Home / Browse projects / Bengaluru Urban, Karnataka / TRENDCON AURELIUS

Registration approved No litigation declared Plotted Development project

TRENDCON AURELIUS

By TRENDCON INFRA LLP

RG-KA-59748 · RERA PRM/KA/RERA/1251/308/PR/211223/006504 · Last updated on RERA Karnataka portal: 14 Oct 2026

Source: official RERA Karnataka filing

Red flags

  • Completion date moved by 12 months
  • 1 extension taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
Oct 2026Possession promisedmoved 12 months from the original
0Complaints at RERA Karnatakaon this registration
Jump to the 156 documents Report an error

TRENDCON AURELIUS is a Plotted Development project by TRENDCON INFRA LLP in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/308/PR/211223/006504 on 21 Dec 2023. Possession is promised by 31 Oct 2026. The completion date has moved by 12 months from the original filing.

At a glance

Project

  • NameTRENDCON AURELIUS
  • TypePlotted Development
  • Location
    • Anekal
    • Bengaluru Urban
  • PincodeNot stated
  • RERA no.PRM/KA/RERA/1251/308/PR/211223/006504
  • ReraGenie IDRG-KA-59748

Builder

  • NameTRENDCON INFRA LLP
  • Entity typePartnership Firm
  • LLPINAAW-5913
  • GSTIN29AAJFL6525E1Z6
  • Authorized SignatorySukanya pakala
  • Other registrations1 more →
  • No longer live1 withdrawn or revoked
  • Declared earlier projects1 →

Key dates

this monthRegisteredDec 2023First promiseOct 2025Revised toOct 2026

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on21 Dec 2023
  • Promised completion31 Oct 2026
  • Revised completionRevised to 31 Oct 2026 (originally 31 Oct 2025)
  • BuildingsNot stated in filing
  • Documents filed156 files

Current status

5.8%Of the estimated cost spent so far

Figures as on 14 Oct 2026, this project's latest RERA Karnataka filing.

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Land and ownership1

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Named landowners1
LandownerVillageDistrict
B.Shivanna--

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 70.39 cr
Cost incurredRs 4.08 cr
Spent of the estimate5.8%
Cost lineEstimatedIncurred
Estimated Cost of Construction as certified by EngineerRs 46.98 crRs 1.63 cr
On-site expenditure-Site OverheadRs 9.67 crRs 1.02 cr
On-site expenditure-Cost Of Services(Water, Electricity, Sewage)Rs 8.24 crRs 1.02 cr
Principal sum and interest payable to financial institutions-Money Lenders on construction funding or money borrowed for constructionRs 4.00 cr-
On-site expenditure-Consultants FeesRs 95.00 lakhRs 20.41 lakh
On-site expenditure-Salaries of workersRs 40.00 lakhRs 20.41 lakh
Payment of chargesRs 15.00 lakh-

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
EngineerCHANDRASHEKAR S
Chartered AccountantIVSS Raju

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EX/PRM/KA/RERA/1251/308/PR/251204/006504Oct 2025 → Oct 2026

Reason as filed by the promoterothers

Complaints filed with RERA Karnataka

No complaints on record against this registration.

Documents filed156

As listed on the registration, under the names the promoter filed them with; the newest 80 of 156 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/308/PR/211223/006504 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Q2 2026-27 Form-4 Certificate issued by Chartered AccountantFile: Trendcon Infra LLP- RERA FORM -4 Q2-2026-27.pdf14 Oct 2026
Q2 2026-27 Form-6 Certificate issued by Structural EngineerFile: Form-6^J Engineer (QU) Q2 2026-27 Aurelius.pdf14 Oct 2026
Q2 2026-27 Water supply and sewage board14 Oct 2026
Q2 2026-27 KSPCB- PCB (10 Acres to 125 Acres)14 Oct 2026
Q2 2026-27 Engineering Department (PWD) for completion of development works14 Oct 2026
Q2 2026-27 KPTCL- BESCOM14 Oct 2026
Q2 2026-27 Horticulture department14 Oct 2026
Q1 2026-27 Form-4 Certificate issued by Chartered AccountantFile: Form 4 Q1 2026-27.pdf9 Jul 2026
Q1 2026-27 Form-6 Certificate issued by Structural EngineerFile: Form-6^J Engineer (QU) Q1 2026-27 Aurelius.pdf9 Jul 2026
Q1 2026-27 Water supply and sewage board9 Jul 2026
Q1 2026-27 KSPCB- PCB (10 Acres to 125 Acres)9 Jul 2026
Q1 2026-27 Engineering Department (PWD) for completion of development works9 Jul 2026
Q1 2026-27 KPTCL- BESCOM9 Jul 2026
Q1 2026-27 Horticulture department9 Jul 2026
Q4 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Trendcon Aurelius Form 4 Q4 25-26.pdf6 May 2026
Q4 2025-26 Form-6 Certificate issued by Structural EngineerFile: Form-6^J Engineer (QU) Q4 2025-26 Aurelius.pdf6 May 2026
Q4 2025-26 Water supply and sewage board6 May 2026
Q4 2025-26 KSPCB- PCB (10 Acres to 125 Acres)6 May 2026
Q4 2025-26 KPTCL- BESCOM6 May 2026
Q4 2025-26 Horticulture department6 May 2026
Q3 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Form 4 Q3 25-26 Trendcon Aurelius_0001.pdf18 Feb 2026
Q3 2025-26 Form-6 Certificate issued by Structural EngineerFile: Form-6^J Engineer (QU) Q3 2025-26 Aurelius.pdf18 Feb 2026
Q3 2025-26 Water supply and sewage board18 Feb 2026
Q3 2025-26 KSPCB- PCB (10 Acres to 125 Acres)18 Feb 2026
Q3 2025-26 KPTCL- BESCOM18 Feb 2026
Q3 2025-26 Horticulture department18 Feb 2026
Sold Unsold InventoryFile: Sold Unsold Inventory.pdf25 Nov 2025
Affidavit BWSSBFile: Affidavit BWSSB.pdf25 Nov 2025
Renewed Approved Provisional Layout plan original drawings.File: Plan - Trendcon Aurelius.pdf21 Nov 2025
Renewed Approved Provisional layout plan order Original letterFile: Plan Approval Letter - Trendcon Aurelius.pdf21 Nov 2025
Kindly upload sold and unsold units details duly mentioning the project name and address along withFile: Sold Unsold Inventory - Trendcon Aurelius.pdf21 Nov 2025
BESCOM NOCFile: NOC Electrical - Trendcon Aurelius.pdf21 Nov 2025
BWSSB NOCFile: NOC water - Trendcon Aurelius.pdf21 Nov 2025
Signed Form 6 luxuriaFile: Signed Form 6 luxuria.pdf16 Dec 2023
KGWA ClarificationFile: KGWA Clarification.pdf16 Dec 2023
Estimated Cost Of ConstructionFile: Estimated Cost of Construction.pdf16 Dec 2023
Previous project quarterly updates not uploadedFile: Quarterly update Details.pdf7 Dec 2023
Firm registration certificateFile: Firm Registration Certificate.pdf7 Dec 2023
What are all the sources of funds to complete the projectFile: Source of Fund Signed.pdf7 Dec 2023
Title/Sale deed in favour of B. Shivanna for Sy no.2/1 Ext 12-00 A-GFile: Sale Deed 2005.pdf7 Dec 2023
Notarized Non litigation Affidavit containing project name, promoter name, land owner name with subjFile: Non-Litigation Affidavit.pdf7 Dec 2023
Notarized Joint Affidavit Cum Declaration in RERA prescribed format and signed by promoter & land owFile: Affidavit Cum Declaration.pdf7 Dec 2023
Upload horticulture department NOC for park developmentFile: clarification horticulture noc.pdf7 Dec 2023
Upload KSPCB CFEFile: Clarification for KSPCB NOC.pdf7 Dec 2023
Engineer certificate in the prescribed format(Form-6)File: Form 6.pdf7 Dec 2023
valid NOC issued by the Power supply Authorities along with a copy of the fee receipt paid towards tFile: BESCOM NOC with Receipt.pdf7 Dec 2023
Permission letter issued by the Karnataka ground Water Authority along with the Bore well yield testFile: Clarification for KGWA.pdf7 Dec 2023
brief estimated cost of construction certified by the EngineerFile: Estimation cost of development.pdf7 Dec 2023
Land cost calculation sheet as per the guidance valueFile: Sub Register Guidline Calculation.pdf7 Dec 2023
proforma of the Agreement for saleFile: Proforma Agreement for Sale.pdf7 Dec 2023
proforma of the Allotment letterFile: Proforma Allotment letter.pdf7 Dec 2023
mention the project name properly as per the name mentioned on the project details in the affidavitFile: Notarised Afidavit.pdf7 Dec 2023
Firm Reg CertificateFile: Firm Reg Cert.pdf12 Nov 2023
Clarification for the land owners signatureFile: Clarification for the land owners signature.pdf12 Nov 2023
Sub Registrar guidelines value certificateFile: Sub Registrar guidelines value certificate.pdf12 Nov 2023
Commencement and WorkorderFile: Commencement and Workorder.pdf12 Nov 2023
CDP MapFile: CDP Map_compressed.pdf12 Nov 2023
STPFile: Aurelius STP without signature.pdf12 Nov 2023
CLUFile: CLU.pdf12 Nov 2023
Village MapFile: HT village map.pdf12 Nov 2023
Pollution FeeFile: Fee Pollution.pdf12 Nov 2023
RTC, survey Old Sy No. 2, New Sy No. 2/1-
Mutation, survey Old Sy No. 2, New Sy No. 2/1-
Encumbrance Certificate, survey Old Sy No. 2, New Sy No. 2/1-
Conversion/Alienation Order, survey Old Sy No. 2, New Sy No. 2/1-
JDA, survey Old Sy No. 2, New Sy No. 2/1-
Khatha, survey Old Sy No. 2, New Sy No. 2/1-
Registration CertificateFile: Partnership Deed_compressed.pdf-
Partnership DeedFile: Partnership Deed_compressed.pdf-
Partner Details-
Partner Details-
Partner Details-
Certificate issued by CA Form 1File: Luxuria Homes LLp _ RERA From Reg-1[1].pdf-
Certificate issued by Engineer Form 3File: FORM-2-arch certificate[1] v2.pdf-
Project Chartered Accountant-
Project Engineer-
AffidavitFile: Affidavit.pdf-
Certificate from Chartered AccountFile: Luxuria Homes LLp _ RERA From Reg-1[1].pdf-
Certificate issued by ArchitectFile: FORM-2-arch certificate[1] v2.pdf-
Balance Sheet 2022 - 2023File: Luxuria Homes LLP ITR AY 2023-24.pdf-

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 not delivered by the promised date
ProjectLocationStatusPromisedDelivered
LUXURIA LAKE VIEWVEERANAHALLIOngoingJun 2025Not delivered

How this compares with Bengaluru Urban

34%of Bengaluru Urban projects moved their completion datethis one moved by 12 months
1%of Bengaluru Urban registrations are shown as withdrawn or revokedthis one is not

Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.

Keep TRENDCON AURELIUS on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bengaluru Urban4,100+ in Bengaluru Urban

Builder: TRENDCON INFRA LLP

TRENDCON INFRA LLP has 2 registrations on RERA Karnataka, including TRENDCON AURELIUS and TRENDCON LAKEVIEW. Its filings declare 1 earlier project, none of them declared completed. Read the full track record. See more projects on the Bengaluru Urban district page.

Frequently asked questions

What are my rights if TRENDCON AURELIUS is delayed beyond 31 Oct 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of TRENDCON AURELIUS?

The registered promoter entity is TRENDCON INFRA LLP, a partnership firm as per the filing. Its LLPIN AAW-5913 and GSTIN 29AAJFL6525E1Z6 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in TRENDCON AURELIUS?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at TRENDCON AURELIUS?

The professionals named in the filing: Engineer: CHANDRASHEKAR S; Chartered Accountant: IVSS Raju. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in TRENDCON AURELIUS?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About TRENDCON AURELIUS. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save TRENDCON AURELIUS to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.