Registration approved Residential/Group Housing project

Tranquil at Brigade Cornerstone Utopia

By Mysore Projects Private Limited

RG-KA-03214 · RERA PRM/KA/RERA/1251/446/PR/200123/003231 · Last updated on RERA Karnataka portal: 21 Jan 2020

Source: official RERA Karnataka filing

Red flags

  • 2 complaints at RERA Karnataka
  • Completion date moved by 9 months
  • 1 extension taken

Clear

  • Separate project account declared
Sep 2025Possession promisedmoved 9 months from the original
2Complaints at RERA Karnatakaon this registration
Jump to the 91 documents Report an error

Tranquil at Brigade Cornerstone Utopia is a Residential/Group Housing project by Mysore Projects Private Limited in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/446/PR/200123/003231 on 23 Jan 2020. Possession is promised by 30 Sep 2025. The completion date has moved by 9 months from the original filing. 2 complaints are on record with the regulator.

At a glance

Project

  • NameTranquil at Brigade Cornerstone Utopia
  • TypeResidential/Group Housing
  • Location
    • Bengaluru East
    • Bengaluru Urban
  • PincodeNot stated
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PRM/KA/RERA/1251/446/PR/200123/003231
  • ReraGenie IDRG-KA-03214

Builder

  • NameMysore Projects Private Limited
  • Entity typeCompany
  • CINU70102KA2010PTC054771
  • Authorized SignatoryViswa Prathap Desu
  • Other registrations6 more →
  • Declared earlier projects4 →

Key dates

this monthRegisteredJan 2020First promiseDec 2024Revised toSep 2025

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on23 Jan 2020
  • Promised completion30 Sep 2025
  • Revised completionRevised to 30 Sep 2025 (originally 31 Dec 2024)
  • Buildings7 building records
  • Documents filed91 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Tower K---1600160
Tower L---94094
Tower M---1140114
Tower N---1160116
Tower O---1140114
Tower P---1060106
Tower Q---1600160

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 21 Jan 2020, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

Building:

ActivityProgress
Earth work and other leveling preparation work-
Foundation footing work-
Retaining wall (All types)-
Plinth level BeamNot applicable
Sub-structure flooring (Parking Floor, more than one floor below general ground level)-
RCC or MS Framed structure-
Masonry construction: Bricks, Concrete blocks etcNot applicable
Plastering inside , outside & CeilingNot applicable
Joinery: Doors, Windows, Ventilators etc-
Basic work of Water supply, Sanitary and Electrification-
Dadoing, Skirting, Flooring, Tiles work (All types)-
Railing and Grill fixing-
Electrification, Water supply and Sanitary Finishing-
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Fire prevention and fire fighting fitting and fixture with network-
Weather Proof work(tile,concrete)-
Painting-
Elevation work-
Internal and External work including landscapes as per santioned drawings-

Progress on shared amenities41

As on 21 Jan 2020, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes-
Internal Roads & FootpathsNoNot applicable
Sewage and Drainage SystemYes-
Parks & Tree plantingNoNot applicable
Street LightingNoNot applicable
Provision for community buildings and for treatment and disposal of sewage and sullage waterYes-
Solid waste management and disposalYes-
Water conservationNoNot applicable
Energy managementYes-
Fire protection and fire safety requirementsNoNot applicable
Education/Health/Other public amenitiesYes-
Electricity supply transformer and substationYes-
Emergency Evacuation servicesYes-
Storm water drainsYes-
Use of renewable energyYes-
Water conservation/rain water harvesting/recharge of ground waterYes-
ElectricityYes-
Smart Home AutomationNoNot applicable
CCTV SurveillanceYes-
Club HouseYes-
Community HallYes-
Outdoor Sports facilityYes-
Indoor Sports facilityYes-
Swimming PoolYes-
GymYes-
ParksYes-
Power BackupYes-
GasNoNot applicable
Water and SanitationYes-
Air Conditioning And incerntionNoNot applicable
StaircasesYes-
LiftsYes-
Staircases and Lift lobbies, corridor,lobbies, corridorYes-
Fire escapesYes-
Common entrance and exit for the building / common portico/foyer/verandahYes-
BasementYes-
TerraceYes-
Outer WallNoNot applicable
Open parking areas and common storage spacesYes-
Provision for lodging of management staff and security staffNoNot applicable
Water conservation and renewable energyYes-

Land and ownership3

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area40,308 sq m
Named landowners3
LandownerVillageDistrict
G. Narayanappa--
M. Prasad--
Cornerstone Bay East Developers Private Limited--

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 413.00 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectC B Vivek Uthaiah
EngineerDesignTree Service Consultants Pvt. Ltd.

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

ExtensionDec 2024 → Sep 2025

No reason recorded in the filing

Complaints filed with RERA Karnataka2

Case no.ComplainantRespondentFiled
00381/2024-Mysore Projects Private Limited15/04/2024
00382/2024-Mysore Projects Private Limited15/04/2024

Documents filed91

As listed on the registration, under the names the promoter filed them with; the newest 80 of 91 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/446/PR/200123/003231 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Income Tax Returns - 2019-20File: MPPL 2019-20.pdf21 Jan 2020
Company Registration CertificateFile: Certificate of Incorporation.pdf21 Jan 2020
Conversion OrdersFile: Conversion Orders.pdf21 Jan 2020
Encumbrance Certificate for 15 years in Form 15File: Encumbrance Certificate - Tranquil.pdf21 Jan 2020
Clarification regarding Sy No's with extent involved in the projectFile: Sy Nos for Tranquil.pdf21 Jan 2020
Typical Floor Plans - Part 1File: Tranquil - Typical Floor Plans-1.pdf21 Jan 2020
Typical Floor Plans - Part 2File: Tranquil - Typical Floor Plans-2.pdf21 Jan 2020
Typical Floor Plans - Part 3File: Tranquil - Typical Floor Plans-3.pdf21 Jan 2020
Typical Floor Plans - Part 4File: Tranquil - Typical Floor Plans-4.pdf21 Jan 2020
Typical Floor Plans - Part 5File: Tranquil - Typical Floor Plans-5.pdf21 Jan 2020
Typical Floor Plans - Part 6File: Tranquil - Typical Floor Plans-6.pdf21 Jan 2020
Fire NOCFile: Brigade Cornerstone Utopia - Fire NOC.pdf21 Jan 2020
Site Plan with Blown UpFile: Site plan with blown up- Tranquil.pdf21 Jan 2020
Brigade Cornerstone Utopia - Tranquil - Sanction Plan Letter-
TRANQUIL_Site Plan-
Development Plan-
Note - Sale Deed-
Proforma Sale Agreement - Tranquil at Brigade Cornerstone Utopia-
Title Documents and RTC-
Section and Elevation_compressed (1)-
Development Plan-
Allotment Letter -Tranquil at Brigade Cornerstone Utopia-
Brochure- Tranquil at Brigade Cornerstone Utopia-
Tranquil @ Brigade Cornerstone Utopia - Specification-
Encumbrance Certificate - Tranquil-
Section 3(1) Affidavit- Tranquil at Brigade Cornerstone Utopia-
Joint Development Affidavit- Tranquil at Brigade Cornerstone Utopia-
Khata Certificate & Extract-
Cornerstone - JDA-
Brigade Cornerstone Utopia - Fire NOC-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Relinquishment Deed-
Unnamed document-
Brigade Cornerstone Utopia - AAI NOC-
Brigade Cornerstone Utopia - BESCOM NOC-
Brigade Cornerstone Utopia - BWSSB NOC-
Brigade Cornerstone Utopia - KSPCB-
Brigade Cornerstone Utopia - Environmental Clearance-
Brigade Cornerstone Utopia - BSNL NOC-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
TRANQUIL_Blown up Details (1)-
Section Elevation and Specification-
Conversion Orders_compressed-
Title Opinion_compressed-compressed_compressed (1)-
Balance Sheet 2018 - 2019File: Balance Sheet - 2018-19 (1).pdf-
Balance Sheet 2017 - 2018File: Balance Sheet - 2017-18 (1).pdf-
Balance Sheet 2016 - 2017File: Balance Sheet -2016 -17.pdf-
Audited Profit and Loss Statement 2018 - 2019File: Statement of Profit and Loss - 2018-19 (1).pdf-
Audited Profit and Loss Statement 2017 - 2018File: Statement of Profit and Loss - 2017-18.pdf-
Audited Profit and Loss Statement 2016 - 2017File: Statement of Profit and Loss- 2016-17.pdf-
Director's Report 2018 - 2019File: Board's Report - 31-03-2017 (1).pdf-
Director's Report 2017 - 2018File: Board's Report - 31-03-2016 (1).pdf-
Director's Report 2016 - 2017File: Board's Report - 31-03-2015.pdf-
Cash Flow Statement 2018 - 2019File: Cash Flow Statement - 2018-19 (1).pdf-
Cash Flow Statement 2017 - 2018File: Cash Flow Statement - 2017-18 (1).pdf-
Auditor's Report 2018 - 2019File: Auditors Report - 2018-19 (1).pdf-
Auditor's Report 2017 - 2018File: Auditors Report - 2017-18 (1).pdf-
Auditor's Report 2016 - 2017File: Auditors Report - 2016-17.pdf-
Income Tax Return Acknowledgement 2018 - 2019File: ITR 2018-19.pdf-
Income Tax Return Acknowledgement 2017 - 2018File: ITR 2017-18.pdf-
Income Tax Return Acknowledgement 2016 - 2017File: ITR 2016- 17 (1).pdf-
Form B- Affidavit Tranquil at Brigade Cornerstone Utopia-
Prospectus/BrochureFile: Tranquil at Brigade Cornerstone Utopia brochure.pdf-
Advertisement Copy 1File: Tranquil Ad copy.pdf-
Tower Excel SheetFile: PRM_KA_RERA_1251_446_PR_200123_003231.xlsx-
Stability CertificateFile: Tranquil - Structural Stability Certificate.pdf-
Road cutting permission letter issued by the planning Authority for laying Water supply line, sanitary line, UFile: BBMP-PERMISSION-ROAD CUTTING WORK.pdf-
NOC issued by the Fire Force department after completion of workFile: Tranquil at Brigade Cornerstone Utopia - Fire CC.pdf-

Promoter's earlier projects3

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

3 not delivered by the promised date
ProjectLocationStatusPromisedDelivered
Halcyon at Brigade Cornerstone Utopia-OngoingDec 2024Not delivered
Serene at Brigade Cornerstone Utopia-OngoingJun 2023Not delivered
Eden at Brigade Cornerstone Utopia-OngoingJun 2023Not delivered

How this compares with Bengaluru Urban

34%of Bengaluru Urban projects moved their completion datethis one moved by 9 months
1%of Bengaluru Urban registrations are shown as withdrawn or revokedthis one is not

Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.

Keep Tranquil at Brigade Cornerstone Utopia on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bengaluru Urban4,100+ in Bengaluru Urban

2 kmTranquil at Brigade CornOther 49Dot size: filed unitsN

Filed coordinates, straight-line distance. 49 registered projects within 2 km.

Builder: Mysore Projects Private Limited

Mysore Projects Private Limited has 7 registrations on RERA Karnataka, including Elysium at Brigade Cornerstone Utopia and Serene at Brigade Cornerstone Utopia. Its filings declare 4 earlier projects, none of them declared completed. Litigation is declared on 1 of its registrations. Read the full track record. See more projects on the Bengaluru Urban district page.

Frequently asked questions

What are my rights if Tranquil at Brigade Cornerstone Utopia is delayed beyond 30 Sep 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of Tranquil at Brigade Cornerstone Utopia?

The registered promoter entity is Mysore Projects Private Limited, a company as per the filing. Its CIN U70102KA2010PTC054771 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in Tranquil at Brigade Cornerstone Utopia?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against Tranquil at Brigade Cornerstone Utopia?

Each case number above is a complaint filed with RERA Karnataka. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

Who certifies construction progress at Tranquil at Brigade Cornerstone Utopia?

The professionals named in the filing: Architect: C B Vivek Uthaiah; Engineer: DesignTree Service Consultants Pvt. Ltd.. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Tranquil at Brigade Cornerstone Utopia?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Tranquil at Brigade Cornerstone Utopia. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Tranquil at Brigade Cornerstone Utopia to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.