ReraGenieLog inGet a buyer report

Home / Browse projects / Bengaluru Urban, Karnataka / UNITED SAI ARCADE

Registration approved Residential/Group Housing project

UNITED SAI ARCADE

By UNITED PROJECTS

RG-KA-84804 · RERA PRM/KA/RERA/1251/446/PR/180521/001790

Source: official RERA Karnataka filing

Red flags

  • Completion date moved by 6 months
  • 1 extension taken

Clear

  • No complaints on record
  • Separate project account declared
Sep 2021Possession promisedmoved 6 months from the original
0Complaints at RERA Karnatakaon this registration
Jump to the 43 documents Report an error

UNITED SAI ARCADE is a Residential/Group Housing project by UNITED PROJECTS in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/446/PR/180521/001790 on 21 May 2018. Possession is promised by 30 Sep 2021. The completion date has moved by 6 months from the original filing.

At a glance

Project

  • NameUNITED SAI ARCADE
  • TypeResidential/Group Housing
  • Location
    • Bengaluru East
    • Bengaluru Urban
  • PincodeNot stated
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PRM/KA/RERA/1251/446/PR/180521/001790
  • ReraGenie IDRG-KA-84804

Builder

  • NameUNITED PROJECTS
  • Entity typePartnership Firm
  • Authorized SignatoryR GANGADHARA
  • Other registrations3 more →
  • Declared earlier projects1 →

Key dates

this monthRegisteredMay 2018First promiseMar 2021Revised toSep 2021

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on21 May 2018
  • Promised completion30 Sep 2021
  • Revised completionRevised to 30 Sep 2021 (originally 31 Mar 2021)
  • Buildings1 building record
  • Documents filed43 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Block A---1650165

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

Building:

ActivityProgress
Earth work and other leveling preparation work-
Foundation footing work-
Retaining wall (All types)-
Plinth level BeamNot applicable
Sub-structure flooring (Parking Floor, more than one floor below general ground level)Not applicable
RCC or MS Framed structure-
Masonry construction: Bricks, Concrete blocks etc-
Plastering inside , outside & Ceiling-
Joinery: Doors, Windows, Ventilators etc-
Basic work of Water supply, Sanitary and Electrification-
Dadoing, Skirting, Flooring, Tiles work (All types)-
Railing and Grill fixing-
Electrification, Water supply and Sanitary Finishing-
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Fire prevention and fire fighting fitting and fixture with networkNot applicable
Weather Proof work(tile,concrete)-
Painting-
Elevation work-
Internal and External work including landscapes as per santioned drawings-

Progress on shared amenities41

Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes-
Internal Roads & FootpathsNoNot applicable
Sewage and Drainage SystemYes-
Parks & Tree plantingNoNot applicable
Street LightingNoNot applicable
Provision for community buildings and for treatment and disposal of sewage and sullage waterNoNot applicable
Solid waste management and disposalYes-
Water conservationNoNot applicable
Energy managementNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Education/Health/Other public amenitiesYes-
Electricity supply transformer and substationYes-
Emergency Evacuation servicesNoNot applicable
Storm water drainsNoNot applicable
Use of renewable energyNoNot applicable
Water conservation/rain water harvesting/recharge of ground waterYes-
ElectricityYes-
Smart Home AutomationNoNot applicable
CCTV SurveillanceNoNot applicable
Club HouseYes-
Community HallNoNot applicable
Outdoor Sports facilityNoNot applicable
Indoor Sports facilityNoNot applicable
Swimming PoolYes-
GymYes-
ParksNoNot applicable
Power BackupYes-
GasNoNot applicable
Water and SanitationYes-
Air Conditioning And incerntionNoNot applicable
StaircasesYes-
LiftsYes-
Staircases and Lift lobbies, corridor,lobbies, corridorYes-
Fire escapesNoNot applicable
Common entrance and exit for the building / common portico/foyer/verandahYes-
BasementYes-
TerraceYes-
Outer WallYes-
Open parking areas and common storage spacesYes-
Provision for lodging of management staff and security staffNoNot applicable
Water conservation and renewable energyNoNot applicable

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area8,498 sq m
Named landownersNone

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 45.30 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectV SIVA KUMAR
EngineerSRINIVAS RAO BOLIMUNTA

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

ExtensionMar 2021 → Sep 2021

No reason recorded in the filing

Complaints filed with RERA Karnataka

No complaints on record against this registration.

Documents filed43

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/446/PR/180521/001790 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
CertificateFile: Firm Registration Certificate.PDF-
8a Encambrance Certificate-
10 BDA Licence 95-1-
MYSCAN_20180504_0001-
18 proforma of saledeed-
12 performa of agreement of sale-
13 Saledeed and RTC-
MYSCAN_20180504_0001-ilovepdf-compressed-
15 Area development plan-
16 Performa of allotment letter-
17 Broucher of current project-
19 Project specifications-
8 Encambrance Certificate-
22 E Katha -
20 Joint Development Agreement -
23 General Power of Attorney-
25 Conversion Order-min-
26 NOC KTCP-
48 Utilization certificate-
49 Transfer of development rights certificate-
27 Fire force Dep NOC-
33 BSNL NOC dt -
46 NOC of building abutting to neighbouring-
39 Urban land ceiling NOC-
38 BMRCL NOC-
41 Bangalore urban arts commission-
42 Inspector of factories-
43 District Magistrate-
44 Costal regulation zone authority-
45 Certificate from Enginer-
40 Sectional Drawing-
35 Existing Layout Plan-
36 Existing Section Plan-
37 Change of land-
47 Advocate search report-
21 declartion form B-
Prospectus/BrochureFile: Brochure - United Sai Arcade.pdf-
Advertisement Copy 1File: 6Will update.jpg-
Tower Excel SheetFile: PRM_KA_RERA_1251_446_PR_180521_001790.xlsx-
Occupancy CertificateFile: UNITED SAI ARCADE OC.pdf-
Completion certificateFile: united.pdf-
Registered Agreement of SaleFile: 432 Sale Agreement.pdf-
Registered conveyance deed for an individual unitFile: Saledeed.pdf-

How this compares with Bengaluru Urban

34%of Bengaluru Urban projects moved their completion datethis one moved by 6 months
1%of Bengaluru Urban registrations are shown as withdrawn or revokedthis one is not

Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.

Keep UNITED SAI ARCADE on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bengaluru Urban4,100+ in Bengaluru Urban

2 kmUNITED SAI ARCADEOther 46Dot size: filed unitsN

Filed coordinates, straight-line distance. 46 registered projects within 2 km.

Builder: UNITED PROJECTS

UNITED PROJECTS has 4 registrations on RERA Karnataka, including UNITED PROJECTS DREAMCITY and UNITED SAI ARCADE. Its filings declare 1 earlier project, none of them declared completed. Read the full track record. See more projects on the Bengaluru Urban district page.

Frequently asked questions

What are my rights if UNITED SAI ARCADE is delayed beyond 30 Sep 2021?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of UNITED SAI ARCADE?

The registered promoter entity is UNITED PROJECTS, a partnership firm as per the filing. Neither this filing nor this promoter's other RERA Karnataka registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in UNITED SAI ARCADE?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at UNITED SAI ARCADE?

The professionals named in the filing: Architect: V SIVA KUMAR; Engineer: SRINIVAS RAO BOLIMUNTA. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in UNITED SAI ARCADE?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About UNITED SAI ARCADE. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save UNITED SAI ARCADE to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.