Registration approved Litigation declared Residential/Group Housing project

MAHINDRA EDEN PHASE-1

By MAHINDRA LIFESPACE DEVELOPERS LIMITED

RG-KA-92201 · RERA PRM/KA/RERA/1251/310/PR/300322/004794 · Last updated on RERA Karnataka portal: 11 Apr 2026

Source: official RERA Karnataka filing

Red flags

  • Litigation declared, 1 case
  • 2 complaints at RERA Karnataka

Clear

  • Completion date never moved
  • Separate project account declared
Mar 2027Possession promisedno revision filed
18 of 18Construction stages doneevery applicable stage filed complete
0 of 277Units unsoldnot recorded sold or booked
2Complaints at RERA Karnatakaon this registration
Jump to the 117 documents Report an error

MAHINDRA EDEN PHASE-1 is a Residential/Group Housing project by MAHINDRA LIFESPACE DEVELOPERS LIMITED in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/310/PR/300322/004794 on 30 Mar 2022. Possession is promised by 30 Mar 2027. 277 of the 277 units on this registration are recorded sold or booked, and 18 of 18 construction stages are filed complete. 2 complaints are on record with the regulator.

At a glance

Project

  • NameMAHINDRA EDEN PHASE-1
  • TypeResidential/Group Housing
  • Location
    • Bengaluru South
    • Bengaluru Urban
    • 560062
  • Pincode560062
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PRM/KA/RERA/1251/310/PR/300322/004794
  • ReraGenie IDRG-KA-92201

Builder

  • NameMAHINDRA LIFESPACE DEVELOPERS LIMITED
  • Entity typeCompany
  • CINL45200MH1999PLC118949
  • GSTIN29AAACG8904C1ZR
  • Authorized SignatoryR. Aswath Prasad
  • Managing Director & Chief Executive OfficerARVIND SUBRAMANIAN
  • DirectorsMr. ARUN KUMAR NANDA, Dr. ANISH DILIP SHAH, Mr. AMEET PRATAPSINH HARIANI, Ms. AMRITA VERMA CHOWDHURY, Mr. SUBRAMANIAM DURGASHANKAR, Mr. ARVIND SUBRAMANIAN
  • Project HeadR. Aswath Prasad
  • Other registrations4 more →
  • Declared earlier projects6 →

Key dates

this monthRegisteredMar 2022PromisedMar 2027

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on30 Mar 2022
  • Promised completion30 Mar 2027
  • Revised completionNone
  • Buildings2 building records
  • Documents filed117 files

Current status

100%277 of 277 units booked
0.0%Of the estimated cost spent so far

Figures as on 11 Apr 2026, this project's latest RERA Karnataka filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Wing-A---1070107
Wing-B---1700170

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 11 Apr 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

18 of 18 construction stages are filed complete.

Building: 100% average across the applicable activities

ActivityProgress
Earth work and other leveling preparation work100%
Foundation footing work100%
Upto Plinth Level100%
Sub-structure flooring (Parking Floor, more than one floor below general ground level)100%
Retaining wall (All types)100%
RCC or MS Framed structure100%
Masonry Construction100%
Plastering inside , outside & Ceiling100%
Joinery: Doors, Windows, Ventilators etc100%
Basic work of Water supply, Sanitary and Electrification100%
Dadoing, Skirting, Flooring, Tiles work (All types)100%
Railing and Grill fixing100%
Electrification, Water supply and Sanitary Finishing100%
Painting100%
Fire prevention and fire fighting fitting and fixture with network100%
Weather Proof work(tile,concrete)100%
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Elevation work100%
Internal and External work including landscapes as per sanctioned drawings100%

Progress on shared amenities57

As on 11 Apr 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes100%
Sewage and Drainage SystemYes100%
Water conservation/rain water harvesting/recharge of ground waterYes100%
Energy managementYes100%
Fire protection and fire safety requirementsYes100%
Solid waste management and disposalYes100%
Emergency Evacuation servicesYes100%
Internal Roads & FootpathsYes100%
Electricity supply transformer and substationYes100%
Storm water drainsYes100%
Use of renewable energyYes100%
Sewage Treatment Plant (STP)Yes100%
Parks & Tree plantingYes100%
Street LightingYes100%
ElectricityYes100%
Smart Home AutomationNoNot applicable
CCTV SurveillanceNoNot applicable
Club HouseNoNot applicable
Community HallNoNot applicable
Outdoor Sports facilityNoNot applicable
Indoor Sports facilityNoNot applicable
Swimming PoolNoNot applicable
GymNoNot applicable
ParksNoNot applicable
Power BackupNoNot applicable
Piped GasNoNot applicable
Water and SanitationNoNot applicable
Air ConditioningNoNot applicable
Nebula Lounge (Part of Open Space)Yes100%
Burma Bridge (Part of Open Space)Yes100%
Swinging Cocoons (Part of Open Space)Yes100%
Yoga & Meditation space (Part of Open Space)Yes100%
Contemplation Zone (Part of Open Space)Yes100%
Camping Zone (Part of Open Space)Yes100%
Sand Pit (Part of Open Space - Kids Play Area)Yes100%
Water Lava (Part of Open Space - Kids Play Area)Yes100%
Reflexology Path (Part of Open Space)Yes100%
Nest house (Part of Open Space)Yes100%
Al fresco Gym (Part of Open Space)Yes100%
Net Bridge (Part of Open Space)Yes100%
Pet Park (Part of Open Space)Yes100%
Pergola Sit-out (Part of Open Space)Yes100%
Multipurpose HallYes100%
Guest RoomsYes100%
Indoor Gym with Aerobics zoneYes100%
StaircasesYes100%
LiftsYes100%
Corridor/LobbiesYes100%
Fire escapesYes100%
Common entrance and exit for the building/common portico/foyer/verandahYes100%
BasementYes100%
TerraceYes100%
Outer WallYes100%
Open parking areasNoNot applicable
Provision for lodging of management staff and security staffNoNot applicable
Water conservation and renewable energyNoNot applicable
Common storage spacesNoNot applicable

Land and ownership2

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area12,621 sq m
Named landowners2
LandownerVillageDistrict
Mahindra Lifespace Developers Limited--
Mahindra Lifespace Developers Limited--

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 168.89 cr
Spent of the estimate0.0%
Cost lineEstimatedIncurred
Estimated Cost of Construction as certified by EngineerRs 116.71 cr-
Payment of taxesRs 21.01 cr-
Approval CostRs 10.68 cr-
Manpower CostRs 6.72 cr-
On-site expenditure-Consultants FeesRs 5.41 cr-
Principal sum and interest payable to financial institutions-Non Banking financial institution (NBFC)Rs 5.36 cr-
On-site expenditure-Site OverheadRs 1.50 cr-
On-site expenditure-Cost Of Services(Water, Electricity, Sewage)Rs 1.50 cr-

Certifying professionals and partners4

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectEdifice Consultants Private Limited
EngineerInnotech Engineering Consult Private Limited
EngineerCBRE South Asia Pvt.Ltd.
Chartered AccountantDEVDATTA MAINKAR

Litigation declared1

CaseCourtStatus
8205Hon'ble City Civil and SessionsJudge, Bengaluru City-

Complaints filed with RERA Karnataka2

Case no.ComplainantRespondentFiled
00243/2023-MAHINDRA LIFESPACE DEVELOPERS LIMITED24/02/2023
00258/2023-MAHINDRA LIFESPACE DEVELOPERS LIMITED27/02/2023

Documents filed117

As listed on the registration, under the names the promoter filed them with; the newest 80 of 117 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/310/PR/300322/004794 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Q4 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Form 4 CA Certificate QU March 26.pdf11 Apr 2026
Q4 2025-26 Form-5 Certificate issued by ArchitectFile: Form 5 Architect Certificate QU March 26.pdf11 Apr 2026
Q4 2025-26 Form-6 Certificate issued by Structural EngineerFile: Form 6 Engineer Certificate QU March 26.pdf11 Apr 2026
Q4 2025-26 Water supply and sewage board11 Apr 2026
Q4 2025-26 KSPCB- PCB (10 Acres to 125 Acres)11 Apr 2026
Q4 2025-26 KSPCB- MOEF (Above 50 Acres)11 Apr 2026
Q4 2025-26 KPTCL- BESCOM11 Apr 2026
Q4 2025-26 Fire and Safety11 Apr 2026
Q4 2025-26 Airport Authority of India11 Apr 2026
Q4 2025-26 BSNL/Telecommunication Department11 Apr 2026
Q4 2025-26 Preventive Order (Injunction / Interim Order / Final Order / Stay OrderFile: Affidavit cum Declaration Litigation.pdf11 Apr 2026
Q4 2025-26 Any further orders in this regardFile: Affidavit cum Declaration Litigation.pdf11 Apr 2026
Q3 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Form 4 CA Certificate QU Dec 25.pdf14 Jan 2026
Q3 2025-26 Form-5 Certificate issued by ArchitectFile: Form 5 Architect Certificate QU Dec 25.pdf14 Jan 2026
Q3 2025-26 Form-6 Certificate issued by Structural EngineerFile: Form 5 Architect Certificate QU Dec 25.pdf14 Jan 2026
Q3 2025-26 Water supply and sewage board14 Jan 2026
Q3 2025-26 KSPCB- PCB (10 Acres to 125 Acres)14 Jan 2026
Q3 2025-26 KSPCB- MOEF (Above 50 Acres)14 Jan 2026
Q3 2025-26 KPTCL- BESCOM14 Jan 2026
Q3 2025-26 Fire and Safety14 Jan 2026
Q3 2025-26 Airport Authority of India14 Jan 2026
Q3 2025-26 BSNL/Telecommunication Department14 Jan 2026
Q3 2025-26 Preventive Order (Injunction / Interim Order / Final Order / Stay OrderFile: Affidavit cum Declaration Litigation.pdf14 Jan 2026
Q3 2025-26 Any further orders in this regardFile: Affidavit cum Declaration Litigation.pdf14 Jan 2026
BBMP BUILDING LICENSEFile: BBMP BUILDING LICENSE.pdf22 Mar 2022
BBMP SITE PLAN STP RWHFile: 1 BBMP SITE PLAN STP RWH.pdf22 Mar 2022
BBMP LOWER BASEMENT FLOOR PLANFile: 2 BBMP LOWER BASEMENT FLOOR PLAN.pdf22 Mar 2022
BBMP UPPER BASEMENT FLOOR PLANFile: 3 BBMP UPPER BASEMENT FLOOR PLAN.pdf22 Mar 2022
BBMP GROUND FLOOR PLANFile: 4 BBMP GROUND FLOOR PLAN.pdf22 Mar 2022
BBMP WING A GF 26F TERRACE SECTNFile: 5 BBMP WING A GF 26F TERRACE SECTN.pdf22 Mar 2022
BBMP WING B GF 28F TERRACE SECTNFile: 6 BBMP WING B GF 28F TERRACE SECTN.pdf22 Mar 2022
BBMP COMBINED SECTION WING A BFile: 9 BBMP COMBINED SECTION WING A B.pdf22 Mar 2022
BBMP COMBINED ELEVATION WING A BFile: 11 BBMP COMBINED ELEVATION WING A B.pdf22 Mar 2022
AGREEMENT FOR SALEFile: AGREEMENT FOR SALE.pdf22 Mar 2022
Project SpecificationsFile: Project Specifications.pdf22 Mar 2022
Affidavit Non Violation of Section 3 OriginalFile: Affidavit Non Violation of Section 3 Original.pdf22 Mar 2022
Development DetailsFile: Development Details.pdf22 Mar 2022
DECLARATIONFile: DECLARATION.pdf22 Mar 2022
Previous Project DetailsFile: 1 Previous Project Details.pdf14 Feb 2022
Form 1 CERTFile: 2 Form 1 CERT.pdf14 Feb 2022
Khata CertificateFile: 3 Khata Certificate.pdf14 Feb 2022
Gift DeedFile: 4 Gift Deed.pdf14 Feb 2022
Form B Company ApartmentFile: 5 Form B Company Apartment.pdf14 Feb 2022
BDA DP Approved PlanFile: 6 BDA DP Approved Plan.pdf14 Feb 2022
Affidavit MortgageFile: 7 Affidavit Mortgage.pdf14 Feb 2022
RTC, survey 49-
Mutation, survey 49-
Encumbrance Certificate, survey 49-
Conversion/Alienation Order, survey 49-
Sale/Title/Gift Deed, survey 49-
Khatha, survey 49-
RTC, survey 50/2-
Mutation, survey 50/2-
Encumbrance Certificate, survey 50/2-
Conversion/Alienation Order, survey 50/2-
Sale/Title/Gift Deed, survey 50/2-
Khatha, survey 50/2-
Registration CertificateFile: Company Registration Certificate.pdf-
Organization StructureFile: 11 Mahindra Eden Org Design.pdf-
Certificate issued by CA Form 1File: Form 1 CERT.pdf-
Certificate issued by Architect Form 2File: Form 2 ARCH CERT.pdf-
Certificate issued by Engineer Form 3File: Form 3 ENG CERT.pdf-
Project Chartered Accountant-
Project Engineer-
Project Engineer-
Project Architect-
AffidavitFile: Affidavit for Non Litigation.pdf-
Certificate from Chartered AccountFile: 56 Form 1 CERT.pdf-
Balance Sheet 2020 - 2021File: Balance sheet FY 20 21.pdf-
Balance Sheet 2019 - 2020File: Balance sheet FY 19 20.pdf-
Balance Sheet 2018 - 2019File: Balance sheet FY 18 19.pdf-
Audited Profit and Loss Statement 2020 - 2021File: Profit and loss FY 20 21.pdf-
Audited Profit and Loss Statement 2019 - 2020File: Profit and loss FY 19 20.pdf-
Audited Profit and Loss Statement 2018 - 2019File: Profit and loss FY 18 19.pdf-
Director's Report 2020 - 2021File: Directors report FY 20 21.pdf-
Director's Report 2019 - 2020File: Directors report FY 19 20.pdf-
Director's Report 2018 - 2019File: Director report FY 18 19.pdf-
Cash Flow Statement 2020 - 2021File: Cash flow FY 20 21.pdf-
Cash Flow Statement 2019 - 2020File: Cash flow FY 19 20.pdf-
Auditor's Report 2020 - 2021File: 60 Annual Report 2020 21 MLDL.pdf-

How this compares with Bengaluru Urban

100%of this project is bookeddistrict median 51%
34%of Bengaluru Urban projects moved their completion datethis one has not
1%of Bengaluru Urban registrations are shown as withdrawn or revokedthis one is not

Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.

Keep MAHINDRA EDEN PHASE-1 on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bengaluru Urban4,100+ in Bengaluru Urban

2 kmMAHINDRA EDEN PHASE-1Other 46Dot size: filed unitsN

Filed coordinates, straight-line distance. 46 registered projects within 2 km.

Builder: MAHINDRA LIFESPACE DEVELOPERS LIMITED

MAHINDRA LIFESPACE DEVELOPERS LIMITED has 5 registrations on RERA Karnataka, including MAHINDRA EDEN PHASE-2 and MAHINDRA NEWHAVEN. Its filings declare 6 earlier projects, none of them declared completed. Litigation is declared on 2 of its registrations. Read the full track record. See more projects on the Bengaluru Urban district page.

Frequently asked questions

What are my rights if MAHINDRA EDEN PHASE-1 is delayed beyond 30 Mar 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of MAHINDRA EDEN PHASE-1?

The registered promoter entity is MAHINDRA LIFESPACE DEVELOPERS LIMITED, a company as per the filing. Its CIN L45200MH1999PLC118949 and GSTIN 29AAACG8904C1ZR can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in MAHINDRA EDEN PHASE-1?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against MAHINDRA EDEN PHASE-1?

Each case number above is a complaint filed with RERA Karnataka. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

Who certifies construction progress at MAHINDRA EDEN PHASE-1?

The professionals named in the filing: Architect: Edifice Consultants Private Limited; Engineer: Innotech Engineering Consult Private Limited; Engineer: CBRE South Asia Pvt.Ltd.; Chartered Accountant: DEVDATTA MAINKAR. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in MAHINDRA EDEN PHASE-1?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; how the declared litigation on this registration affects your risk; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About MAHINDRA EDEN PHASE-1. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save MAHINDRA EDEN PHASE-1 to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.