents filed194
As listed on the registration, under the names the promoter filed them with; the newest 80 of 194 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/310/PR/040524/006862 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Q2 2026-27 Form-4 Certificate issued by Chartered AccountantFile: RERA CA form 4 sep 2026 Casablanca.pdf | 14 Oct 2026 |
| Q2 2026-27 Form-5 Certificate issued by ArchitectFile: FORM 5.pdf | 14 Oct 2026 |
| Q2 2026-27 Form-6 Certificate issued by Structural EngineerFile: Casablanc Form 6 SEP 2026.pdf | 14 Oct 2026 |
| Q2 2026-27 Water supply and sewage board | 14 Oct 2026 |
| Q2 2026-27 KSPCB- PCB (10 Acres to 125 Acres) | 14 Oct 2026 |
| Q2 2026-27 KPTCL- BESCOM | 14 Oct 2026 |
| Q2 2026-27 Fire and Safety | 14 Oct 2026 |
| Q2 2026-27 Airport Authority of India | 14 Oct 2026 |
| Q2 2026-27 BSNL/Telecommunication Department | 14 Oct 2026 |
| Q1 2026-27 Form-4 Certificate issued by Chartered AccountantFile: RERA CA form 4 june 2026 Casablanca.pdf | 10 Jul 2026 |
| Q1 2026-27 Form-5 Certificate issued by ArchitectFile: Architect cert QU1 june 2026.pdf | 10 Jul 2026 |
| Q1 2026-27 Form-6 Certificate issued by Structural EngineerFile: Engg certifiacte.pdf | 10 Jul 2026 |
| Q1 2026-27 Water supply and sewage board | 10 Jul 2026 |
| Q1 2026-27 KSPCB- PCB (10 Acres to 125 Acres) | 10 Jul 2026 |
| Q1 2026-27 KPTCL- BESCOM | 10 Jul 2026 |
| Q1 2026-27 Fire and Safety | 10 Jul 2026 |
| Q1 2026-27 Airport Authority of India | 10 Jul 2026 |
| Q1 2026-27 BSNL/Telecommunication Department | 10 Jul 2026 |
| Q4 2025-26 Form-4 Certificate issued by Chartered AccountantFile: CA Certificate.pdf | 11 Apr 2026 |
| Q4 2025-26 Form-5 Certificate issued by ArchitectFile: Architect cert Proj Casablanca.pdf | 11 Apr 2026 |
| Q4 2025-26 Form-6 Certificate issued by Structural EngineerFile: Engg Proj Casablanca Qtr.pdf | 11 Apr 2026 |
| Q4 2025-26 Water supply and sewage board | 11 Apr 2026 |
| Q4 2025-26 KSPCB- PCB (10 Acres to 125 Acres) | 11 Apr 2026 |
| Q4 2025-26 KPTCL- BESCOM | 11 Apr 2026 |
| Q4 2025-26 Airport Authority of India | 11 Apr 2026 |
| Q4 2025-26 BSNL/Telecommunication Department | 11 Apr 2026 |
| Q3 2025-26 Form-4 Certificate issued by Chartered AccountantFile: CA Certificate.pdf | 9 Jan 2026 |
| Q3 2025-26 Form-5 Certificate issued by ArchitectFile: Architect cert Q3 25 Proj Casablanca.pdf | 9 Jan 2026 |
| Q3 2025-26 Form-6 Certificate issued by Structural EngineerFile: Engg Proj Casablanca Dec 25 Qtr.pdf | 9 Jan 2026 |
| Q3 2025-26 Water supply and sewage board | 9 Jan 2026 |
| Q3 2025-26 KPTCL- BESCOM | 9 Jan 2026 |
| Q3 2025-26 Fire and Safety | 9 Jan 2026 |
| Q3 2025-26 Airport Authority of India | 9 Jan 2026 |
| Q3 2025-26 BSNL/Telecommunication Department | 9 Jan 2026 |
| RELINQUISHMENT DEEDFile: 1 RELINQUISHMENT DEED.pdf | 3 May 2024 |
| BDA Zonal RegulationsFile: 2 BDA Zonal Regulations.pdf | 3 May 2024 |
| Engineer LicenseFile: 3 Engineer License.pdf | 3 May 2024 |
| CASAGRAND CASABLANCA- AMENITIES LIST & COMMON AREASFile: 4 CASAGRAND CASABLANCA- AMENITIES LIST & COMMON AREAS.pdf | 3 May 2024 |
| Land cost clarificationFile: 5 Land cost clarification.pdf | 3 May 2024 |
| Source of Water ClarificationFile: 6 Source of Water Clarification.pdf | 3 May 2024 |
| Khata Clarification with supporting docsFile: 2 Khata Clarification with supporting docs.pdf | 3 May 2024 |
| New Conversion Order Sy No 18-3File: 3 New Conversion Order Sy No 18-3.pdf | 3 May 2024 |
| OLD Conversion Order Sy No 18-1A12File: 4 OLD Conversion Order Sy No 18-1A12.pdf | 3 May 2024 |
| New Conversion Order Sy No 18-1A12File: 5 New Conversion Order Sy No 18-1A12.pdf | 3 May 2024 |
| OLD Conversion Order Sy No 18-1A11File: 6 OLD Conversion Order Sy No 18-1A11.pdf | 3 May 2024 |
| New Conversion Order Sy No 18-1A11File: 7 New Conversion Order Sy No 18-1A11.pdf | 3 May 2024 |
| OLD Conversion Order Sy No 18-1A10File: 8 OLD Conversion Order Sy No 18-1A10.pdf | 3 May 2024 |
| New Conversion Order Sy No 18-1A10File: 9 New Conversion Order Sy No 18-1A10.pdf | 3 May 2024 |
| OLD Conversion Order Sy No 18-1A9File: 10 OLD Conversion Order Sy No 18-1A9.pdf | 3 May 2024 |
| New Conversion Order Sy No 18-1A9File: 11 New Conversion Order Sy No 18-1A9.pdf | 3 May 2024 |
| OLD Conversion Order Sy No 18-1A8File: 12 OLD Conversion Order Sy No 18-1A8.pdf | 3 May 2024 |
| New Conversion Order Sy No 18-1A8File: 13 New Conversion Order Sy No 18-1A8.pdf | 3 May 2024 |
| OLD Conversion Order Sy No 18-1A7File: 14 OLD Conversion Order Sy No 18-1A7.pdf | 3 May 2024 |
| New Conversion Order Sy No 18-1A7File: 15 New Conversion Order Sy No 18-1A7.pdf | 3 May 2024 |
| OLD Conversion Order Sy No 18-1A5File: 16 OLD Conversion Order Sy No 18-1A5.pdf | 3 May 2024 |
| New Conversion Order Sy No 18-1A5File: 17 New Conversion Order Sy No 18-1A5.pdf | 3 May 2024 |
| All Sy No RTCsFile: 1 All Sy No RTCs.pdf | 3 May 2024 |
| Clarification on A KHARABFile: 18 Clarification on A KHARAB.pdf | 3 May 2024 |
| Clarification on Land Procurement source with supporting docsFile: 2 Clarification on Land Procurement source with supporting docs.pdf | 3 May 2024 |
| Source of funds with supporting docsFile: 3 Source of funds with supporting docs.pdf | 3 May 2024 |
| PARENT COMPANY BALANCE SHEET EXTRACTFile: 4 PARENT COMPANY BALANCE SHEET EXTRACT.pdf | 3 May 2024 |
| LAND COST STATEMENTFile: 5 LAND COST STATEMENT.pdf | 3 May 2024 |
| REGISTRATION COST STATEMENTFile: 6 REGISTRATION COST STATEMENT.pdf | 3 May 2024 |
| Form-1 CA CertificateFile: 1 Form-1 CA Certificate.pdf | 3 May 2024 |
| RTC, survey 18/1A5 | - |
| Mutation, survey 18/1A5 | - |
| Encumbrance Certificate, survey 18/1A5 | - |
| Conversion/Alienation Order, survey 18/1A5 | - |
| Sale/Title/Gift Deed, survey 18/1A5 | - |
| Khatha, survey 18/1A5 | - |
| RTC, survey 18/3 | - |
| Mutation, survey 18/3 | - |
| Encumbrance Certificate, survey 18/3 | - |
| Conversion/Alienation Order, survey 18/3 | - |
| Sale/Title/Gift Deed, survey 18/3 | - |
| Khatha, survey 18/3 | - |
| RTC, survey 18/1A7 | - |
| Mutation, survey 18/1A7 | - |
| Encumbrance Certificate, survey 18/1A7 | - |
| Conversion/Alienation Order, survey 18/1A7 | - |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Bengaluru Urban
Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.
Keep CASAGRAND CASABLANCA on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Bengaluru Urban4,100+ in Bengaluru Urban
Filed coordinates, straight-line distance. 33 registered projects within 2 km.
Assetz Meru & Meadow
GOKULAM SHELTERS PRIVATE LIMITED
Sattva Forest Ridge
Sattva Resi Private Limited
CASAGRAND ZAIDEN
CASA GRANDE GARDEN CITY BUILDERS PVT LTD
MAHINDRA EDEN PHASE-1
MAHINDRA LIFESPACE DEVELOPERS LIMITED
MAHINDRA EDEN PHASE-2
MAHINDRA LIFESPACE DEVELOPERS LIMITED
RAINBOW UNO
M/S. RAINVAS INFRAA
See every Bengaluru Urban project, with the district possession charts
Builder: CASAGRAND LOTUS PRIVATE LIMITED
CASAGRAND LOTUS PRIVATE LIMITED has 1 registration on RERA Karnataka, including CASAGRAND CASABLANCA. Its filings disclose no earlier RERA Karnataka projects. Read the full track record. See more projects on the Bengaluru Urban district page.
Frequently asked questions
What are my rights if CASAGRAND CASABLANCA is delayed beyond 4 May 2029?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.
How do I verify and contact the developer of CASAGRAND CASABLANCA?
The registered promoter entity is CASAGRAND LOTUS PRIVATE LIMITED, a company as per the filing. Its CIN U70109TN2022PTC153057 and GSTIN 29AAKCC3896R1ZH can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.
Is my payment protected in CASAGRAND CASABLANCA?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against CASAGRAND CASABLANCA?
Each case number above is a complaint filed with RERA Karnataka. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
Who certifies construction progress at CASAGRAND CASABLANCA?
The professionals named in the filing: Architect: P S NAGESH; Engineer: Shivaraj G Naik; Chartered Accountant: NARAYANA RAO M. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in CASAGRAND CASABLANCA?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.
Report an error Share feedback