Home / Browse projects / Bengaluru Urban, Karnataka / CASAGRAND ZAIDEN

Registration approved No litigation declared Residential/Group Housing project

CASAGRAND ZAIDEN

By CASA GRANDE GARDEN CITY BUILDERS PVT LTD

RG-KA-10137 · RERA PRM/KA/RERA/1251/310/PR/120423/005862 · Last updated on RERA Karnataka portal: 14 Oct 2026

Source: official RERA Karnataka filing

Red flags

  • 5 complaints at RERA Karnataka
  • Completion date moved by 12 months
  • 1 extension taken

Clear

  • No litigation declared
  • Separate project account declared
Mar 2027Possession promisedmoved 12 months from the original
12 of 18Construction stages donefurthest along: Electrification, 80%
0 of 286Units unsoldnot recorded sold or booked
5Complaints at RERA Karnatakaon this registration
Jump to the 168 documents Report an error

CASAGRAND ZAIDEN is a Residential/Group Housing project by CASA GRANDE GARDEN CITY BUILDERS PVT LTD in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/310/PR/120423/005862 on 12 Apr 2023. Possession is promised by 22 Mar 2027. The completion date has moved by 12 months from the original filing. 286 of the 286 units on this registration are recorded sold or booked, and 12 of 18 construction stages are filed complete. 5 complaints are on record with the regulator.

At a glance

Project

  • NameCASAGRAND ZAIDEN
  • TypeResidential/Group Housing
  • Location
    • Bengaluru South
    • Bengaluru Urban
    • 560062
  • Pincode560062
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PRM/KA/RERA/1251/310/PR/120423/005862
  • ReraGenie IDRG-KA-10137

Builder

  • NameCASA GRANDE GARDEN CITY BUILDERS PVT LTD
  • Entity typeCompany
  • CINU45205KA2015PTC082415
  • GSTIN29AAGCC1577R1ZV
  • Authorized SignatorySethupathy G
  • MdARUN M N
  • DirectorsCG SATHISH, ARUN M N, T Jagmohan
  • Project HeadSRIRAM
  • Other registrations16 more →
  • Declared earlier projects12 →

Key dates

this monthRegisteredApr 2023First promiseMar 2026Revised toMar 2027

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on12 Apr 2023
  • Promised completion22 Mar 2027
  • Revised completionRevised to 22 Mar 2027 (originally 22 Mar 2026)
  • Buildings3 building records
  • Documents filed168 files

Current status

100%286 of 286 units booked
5.4%Of the estimated cost spent so far

Figures as on 14 Oct 2026, this project's latest RERA Karnataka filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Tower A---81081
Tower B---95095
Tower C---1100110

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 14 Oct 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

12 of 18 construction stages are filed complete. The stage furthest along is Electrification, at 80%.

Building: 93% average across the applicable activities

ActivityProgress
Earth work and other leveling preparation work100%
Foundation footing work100%
Upto Plinth Level100%
Sub-structure flooring (Parking Floor, more than one floor below general ground level)100%
Retaining wall (All types)100%
RCC or MS Framed structure100%
Masonry Construction100%
Plastering inside , outside & Ceiling100%
Joinery: Doors, Windows, Ventilators etc100%
Basic work of Water supply, Sanitary and Electrification100%
Dadoing, Skirting, Flooring, Tiles work (All types)100%
Railing and Grill fixing100%
Electrification, Water supply and Sanitary Finishing80%
Painting80%
Fire prevention and fire fighting fitting and fixture with network80%
Weather Proof work(tile,concrete)80%
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Elevation work80%
Internal and External work including landscapes as per sanctioned drawings80%

Progress on shared amenities40

As on 14 Oct 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes80%
Sewage and Drainage SystemYes80%
Water conservation/rain water harvesting/recharge of ground waterYes80%
Energy managementNoNot applicable
Fire protection and fire safety requirementsYes80%
Solid waste management and disposalYes80%
Emergency Evacuation servicesYes80%
Internal Roads & FootpathsYes80%
Electricity supply transformer and substationYes80%
Storm water drainsYes80%
Use of renewable energyNoNot applicable
Sewage Treatment Plant (STP)Yes80%
Parks & Tree plantingYes80%
Street LightingYes80%
ElectricityYes70%
Smart Home AutomationNoNot applicable
CCTV SurveillanceYes70%
Club HouseYes70%
Community HallYes70%
Outdoor Sports facilityYes70%
Indoor Sports facilityNoNot applicable
Swimming PoolYes70%
GymYes70%
ParksNoNot applicable
Power BackupYes70%
Piped GasNoNot applicable
Water and SanitationYes70%
Air ConditioningNoNot applicable
StaircasesYes80%
LiftsYes80%
Corridor/LobbiesYes80%
Fire escapesYes80%
Common entrance and exit for the building/common portico/foyer/verandahYes80%
BasementYes80%
TerraceYes80%
Outer WallYes80%
Open parking areasYes80%
Provision for lodging of management staff and security staffYes80%
Water conservation and renewable energyNoNot applicable
Common storage spacesYes80%

Land and ownership1

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area14,928 sq m
Named landowners1
LandownerVillageDistrict
M/s CASA GRANDE CITY GARDEN CITY BUILDERS PVT LTD--

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 104.53 cr
Cost incurredRs 5.62 cr
Spent of the estimate5.38%
Cost lineEstimatedIncurred
Estimated Cost of Construction as certified by EngineerRs 104.53 crRs 5.62 cr

Certifying professionals and partners3

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectDILIP NADIG
EngineerShivaraj G Naik
Chartered AccountantNARAYANA RAO M

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EX/PRM/KA/RERA/1251/310/PR/260911/005862Mar 2026 → Mar 2027

Reason as filed by the promoterShortage of Labour

Complaints filed with RERA Karnataka5

Case no.ComplainantRespondentFiled
01808/2023-CASA GRANDE GARDEN CITY BUILDERS PVT LTD08/12/2023
01863/2023-CASA GRANDE GARDEN CITY BUILDERS PVT LTD21/12/2023
01351/2024-CASA GRANDE GARDEN CITY BUILDERS PVT LTD24/12/2024
00431/2026-CASA GRANDE GARDEN CITY BUILDERS PVT LTD22/04/2026
00871/2026-CASA GRANDE GARDEN CITY BUILDERS PVT LTD27/07/2026

Documents filed168

As listed on the registration, under the names the promoter filed them with; the newest 80 of 168 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/310/PR/120423/005862 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Q2 2026-27 Form-4 Certificate issued by Chartered AccountantFile: RERA CA form 4 sep 2026 Zaiden.pdf14 Oct 2026
Q2 2026-27 Form-5 Certificate issued by ArchitectFile: Form 5- CG Zaiden.pdf14 Oct 2026
Q2 2026-27 Form-6 Certificate issued by Structural EngineerFile: Zaiden SEP 2026.pdf14 Oct 2026
Q2 2026-27 Water supply and sewage board14 Oct 2026
Q2 2026-27 KSPCB- PCB (10 Acres to 125 Acres)14 Oct 2026
Q2 2026-27 KPTCL- BESCOM14 Oct 2026
Q2 2026-27 Airport Authority of India14 Oct 2026
Affidavit & Nocs with clarificationFile: Affidavit & Nocs with clarification.pdf7 Sep 2026
Sold & unsold details with Allottees listFile: Sold & unsold details wiyh Allottees list.pdf3 Sep 2026
clarification on Dispatch number & NocFile: clarification on Dispatch number & Noc.pdf3 Sep 2026
BESCOM NOCFile: BESCOM NOC.pdf3 Sep 2026
BWSSB NOCFile: BWSSB NOC.pdf3 Sep 2026
Approval/NOC under section 109 of KLR Act 1961File: Balance confirmation_HCFBLRCTL00013076544.pdf16 Jul 2026
Approval/NOC under section 14 of the KTCP ActFile: Balance confirmation_HCFBLRCTL00013076544.pdf16 Jul 2026
Loan amount deposited into RERA designated accountFile: Balance confirmation_HCFBLRCTL00013076544.pdf16 Jul 2026
Bank StatementFile: Bank Statement.pdf16 Jul 2026
Renewed Approved Building planFile: Zaiden Approved Building Plan.pdf16 Jul 2026
Renewed Approved Building plan order letterFile: Zaiden Builing Permit Licence Copy.pdf16 Jul 2026
self attested engineer licenceFile: 3 Engineer License.pdf16 Jul 2026
BWSSB NOCFile: BWSSB NOC.pdf16 Jul 2026
BESCOM NOCFile: BESCOM NOC.pdf16 Jul 2026
AAIFile: AAI NOC.pdf16 Jul 2026
MOEFFile: MOEF NOC.pdf16 Jul 2026
KSPCBFile: KSPCB CFE.pdf16 Jul 2026
FIRE NOCFile: FIRE NOC.pdf16 Jul 2026
BNPFile: BNP.pdf16 Jul 2026
Sold and unsold detailsFile: Sold & Unsold Details.xlsx16 Jul 2026
BWSSB ACKFile: ZAIDEN BWSSB NOC ACK.pdf16 Jul 2026
Q1 2026-27 Form-4 Certificate issued by Chartered AccountantFile: RERA CA form 4 june 2026 Zaiden.pdf10 Jul 2026
Q1 2026-27 Form-5 Certificate issued by ArchitectFile: Architect cert QU1 2026 .pdf10 Jul 2026
Q1 2026-27 Form-6 Certificate issued by Structural EngineerFile: Engg Proj Zaiden Jun 2026 Qtr.pdf10 Jul 2026
Q1 2026-27 Water supply and sewage board10 Jul 2026
Q1 2026-27 KSPCB- PCB (10 Acres to 125 Acres)10 Jul 2026
Q1 2026-27 KPTCL- BESCOM10 Jul 2026
Q1 2026-27 Airport Authority of India10 Jul 2026
Q4 2025-26 Form-4 Certificate issued by Chartered AccountantFile: CA Certificate.pdf11 Apr 2026
Q4 2025-26 Form-5 Certificate issued by ArchitectFile: Architect cert Proj Zaiden.pdf11 Apr 2026
Q4 2025-26 Form-6 Certificate issued by Structural EngineerFile: Engg Proj Zaiden Qtr.pdf11 Apr 2026
Q4 2025-26 Water supply and sewage board11 Apr 2026
Q4 2025-26 KSPCB- PCB (10 Acres to 125 Acres)11 Apr 2026
Q4 2025-26 KPTCL- BESCOM11 Apr 2026
Q4 2025-26 Fire and Safety11 Apr 2026
Q4 2025-26 Airport Authority of India11 Apr 2026
Q3 2025-26 Form-4 Certificate issued by Chartered AccountantFile: RERA CA form 4 dec 2025 Zaiden.pdf13 Jan 2026
Q3 2025-26 Form-5 Certificate issued by ArchitectFile: Architect cert QU3 dec 25 Proj Zaiden.pdf13 Jan 2026
Q3 2025-26 Form-6 Certificate issued by Structural EngineerFile: Engg Proj Zaiden Dec 25 Qtr.pdf13 Jan 2026
Q3 2025-26 Water supply and sewage board13 Jan 2026
Q3 2025-26 KPTCL- BESCOM13 Jan 2026
Q3 2025-26 Fire and Safety13 Jan 2026
Q3 2025-26 Airport Authority of India13 Jan 2026
Grant certificate-originalFile: 1 Grant certificate-original.pdf11 Apr 2023
Sale Deed Doc 9536File: 2 Sale Deed Doc 9536.pdf11 Apr 2023
Firm Name Change CopyFile: 3 Firm Name Change Copy.pdf11 Apr 2023
Clarification on Commencement CertificateFile: 4 Clarification on Commencement Certificate.pdf11 Apr 2023
BBMP Approved PlanFile: 5 BBMP Approved Plan.pdf11 Apr 2023
Form 2 Architect CertificateFile: 6 Form 2 Architect Certificate.pdf11 Apr 2023
Agreement for Sale - Thalagattapura UpdatedFile: 7 Agreement for Sale - Thalagattapura Updated.pdf11 Apr 2023
STP DesignFile: 8 STP Design.pdf11 Apr 2023
BWSSB NOC Clarification with fee paid receiptFile: 9 BWSSB NOC Clarification with fee paid receipt.pdf11 Apr 2023
Form 3 Engineer CertificateFile: 10 Form 3 Engineer Certificate.pdf11 Apr 2023
Cost Estimated BreakupFile: 11 Cost Estimated Breakup.pdf11 Apr 2023
MR no 2 of 57-58File: 12 MR no 2 of 57-58.pdf11 Apr 2023
Architect LicenseFile: 13 Architect License.pdf11 Apr 2023
RTC, survey 1-
Mutation, survey 1-
Encumbrance Certificate, survey 1-
Conversion/Alienation Order, survey 1-
Sale/Title/Gift Deed, survey 1-
Khatha, survey 1-
Registration CertificateFile: Certificate of Incorporation.pdf-
Organization StructureFile: Organization Structure.pdf-
Certificate issued by CA Form 1File: Form 1 CA Certificate.pdf-
Certificate issued by Architect Form 2File: 6 Form 2 Architect Certificate.pdf-
Certificate issued by Engineer Form 3File: 10 Form 3 Engineer Certificate.pdf-
Project Chartered Accountant-
Project Engineer-
Project Architect-
AffidavitFile: Non-Litigation Affidavit.pdf-
Certificate from Chartered AccountFile: Form 1 CA Certificate.pdf-
Balance Sheet 2021 - 2022File: Blalance sheet 2021-22.pdf-

How this compares with Bengaluru Urban

100%of this project is bookeddistrict median 51%
34%of Bengaluru Urban projects moved their completion datethis one moved by 12 months
1%of Bengaluru Urban registrations are shown as withdrawn or revokedthis one is not

Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.

Keep CASAGRAND ZAIDEN on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bengaluru Urban4,100+ in Bengaluru Urban

2 kmCASAGRAND ZAIDENOther 30Dot size: filed unitsN

Filed coordinates, straight-line distance. 30 registered projects within 2 km.

Builder: CASA GRANDE GARDEN CITY BUILDERS PVT LTD

Casa Grande Garden City Builders Pvt ltd has 17 registrations on RERA Karnataka, including Casagrand Florella Phase 2 and CASAGRAND VIVACITY. Its filings declare 12 earlier projects, 3 of them declared completed. Read the full track record. See more projects on the Bengaluru Urban district page.

Frequently asked questions

What are my rights if CASAGRAND ZAIDEN is delayed beyond 22 Mar 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of CASAGRAND ZAIDEN?

The registered promoter entity is CASA GRANDE GARDEN CITY BUILDERS PVT LTD, a company as per the filing. Its CIN U45205KA2015PTC082415 and GSTIN 29AAGCC1577R1ZV can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in CASAGRAND ZAIDEN?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against CASAGRAND ZAIDEN?

Each case number above is a complaint filed with RERA Karnataka. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

Who certifies construction progress at CASAGRAND ZAIDEN?

The professionals named in the filing: Architect: DILIP NADIG; Engineer: Shivaraj G Naik; Chartered Accountant: NARAYANA RAO M. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in CASAGRAND ZAIDEN?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About CASAGRAND ZAIDEN. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save CASAGRAND ZAIDEN to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.