ReraGenieLog inGet a buyer report

Home / Browse projects / Bengaluru Urban, Karnataka / URBAN SERENITY

Registration approved Residential/Group Housing project

URBAN SERENITY

By INNER URBAN INFRAESTATE PVT LTD

RG-KA-08028 · RERA PRM/KA/RERA/1251/308/PR/171102/001592

Source: official RERA Karnataka filing

Red flags

  • 7 complaints at RERA Karnataka
  • Completion date moved by 12 months
  • 2 extensions taken

Clear

  • Separate project account declared
Dec 2020Possession promisedmoved 12 months from the original
7Complaints at RERA Karnatakaon this registration
Jump to the 60 documents Report an error

URBAN SERENITY is a Residential/Group Housing project by INNER URBAN INFRAESTATE PVT LTD in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/308/PR/171102/001592 on 2 Nov 2017. Possession is promised by 31 Dec 2020. The completion date has moved by 12 months from the original filing. 7 complaints are on record with the regulator.

At a glance

Project

  • NameURBAN SERENITY
  • TypeResidential/Group Housing
  • Location
    • Anekal
    • Bengaluru Urban
  • PincodeNot stated
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PRM/KA/RERA/1251/308/PR/171102/001592
  • ReraGenie IDRG-KA-08028

Builder

  • NameINNER URBAN INFRAESTATE PVT LTD
  • Entity typeCompany
  • CINU70102KA2011PTC058984
  • Authorized SignatoryP K CHANDRASHEKAR
  • DirectorP K CHANDRASHEKAR AND C BABU REDDY
  • Declared earlier projects1 →

Key dates

this monthRegisteredNov 2017First promiseDec 2019Revised toDec 2020

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on2 Nov 2017
  • Promised completion31 Dec 2020
  • Revised completionRevised to 31 Dec 2020 (originally 31 Dec 2019)
  • Buildings107 building records
  • Documents filed60 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
1---101
2---101
3---101
4---101
5---101
6---101
7---101
8---101
9---101
10---101
11---101
12---101
13---101
14---101
15---101
16---101
17---101
18---101
19---101
20---101
21---101
22---101
23---101
24---101
25---101
26---101
27---101
28---101
29---101
30---101
31---101
32---101
33---101
34---101
35---101
36---101
37---101
38---101
39---101
40---101
41---101
42---101
43---101
44---101
45---101
46---101
47---101
48---101
49---101
50---101
51---101
52---101
53---101
54---101
55---101
56---101
57---101
58---101
59---101
60---101
61---101
62---101
63---101
64---101
65---101
66---101
67---101
68---101
69---101
70---101
71---101
72---101
73---101
74---101
75---101
76---101
77---101
78---101
79---101
80---101
81---101
82---101
83---101
84---101
85---101
86---101
87---101
88---101
89---101
90---101
91---101
92---101
93---101
94---101
95---101
96---101
97---101
98---101
99---101
100---101
101---101
102---101
103---101
104---101
105---101
106---101
107---101

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

Building:

ActivityProgress
Earth work and other leveling preparation work-
Foundation footing work-
Retaining wall (All types)Not applicable
Plinth level Beam-
Sub-structure flooring (Parking Floor, more than one floor below general ground level)Not applicable
RCC or MS Framed structure-
Masonry construction: Bricks, Concrete blocks etc-
Plastering inside , outside & Ceiling-
Joinery: Doors, Windows, Ventilators etc-
Basic work of Water supply, Sanitary and Electrification-
Dadoing, Skirting, Flooring, Tiles work (All types)-
Railing and Grill fixing-
Electrification, Water supply and Sanitary Finishing-
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Fire prevention and fire fighting fitting and fixture with networkNot applicable
Weather Proof work(tile,concrete)-
Painting-
Elevation workNot applicable
Internal and External work including landscapes as per santioned drawings-

Progress on shared amenities41

Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes-
Internal Roads & FootpathsNoNot applicable
Sewage and Drainage SystemYes-
Parks & Tree plantingYes-
Street LightingNoNot applicable
Provision for community buildings and for treatment and disposal of sewage and sullage waterYes-
Solid waste management and disposalYes-
Water conservationYes-
Energy managementNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Education/Health/Other public amenitiesNoNot applicable
Electricity supply transformer and substationYes-
Emergency Evacuation servicesNoNot applicable
Storm water drainsYes-
Use of renewable energyNoNot applicable
Water conservation/rain water harvesting/recharge of ground waterYes-
ElectricityYes-
Smart Home AutomationNoNot applicable
CCTV SurveillanceYes-
Club HouseYes-
Community HallYes-
Outdoor Sports facilityYes-
Indoor Sports facilityYes-
Swimming PoolYes-
GymYes-
ParksYes-
Power BackupYes-
GasNoNot applicable
Water and SanitationYes-
Air Conditioning And incerntionNoNot applicable
StaircasesYes-
LiftsNoNot applicable
Staircases and Lift lobbies, corridor,lobbies, corridorNoNot applicable
Fire escapesNoNot applicable
Common entrance and exit for the building / common portico/foyer/verandahNoNot applicable
BasementNoNot applicable
TerraceYes-
Outer WallYes-
Open parking areas and common storage spacesNoNot applicable
Provision for lodging of management staff and security staffYes-
Water conservation and renewable energyYes-

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area29,440 sq m
Named landownersNone

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 60.00 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectJamuna Chalam
EngineerARUN RAO

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

ExtensionDec 2019 → Jun 2021

No reason recorded in the filing

EX/PRM/KA/RERA/1251/308/PR/200522/001592Jun 2021 → Dec 2020

Reason as filed by the promoterothers

Complaints filed with RERA Karnataka7

Case no.ComplainantRespondentFiled
CMP/210523/0007956-INNER URBAN INFRAESTATE PVT LTD23/05/2021
CMP/211126/0008634-INNER URBAN INFRAESTATE PVT LTD26/11/2021
CMP/211126/0008635-INNER URBAN INFRAESTATE PVT LTD26/11/2021
CMP/211126/0008636-INNER URBAN INFRAESTATE PVT LTD26/11/2021
CMP/220203/0008935-INNER URBAN INFRAESTATE PVT LTD03/02/2022
CMP/220203/0008936-INNER URBAN INFRAESTATE PVT LTD03/02/2022
CMP/220203/0008940-INNER URBAN INFRAESTATE PVT LTD03/02/2022

Documents filed60

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/308/PR/171102/001592 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
CertificateFile: certificate of incorportion inner.pdf-
Architect Certificate for Work Completion Schedule till DateFile: work completed.pdf-
Engineer Certificate for Work Completion Schedule till DateFile: ST C.pdf-
CA Certificate for Funds UtilizationFile: UDIN FUNDS UTILIZ .pdf-
Architect Certificate for Pending Work Completion Schedule.File: Work pending.pdf-
Engineer Certificate for Pending Work Completion Schedule.File: ST _ P.pdf-
CA Certificate for Funds required for Project CompletionFile: UDIN FUNDS REQ.pdf-
AffidavitFile: AF.pdf-
Latest Encumbrance CertificateFile: US EC.pdf-
Consent letter from 2/3rd of AllotteesFile: CC.pdf-
Details Of Sold/ Un-sold UnitsFile: SoldUnsoldDetails.xlsx-
Document 1File: CC serenity.pdf-
Document 2File: 1st release Letter.pdf-
Document 3File: S0T1000055_2001271732000_compressed.pdf-
Document 4File: Consent w Aff.pdf-
Document 5File: Consent Letter.pdf-
Document 6File: COMP AFFI.pdf-
Document 7File: Comp Letter.pdf-
Document 8File: BMRD RELEASE ORDER.pdf-
Document 9File: 2nd RELEASE LETTER STRR.pdf-
Document 10File: 3rd BMRDA Release Letter.pdf-
Document 11File: rera eXTENSION affi.pdf-
Document 12File: CONSENT LETTER.pdf-
Document 13File: Compensation Affidivat.pdf-
Document 14File: Udin Sheet.pdf-
certificate of incorportion inner-
Serenity Layout Plan-
Serenity Layout Plan-
Sale Deed for U-S-
Sale Agreement-
Sale Deed Mentor-
Letter of Alotment-
Brochure- Urban Serenity-
specificaion of villa-
EC-
Serenity Khata 2222-3-
JD-
CONVERSION COPY SERENITY-
Muguler Panchayat-
Unnamed document-
Balance Sheet 2015 - 2016File: BALANCE SHEET 15-16.pdf-
Balance Sheet 2014 - 2015File: BALANCE SHEET 14-15.pdf-
Balance Sheet 2013 - 2014File: Balance Sheet 13-14.pdf-
Audited Profit and Loss Statement 2015 - 2016File: P & L SHEET 15-16.pdf-
Audited Profit and Loss Statement 2014 - 2015File: P & L SHEET 14-15.pdf-
Audited Profit and Loss Statement 2013 - 2014File: P & L SHEET 13-14.pdf-
Auditor's Report 2015 - 2016File: Audit Report_2015-16.pdf-
Auditor's Report 2014 - 2015File: Audit Report_2014-15.pdf-
Auditor's Report 2013 - 2014File: AUDITOR REPORT 13-14.pdf-
Income Tax Return Acknowledgement 2015 - 2016File: ITR 15-16.pdf-
Income Tax Return Acknowledgement 2014 - 2015File: ITR 14-15.pdf-
Income Tax Return Acknowledgement 2013 - 2014File: ITR 13-14.pdf-
affidvit of director-
Prospectus/BrochureFile: Brochure- Urban Serenity.pdf-
Advertisement Copy 1File: AD.pdf-
Tower Excel SheetFile: PRM_KA_RERA_1251_308_PR_171102_001592.xlsx-
Occupancy CertificateFile: 3rd BMRDA Release Letter.pdf-
Completion certificateFile: 3rd BMRDA Release Letter.pdf-
Registered Agreement of SaleFile: 36 Sale Agreement.pdf-
Registered conveyance deed for an individual unitFile: Villa No 36 Sale Deed Copy.pdf-

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 declared completed, no finish date filed
ProjectLocationStatusPromisedDelivered
URBAN GREENS-CompletedAug 2017No date filed

How this compares with Bengaluru Urban

34%of Bengaluru Urban projects moved their completion datethis one moved by 12 months
1%of Bengaluru Urban registrations are shown as withdrawn or revokedthis one is not

Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.

Keep URBAN SERENITY on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bengaluru Urban4,100+ in Bengaluru Urban

2 kmURBAN SERENITYOther 19Dot size: filed unitsN

Filed coordinates, straight-line distance. 19 registered projects within 2 km.

Builder: INNER URBAN INFRAESTATE PVT LTD

INNER URBAN INFRAESTATE PVT LTD has 1 registration on RERA Karnataka, including URBAN SERENITY. Its filings declare 1 earlier project, 1 of them declared completed. Read the full track record. See more projects on the Bengaluru Urban district page.

Frequently asked questions

What are my rights if URBAN SERENITY is delayed beyond 31 Dec 2020?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of URBAN SERENITY?

The registered promoter entity is INNER URBAN INFRAESTATE PVT LTD, a company as per the filing. Its CIN U70102KA2011PTC058984 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in URBAN SERENITY?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against URBAN SERENITY?

Each case number above is a complaint filed with RERA Karnataka. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

Who certifies construction progress at URBAN SERENITY?

The professionals named in the filing: Architect: Jamuna Chalam; Engineer: ARUN RAO. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in URBAN SERENITY?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About URBAN SERENITY. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save URBAN SERENITY to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.