Home / Browse projects / Bengaluru Urban, Karnataka / URBAN SERENITY -I

Registration approved No litigation declared Residential/Group Housing project

URBAN SERENITY -I

By P K CHANDRASHEKAR

RG-KA-71907 · RERA PRM/KA/RERA/1251/308/PR/200526/003412 · Last updated on RERA Karnataka portal: 15 Oct 2026

Source: official RERA Karnataka filing

Red flags

  • Completion date moved by 9 months
  • 1 extension taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
Sep 2026Possession promisedmoved 9 months from the original
8 of 8Construction stages doneevery applicable stage filed complete
2 of 47Units unsoldnot recorded sold or booked
0Complaints at RERA Karnatakaon this registration
Jump to the 77 documents Report an error

URBAN SERENITY -I is a Residential/Group Housing project by P K CHANDRASHEKAR in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/308/PR/200526/003412 on 26 May 2020. Possession is promised by 30 Sep 2026. The completion date has moved by 9 months from the original filing. 45 of the 47 units on this registration are recorded sold or booked, and 8 of 8 construction stages are filed complete.

At a glance

Project

  • NameURBAN SERENITY -I
  • TypeResidential/Group Housing
  • Location
    • Anekal
    • Bengaluru Urban
  • PincodeNot stated
  • RERA no.PRM/KA/RERA/1251/308/PR/200526/003412
  • ReraGenie IDRG-KA-71907

Builder

  • NameP K CHANDRASHEKAR

Key dates

this monthRegisteredMay 2020First promiseDec 2025Revised toSep 2026

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on26 May 2020
  • Promised completion30 Sep 2026
  • Revised completionRevised to 30 Sep 2026 (originally 31 Dec 2025)
  • Buildings1 building record
  • Documents filed77 files

Current status

96%45 of 47 units booked
71.7%Of the estimated cost spent so far

Figures as on 15 Oct 2026, this project's latest RERA Karnataka filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
URBAN SERENITY---47047

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 15 Oct 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

8 of 8 construction stages are filed complete.

Building: 100% average across the applicable activities

ActivityProgress
Earth work and other leveling preparation work100%
Foundation footing work100%
Retaining wall (All types)Not applicable
Plinth level Beam100%
Sub-structure flooring (Parking Floor, more than one floor below general ground level)Not applicable
RCC or MS Framed structure100%
Masonry construction: Bricks, Concrete blocks etc100%
Plastering inside , outside & Ceiling100%
Joinery: Doors, Windows, Ventilators etc100%
Basic work of Water supply, Sanitary and ElectrificationNot applicable
Dadoing, Skirting, Flooring, Tiles work (All types)Not applicable
Railing and Grill fixingNot applicable
Electrification, Water supply and Sanitary Finishing100%
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Fire prevention and fire fighting fitting and fixture with networkNot applicable
Weather Proof work(tile,concrete)Not applicable
PaintingNot applicable
Elevation workNot applicable
Internal and External work including landscapes as per santioned drawingsNot applicable

Progress on shared amenities41

As on 15 Oct 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes100%
Internal Roads & FootpathsNoNot applicable
Sewage and Drainage SystemNoNot applicable
Parks & Tree plantingNoNot applicable
Street LightingNoNot applicable
Provision for community buildings and for treatment and disposal of sewage and sullage waterYes100%
Solid waste management and disposalYes100%
Water conservationNoNot applicable
Energy managementNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Education/Health/Other public amenitiesNoNot applicable
Electricity supply transformer and substationYes100%
Emergency Evacuation servicesNoNot applicable
Storm water drainsYes100%
Use of renewable energyNoNot applicable
Water conservation/rain water harvesting/recharge of ground waterYes100%
ElectricityYes100%
Smart Home AutomationNoNot applicable
CCTV SurveillanceYes100%
Club HouseYes100%
Community HallYes100%
Outdoor Sports facilityYes100%
Indoor Sports facilityYes100%
Swimming PoolNoNot applicable
GymYes100%
ParksYes100%
Power BackupNoNot applicable
GasNoNot applicable
Water and SanitationYes100%
Air Conditioning And incerntionNoNot applicable
StaircasesYes100%
LiftsNoNot applicable
Staircases and Lift lobbies, corridor,lobbies, corridorNoNot applicable
Fire escapesNoNot applicable
Common entrance and exit for the building / common portico/foyer/verandahNoNot applicable
BasementNoNot applicable
TerraceYes100%
Outer WallYes100%
Open parking areas and common storage spacesYes100%
Provision for lodging of management staff and security staffYes100%
Water conservation and renewable energyNoNot applicable

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area9,712 sq m
Named landownersNone

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 21.69 cr
Cost incurredRs 15.55 cr
Spent of the estimate71.68%
Cost lineEstimatedIncurred
On-site expenditure-Site OverheadRs 9.06 crRs 8.04 cr
Principal sum and interest payable to financial institutions-Non Banking financial institution (NBFC)Rs 5.25 cr-
On-site expenditure-Salaries of workersRs 3.57 crRs 3.57 cr
Payment of taxesRs 2.15 crRs 2.26 cr
On-site expenditure-Cost Of Services(Water, Electricity, Sewage)Rs 60.00 lakhRs 60.00 lakh
On-site expenditure-Consultants FeesRs 55.48 lakhRs 55.48 lakh
Estimated Cost of Construction as certified by EngineerRs 43.39 lakhRs 43.39 lakh
Payment of cessRs 8.70 lakhRs 8.70 lakh

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectJamuna Chalam
EngineerK. Venkatesh Babu Reddy M.E.(Str)

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

ExtensionDec 2025 → Sep 2026

No reason recorded in the filing

Complaints filed with RERA Karnataka

No complaints on record against this registration.

Documents filed77

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/308/PR/200526/003412 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Q1 2026-27 Form-4 Certificate issued by Chartered AccountantFile: Q1FY2026-27US-1CA.pdf15 Oct 2026
Q1 2026-27 Form-5 Certificate issued by ArchitectFile: Q1FY2026-27US-1Vernekar .pdf15 Oct 2026
Q1 2026-27 Form-6 Certificate issued by Structural EngineerFile: Q1FY2026-27US-1EngineersForm-6.pdf15 Oct 2026
Q1 2026-27 Registration documentFile: USRWA Registration Certificate (1).pdf15 Oct 2026
Q2 2026-27 Form-4 Certificate issued by Chartered AccountantFile: Q2FY202627US1F4.pdf15 Oct 2026
Q2 2026-27 Form-5 Certificate issued by ArchitectFile: Q2FY202627US1F6.pdf15 Oct 2026
Q2 2026-27 Form-6 Certificate issued by Structural EngineerFile: Q2FY202627US1F5.pdf15 Oct 2026
Q2 2026-27 Registration documentFile: USRWA Registration Certificate (1).pdf15 Oct 2026
Q4 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Form-4 CA Q4 FY 2025-26.pdf17 Jul 2026
Q4 2025-26 Form-5 Certificate issued by ArchitectFile: URBAN SERENITY RERA.pdf17 Jul 2026
Q4 2025-26 Form-6 Certificate issued by Structural EngineerFile: Q4 FY 2025-26 US-1 Engineers Form-6.pdf17 Jul 2026
Q4 2025-26 Registration documentFile: USRWA Registration Certificate (1).pdf17 Jul 2026
Q3 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Q3 FY 2025-26 US-1 CA Form-4_compressed.pdf31 Mar 2026
Q3 2025-26 Form-5 Certificate issued by ArchitectFile: Q3 FY 2025-26 US-1 Architect Form-5.pdf31 Mar 2026
Q3 2025-26 Form-6 Certificate issued by Structural EngineerFile: Q3 FY 2025-26 US-1 Engineers Form-6.pdf31 Mar 2026
Q3 2025-26 Registration documentFile: USRWA Registration Certificate (1).pdf31 Mar 2026
AREA SUMMARY ATTACHEDFile: AREA SUMMARY.pdf23 May 2020
Joint Affidavit cum Declaration land owner is uploadedFile: Landowner.pdf17 Mar 2020
Treasury receiptFile: EKhajaneChallanForm17-03-2020.pdf17 Mar 2020
Balance Sheet 18-19File: Balance Sheet 18-19.pdf3 Mar 2020
Bank StatementFile: NIFT Bank Statement.pdf3 Mar 2020
P & L Account 18-19File: P & L 18-19.pdf3 Mar 2020
Affidivate cum DeclarationFile: AFF CUM DECLARATION.pdf3 Mar 2020
2017 ITR WITH SELF ATTESTATIONFile: ITR 17 6.pdf25 Feb 2020
2018 ITR WITH SELF ATTESTATIONFile: ITR 18 6.pdf25 Feb 2020
2019 ITR WITH SELF ATTESTATIONFile: ITR 19 6.pdf25 Feb 2020
2017 P & L WITH SELF ATTESTATIONFile: P & L 17 2.pdf25 Feb 2020
2018 P & L WITH SELF ATTESTATIONFile: P & L 18 2.pdf25 Feb 2020
2019 P & L WITH SELF ATTESTATIONFile: P & L 19 2.pdf25 Feb 2020
2017 BALANCE SHEET SELF ATTESTATIONFile: BAL SHEET 17 1.pdf25 Feb 2020
2018 BALANCE SHEET SELF ATTESTATIONFile: BAL SHEET 18 1.pdf25 Feb 2020
2019 BALANCE SHEET SELF ATTESTATIONFile: 19-1 BS.pdf25 Feb 2020
LOCAL PANCHYAT WATER NOCFile: Muguler Panchayat.pdf25 Feb 2020
BESCOM NOCFile: Bescom Serenity.pdf25 Feb 2020
VILLAMENT/ROWHOUSE/APARTMENT 1ST FLOOR SANCTION PLAN COPYFile: Villament 1st Floor Plan.pdf25 Feb 2020
VILLAMENT/ROWHOUSE/APARTMENT 2ND FLOOR SANCTION PLAN COPYFile: Villament 2nd Floor Plan.pdf25 Feb 2020
VILLAMENT/ROWHOUSE/APARTMENT GROUND FLOOR SANCTION PLAN COPYFile: Villament Ground Floor Plan.pdf25 Feb 2020
VILLAMENT/ROWHOUSE/APARTMENT SECTION & ELEVATION SANCTION PLAN COPYFile: Villament Section & Elevation.pdf25 Feb 2020
VILLAMENT/ROWHOUSE/APARTMENT SITE LAYOUT SANCTION PLAN COPYFile: Villament Site Layout Plan.pdf25 Feb 2020
VILLAMENT/ROWHOUSE/APARTMENT TERRACE SANCTION PLAN COPYFile: Villament Terrace Plan.pdf25 Feb 2020
FORM B WITH NOTARYFile: F B W NOT.pdf25 Feb 2020
AFFIDAVITE CUM DECLARATION OLD COPY LAND OWNER IS OUT OF STATION WE REQUIRED FEW DAYS TO UPLOADFile: AFF CUM DECLARATION.pdf25 Feb 2020
CC serenity-
Villament Site Layout Plan_compressed_compressed-
Villament Site Layout Plan_compressed_compressed-
Sale Deed-
Sale Agr Villament_compressed-compressed_compressed (1)-
sale deed mentor-
Compress_70% Letter of Allotment-
Brochure- Urban Serenity-
specificaion of villa-
EC 118-
Affidavit 1-
AFF CUM DECLARATION-
SY NO 118 KATHA-
Villament JDA-
conversion order-
URBAN SERENITY PCB_compressed-
Unnamed document-
Balance Sheet 2018 - 2019File: Ba -19-1.pdf-
Balance Sheet 2017 - 2018File: Ba -18-1.pdf-
Balance Sheet 2016 - 2017File: Ba -17-1.pdf-
Audited Profit and Loss Statement 2018 - 2019File: p & l 19-2.pdf-
Audited Profit and Loss Statement 2017 - 2018File: p & l 18-2.pdf-
Audited Profit and Loss Statement 2016 - 2017File: p & l 17-2.pdf-
Cash Flow Statement 2018 - 2019File: Cashflow 19-4.pdf-
Cash Flow Statement 2017 - 2018File: Cashflow 18-4.pdf-
Auditor's Report 2018 - 2019File: auditor-19-5_compressed (1).pdf-
Auditor's Report 2017 - 2018File: auditor-18-5_compressed.pdf-
Auditor's Report 2016 - 2017File: auditor-17-5_compressed (1).pdf-
Income Tax Return Acknowledgement 2018 - 2019File: itr -ack- 19-6.pdf-
Income Tax Return Acknowledgement 2017 - 2018File: itr -ack -18-6.pdf-
Income Tax Return Acknowledgement 2016 - 2017File: itr ack -17-6.pdf-
AF CUM DECL-
Prospectus/BrochureFile: Brochure_compressed.pdf-
Advertisement Copy 1File: Advertisement Copy.jpg-
Tower Excel SheetFile: PRMKARERA1251308PR200526003412 (4).xlsx-

How this compares with Bengaluru Urban

96%of this project is bookeddistrict median 51%
34%of Bengaluru Urban projects moved their completion datethis one moved by 9 months
1%of Bengaluru Urban registrations are shown as withdrawn or revokedthis one is not

Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.

Keep URBAN SERENITY -I on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bengaluru Urban4,100+ in Bengaluru Urban

Builder: P K CHANDRASHEKAR

P K CHANDRASHEKAR has 1 registration on RERA Karnataka, including URBAN SERENITY -I. Its filings disclose no earlier RERA Karnataka projects. Read the full track record. See more projects on the Bengaluru Urban district page.

Frequently asked questions

What are my rights if URBAN SERENITY -I is delayed beyond 30 Sep 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of URBAN SERENITY -I?

The registered promoter entity is P K CHANDRASHEKAR. Neither this filing nor this promoter's other RERA Karnataka registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in URBAN SERENITY -I?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at URBAN SERENITY -I?

The professionals named in the filing: Architect: Jamuna Chalam; Engineer: K. Venkatesh Babu Reddy M.E.(Str). Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in URBAN SERENITY -I?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About URBAN SERENITY -I. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save URBAN SERENITY -I to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.