Home / Browse projects / Bengaluru Urban, Karnataka / Umiya Velociti
Umiya Velociti
By Umiya Builders and Developers
RG-KA-43862 · RERA PRM/KA/RERA/1251/309/PR/171102/001912
Source: official RERA Karnataka filing
Red flags
- Completion date moved by 9 months
- 1 extension taken
Clear
- No complaints on record
- Separate project account declared
Saved.
Umiya Velociti is a Commercial project by Umiya Builders and Developers in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/309/PR/171102/001912 on 2 Nov 2017. Possession is promised by 31 Dec 2020. The completion date has moved by 9 months from the original filing.
At a glance
Project
- NameUmiya Velociti
- TypeCommercial
- Location
- Bengaluru North
- Bengaluru Urban
- PincodeNot stated
- RERA no.PRM/KA/RERA/1251/309/PR/171102/001912
- ReraGenie IDRG-KA-43862
Key dates
Key facts
Registration and timeline
- StatusRegistration approved
- Registered on2 Nov 2017
- Promised completion31 Dec 2020
- Revised completionRevised to 31 Dec 2020 (originally 31 Mar 2020)
- Buildings1 building record
- Documents filed56 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| Umiya Velociti | - | - | - | 0 | 13 | 13 |
The full filing
Everything below is from the project's own RERA Karnataka filing, free to read.
Construction progress by building1
The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
Building:
| Activity | Progress |
|---|---|
| Earth work and other leveling preparation work | - |
| Foundation footing work | - |
| Retaining wall (All types) | - |
| Plinth level Beam | Not applicable |
| Sub-structure flooring (Parking Floor, more than one floor below general ground level) | - |
| RCC or MS Framed structure | - |
| Masonry construction: Bricks, Concrete blocks etc | - |
| Plastering inside , outside & Ceiling | - |
| Joinery: Doors, Windows, Ventilators etc | - |
| Basic work of Water supply, Sanitary and Electrification | - |
| Dadoing, Skirting, Flooring, Tiles work (All types) | - |
| Railing and Grill fixing | - |
| Electrification, Water supply and Sanitary Finishing | - |
| Wardrobe, Showcase, Kitchen cabinet, Puja work | Not applicable |
| Fire prevention and fire fighting fitting and fixture with network | - |
| Weather Proof work(tile,concrete) | - |
| Painting | - |
| Elevation work | - |
| Internal and External work including landscapes as per santioned drawings | - |
Progress on shared amenities41
Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Water Supply | Yes | - |
| Internal Roads & Footpaths | No | Not applicable |
| Sewage and Drainage System | Yes | - |
| Parks & Tree planting | No | Not applicable |
| Street Lighting | Yes | - |
| Provision for community buildings and for treatment and disposal of sewage and sullage water | Yes | - |
| Solid waste management and disposal | Yes | - |
| Water conservation | Yes | - |
| Energy management | Yes | - |
| Fire protection and fire safety requirements | No | Not applicable |
| Education/Health/Other public amenities | Yes | - |
| Electricity supply transformer and substation | Yes | - |
| Emergency Evacuation services | Yes | - |
| Storm water drains | Yes | - |
| Use of renewable energy | Yes | - |
| Water conservation/rain water harvesting/recharge of ground water | Yes | - |
| Electricity | Yes | - |
| Smart Home Automation | No | Not applicable |
| CCTV Surveillance | Yes | - |
| Club House | No | Not applicable |
| Community Hall | No | Not applicable |
| Outdoor Sports facility | No | Not applicable |
| Indoor Sports facility | No | Not applicable |
| Swimming Pool | No | Not applicable |
| Gym | No | Not applicable |
| Parks | No | Not applicable |
| Power Backup | Yes | - |
| Gas | No | Not applicable |
| Water and Sanitation | Yes | - |
| Air Conditioning And incerntion | Yes | - |
| Staircases | Yes | - |
| Lifts | Yes | - |
| Staircases and Lift lobbies, corridor,lobbies, corridor | Yes | - |
| Fire escapes | Yes | - |
| Common entrance and exit for the building / common portico/foyer/verandah | Yes | - |
| Basement | Yes | - |
| Terrace | Yes | - |
| Outer Wall | No | Not applicable |
| Open parking areas and common storage spaces | Yes | - |
| Provision for lodging of management staff and security staff | No | Not applicable |
| Water conservation and renewable energy | Yes | - |
Land and ownership
This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Project account and cost
70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners2
Certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | C B VIVEK UTHAIAH |
| Engineer | Pragathi Consultants |
Extensions applied for1
A revised date filed with the regulator does not change the possession date in your agreement for sale.
No reason recorded in the filing
Complaints filed with RERA Karnataka
No complaints on record against this registration.
Documents filed56
As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/309/PR/171102/001912 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| CertificateFile: Ser Tax UBD 1.jpg | - |
| Architect Certificate for Work Completion Schedule till DateFile: Architect Certificate Q2 2019-20.pdf | - |
| Engineer Certificate for Work Completion Schedule till DateFile: Engineer certificate Q2 2019-20.pdf | - |
| CA Certificate for Funds UtilizationFile: Scan CA Certificate Q2 2019-20 velociti.pdf | - |
| Architect Certificate for Pending Work Completion Schedule.File: RERA Architect Certificate - Pending.pdf | - |
| Engineer Certificate for Pending Work Completion Schedule.File: RERA Engineer Certificate - Pending.pdf | - |
| CA Certificate for Funds required for Project CompletionFile: RERA CA Certificate - Pending.pdf | - |
| AffidavitFile: Affidavit 20-03-2020.pdf | - |
| Latest Encumbrance CertificateFile: Velociti EC Latest.pdf | - |
| Details Of Sold/ Un-sold UnitsFile: SoldUnsoldDetails.xlsx | - |
| Document 1File: RERA - Plan revision in process - Pending.pdf | - |
| COMMENCEMENT CERTIFICATE NOT ISSUED | - |
| Site Plan | - |
| Layout Plan | - |
| Sale Deed | - |
| Umiya Velociti Final Agreement_to_sell-UDS | - |
| LAND DOCUMENTS | - |
| Section Plan | - |
| AREA DEVELOPMENT | - |
| ALLOTMENT LETTER | - |
| Brochure | - |
| UMIYA VELOCITI-NOC | - |
| UMIYA VELOCITI PROJECT SPECIFICATIONS | - |
| Umiya Velociti Encumbrance Certificate | - |
| LAND DOCUMENTS | - |
| LAND DOCUMENTS | - |
| Balance Sheet 2015 - 2016File: BS 16 001.jpg | - |
| Balance Sheet 2014 - 2015File: BS 15 001.jpg | - |
| Balance Sheet 2013 - 2014File: BS 14 001.jpg | - |
| Audited Profit and Loss Statement 2015 - 2016File: PL 16 001.jpg | - |
| Audited Profit and Loss Statement 2014 - 2015File: PL 15 001.jpg | - |
| Audited Profit and Loss Statement 2013 - 2014File: PL 14 001.jpg | - |
| Director's Report 2015 - 2016File: Directors Report.pdf | - |
| Director's Report 2014 - 2015File: Directors Report.pdf | - |
| Director's Report 2013 - 2014File: Directors Report.pdf | - |
| Cash Flow Statement 2015 - 2016File: Cash Flow.pdf | - |
| Cash Flow Statement 2014 - 2015File: Cash Flow.pdf | - |
| Auditor's Report 2015 - 2016File: 3CB 16 001.jpg | - |
| Auditor's Report 2014 - 2015File: 3 CB 15 rr.jpg | - |
| Auditor's Report 2013 - 2014File: 3CB 14 001.jpg | - |
| Income Tax Return Acknowledgement 2015 - 2016File: IT 16-17 001.jpg | - |
| Income Tax Return Acknowledgement 2014 - 2015File: IT 15-16 001.jpg | - |
| Income Tax Return Acknowledgement 2013 - 2014File: IT 14-15 001.jpg | - |
| UMIYA VELOCITI RERA FORM B | - |
| Prospectus/BrochureFile: NO BROCHURE.pdf | - |
| Advertisement Copy 1File: NO ADVERTISEMENT.pdf | - |
| Tower Excel SheetFile: PRM_KA_RERA_1251_309_PR_171102_001912.xlsx | - |
| NOC issued by the Fire Force department after completion of workFile: Fire NOC- Umiya Velociti.pdf | - |
| Occupancy CertificateFile: Umiya Velociti OC.pdf | - |
| Consent for operation issued by KSPCBFile: KSPCB- CFE- Umiya Velociti.pdf | - |
| Certificate of operation for lifts issued by the Chief of Department of Electrical inspectorate Government of File: BESCOM- NOC-Umiya Velociti.pdf | - |
| Sanctioned Letter issued by concerned ESCOM of Power sanction and details of transformer installed and whetherFile: BESCOM- NOC-Umiya Velociti.pdf | - |
| Sanctioned letter issued by concerned water supply and sanitary board for the projectFile: BWSSB-NOC-Umiya Velociti.pdf | - |
| Architect certificate for having completed the work(in format no 5)File: QU - ARCHITECTS FORM 5 - COMPLTED CERTIFICATE.pdf | - |
| Chartered Accountant certificate for having completed the work(in format no 4)File: Form -4, Chartered Accountant quarter MAR 20.pdf | - |
| Affidavit cum declaration from promoter for having completed the project as per specification and as per adverFile: Affidavit-Umiya Velociti_Project Completion.pdf | - |
Promoter's earlier projects1
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Status | Promised | Delivered |
|---|---|---|---|---|
| Umiya Willows | - | Completed | Aug 2017 | No date filed |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Bengaluru Urban
Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.
Keep Umiya Velociti on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Bengaluru Urban4,100+ in Bengaluru Urban
Prestige Park Grove
PRESTIGE PROJECTS PRIVATE LIMITED
Prestige Lakeside Habitat
Prestige Habitat Ventures
LivingTree by Kalyani Developers
Kalyani Tech Park Private Limited
PRESTIGE FALCON CITY
PRESTIGE NOTTINGHILL INVESTMENTS
SATTVA CITY
SATTVA CITY PRIVATE LIMITED
GM AMBITIOUS ENCLAVE
M/s. Allam Infinite India Private Limited
See every Bengaluru Urban project, with the district possession charts
Builder: Umiya Builders and Developers
Umiya Builders and Developers has 2 registrations on RERA Karnataka, including Umiya Velociti and Umiya Woods. Its filings declare 1 earlier project, 1 of them declared completed. Read the full track record. See more projects on the Bengaluru Urban district page.
Frequently asked questions
What are my rights if Umiya Velociti is delayed beyond 31 Dec 2020?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.
How do I verify and contact the developer of Umiya Velociti?
The registered promoter entity is Umiya Builders and Developers, a company as per the filing. Neither this filing nor this promoter's other RERA Karnataka registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.
Is my payment protected in Umiya Velociti?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
Who certifies construction progress at Umiya Velociti?
The professionals named in the filing: Architect: C B VIVEK UTHAIAH; Engineer: Pragathi Consultants. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Umiya Velociti?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.