Registered Litigation declared Mixed project

TOWER INDUSTRIAL PARK

By TOWER ENGINEERING PRIVATE LIMITED

RG-MH-45808 · RERA P51700047580 · Last updated on MahaRERA portal: 22 Jun 2026

Source: official MahaRERA filing

Red flags

  • Litigation declared, 3 cases

Clear

  • No complaints on record
  • Completion date never moved
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

1 condition is on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Thane registration emailed to you, free during the pilot beta.
Sep 2027Possession promisedno revision filed
7 of 11Construction stages donefurthest along: Sanitary Fittings within the flats /..., 95%
23 of 56Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 144 documents Report an error

TOWER INDUSTRIAL PARK is a Mixed project by TOWER ENGINEERING PRIVATE LIMITED in Thane, Maharashtra, registered with MahaRERA as P51700047580 on 14 Nov 2022. Possession is promised by 30 Sep 2027. 33 of the 56 units on this registration are recorded sold or booked, and 7 of 11 construction stages are filed complete.

At a glance

Project

  • NameTOWER INDUSTRIAL PARK
  • TypeMixed
  • Location
    • ROAD NO 28
    • WAGLE ESTATE MIDC
    • Thane (M Corp.)
    • Thane
    • 400604
  • Pincode400604
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51700047580
  • ReraGenie IDRG-MH-45808

Builder

  • NameTOWER ENGINEERING PRIVATE LIMITED
  • Entity typeCompany
  • DirectorsASHISH KAMPANI, RACHNA KAMPANI, NIGEL DAVIS

Key dates

this monthRegisteredNov 2022PromisedSep 2027

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on14 Nov 2022
  • Promised completion30 Sep 2027
  • Revised completionNone
  • Buildings1 building record
  • Documents filed144 files

Current status

59%33 of 56 units booked
81.8%Work done, per cost certificate

Figures as on 22 Jun 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
TOWER INDUSTRIAL PARKNA6505656

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 22 Jun 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

7 of 11 construction stages are filed complete. The stage furthest along is Sanitary Fittings within the flats / premises, at 95%.

TOWER INDUSTRIAL PARK: 72% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises95%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 22 Jun 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes100%
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes100%
Street LightingYes100%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes100%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingNoNot applicable
Energy managemcntYes0%
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes90%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingYes0%

Parking filed39

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots39
Open Space39

Land and ownership

Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area4,160 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on16 Jul 2025

Approvals and building plan

Sanctioning authorityMAHARASHTRA INDUSTRIAL DEVELOPMENT CORPORATION
Permissible FSI6248.92
Proposed, not sanctioned2,866 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchLANDMARK BUILDING PALI NAKA PALI HILL BANDRA WEST MUMBAI 400 050
Estimated costRs 13.00 cr
Cost incurredRs 10.63 cr
Work done81.76%
BuildingWingEstimatedIncurred
TOWER INDUSTRIAL PARKNARs 13.00 crRs 10.63 cr

Certifying professionals and partners5

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectAPICES STUDIO PRIVATE LIMITED
EngineerAJAY MAHALE
EngineerJagdish Rauthan
Chartered AccountantROSHAN GAWDE & CO
Chartered AccountantA K O R D & CO
PartnerRole in project
TOWER ENGINEERING PRIVATE LIMITED-

Litigation declared3

CaseCourtStatus
RCS/273/2024/2024Joint Civil Judge Senior Division and Addl C J M ThaneOngoing
R.C.S./273/2024/20244th Joint Civil Judge Senior Division and Addl.C.J.M. ThaneOngoing
R.C.S./226/2024/20244th Joint Civil Judge Senior Division and Addl.C.J.M. ThaneOngoing

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 30 Oct 2022
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 28 Oct 2022
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 28 Oct 2022
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 28 Oct 2022Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 30 Sep 2027

Documents filed144

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 144 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: FORM 1 Tower Engineering Q4 FY 25-26 Signed.pdf22 Jun 2026
Withdrawal Update Form 2File: FORM 2_ Tower Industrial Park Q4 FY 25-26 signed.pdf22 Jun 2026
Withdrawal Update Form 3File: FORM 3 Tower Engineering_Q4 FY 25-26 Signed.pdf22 Jun 2026
Withdrawal Update Form 1File: Final Form 1 Q3 (1).pdf9 Mar 2026
Withdrawal Update Form 2File: FORM 2 Q3 FY 25-26.pdf9 Mar 2026
Withdrawal Update Form 3File: Final Form 3 Q3.pdf9 Mar 2026
Withdrawal Update Form 1File: Final Form 1 Q3 (1).pdf4 Mar 2026
Withdrawal Update Form 2File: FORM 2 Q3 FY 25-26.pdf4 Mar 2026
Withdrawal Update Form 3File: Final Form 3 Q3.pdf4 Mar 2026
Withdrawal Update Form 1File: Signed Form 1 Q2.pdf5 Jan 2026
Withdrawal Update Form 2File: Form 2 Q2 .pdf5 Jan 2026
Withdrawal Update Form 3File: FORM 3.pdf5 Jan 2026
Form 5 (FY 2024-2025)File: Final FORM 5 FY 24-25.pdf9 Dec 2025
Withdrawal Update Form 1File: ARCHIT_1.PDF18 Sep 2025
Withdrawal Update Form 2File: FORM 2 ENGINEERERS CERTIFICATE 30-06-2025.pdf18 Sep 2025
Withdrawal Update Form 3File: Final_Signed_FORM 3_Q1_FY 25-26.pdf18 Sep 2025
Withdrawal Update Form 1File: ARCHITECT CERTIFICATE Q4.pdf16 Jul 2025
Withdrawal Update Form 2File: Form 2 Q4 FY 24-25.pdf16 Jul 2025
Withdrawal Update Form 3File: FORM-3 Tower Industrial Park.pdf16 Jul 2025
Form 2A (FY 2024-2025)File: Form 2A_format_New Format-1.pdf30 Jun 2025
Form 1File: ARCHITECT CERTIFICATE Q4.pdf9 May 2025
Form 2File: Form 2 Q4 FY 24-25.pdf9 May 2025
Form 3File: FORM-3 Tower Industrial Park.pdf9 May 2025
Disclosure of Sold and Booked InventoryFile: Disclosure of Sold Unsold Inventory Q4.PDF9 May 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Q3 FY 24-25.pdf7 May 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Q4 FY 24-25.pdf7 May 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Q3 FY 24-25.pdf3 May 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM-3 Tower Industrial Park.pdf30 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCHITECT CERTIFICATE Q4.pdf23 Apr 2025
Disclosure of sold/ booked inventoryFile: Disclosure of Sold Unsold Inventory Q4.PDF15 Apr 2025
Details of encumbrances concerned to FinanceFile: Annexure K Non-Encumbrance related to Financial and Legal.PDF12 Apr 2025
CERSAI detailsFile: Annexure G Asset Based Declaration.PDF12 Apr 2025
CERSAI detailsFile: Annexure L Debtor Based Declaration.PDF12 Apr 2025
Details of encumbrances concerned to LegalFile: Annexure K Non-Encumbrance related to Financial and Legal.PDF12 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Signed Q3 Form 3 tower.pdf24 Jan 2025
Disclosure of sold/ booked inventoryFile: Disclosure of sold unsold Q3.PDF24 Jan 2025
Details of encumbrances concerned to FinanceFile: Updated non encumbrance.PDF24 Jan 2025
Details of encumbrances concerned to LegalFile: Updated non encumbrance.PDF24 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Signed Q3 Form 3 tower.pdf24 Jan 2025
Disclosure of sold/ booked inventoryFile: Disclosure of sold unsold Q3.PDF24 Jan 2025
Details of encumbrances concerned to FinanceFile: Updated non encumbrance.PDF24 Jan 2025
Details of encumbrances concerned to LegalFile: Updated non encumbrance.PDF24 Jan 2025
Details of encumbrances concerned to FinanceFile: Updated non encumbrance.PDF24 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Signed Q3 Form 3 tower.pdf24 Jan 2025
Disclosure of sold/ booked inventoryFile: Disclosure of sold unsold Q3.PDF24 Jan 2025
Details of encumbrances concerned to LegalFile: Updated non encumbrance.PDF24 Jan 2025
CERSAI detailsFile: Assets Based Declaration Q3.PDF18 Jan 2025
CERSAI detailsFile: Debtor Based Declaration Q3.PDF18 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCHITECT CERTIFICATE F1.pdf18 Jan 2025
CERSAI detailsFile: Assets Based Declaration Q3.PDF18 Jan 2025
CERSAI detailsFile: Debtor Based Declaration Q3.PDF18 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCHITECT CERTIFICATE F1.pdf18 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCHITECT CERTIFICATE F1.pdf18 Jan 2025
CERSAI detailsFile: Assets Based Declaration Q3.PDF18 Jan 2025
CERSAI detailsFile: Debtor Based Declaration Q3.PDF18 Jan 2025
CERSAI detailsFile: Annexure G-Asset Based Declaration.pdf16 Oct 2024
CERSAI detailsFile: Annexure L- Debtor Based Declaration.pdf16 Oct 2024
Details of encumbrances concerned to FinanceFile: Annexure K-Non-Encumbrance Concerned to Finance.pdf16 Oct 2024
Details of encumbrances concerned to LegalFile: Annexure K-Non-Encumbrance Concerned to Finance.pdf16 Oct 2024
Disclosure of sold/ booked inventoryFile: Annexure B-Disclosure of Sold or Unsold Inventory.pdf16 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM1 ARCHITECT CER 30-09.pdf16 Oct 2024
CERSAI detailsFile: Annexure G-Asset Based Declaration.pdf16 Oct 2024
CERSAI detailsFile: Annexure L- Debtor Based Declaration.pdf16 Oct 2024
Details of encumbrances concerned to FinanceFile: Annexure K-Non-Encumbrance Concerned to Finance.pdf16 Oct 2024
Details of encumbrances concerned to LegalFile: Annexure K-Non-Encumbrance Concerned to Finance.pdf16 Oct 2024
Disclosure of sold/ booked inventoryFile: Annexure B-Disclosure of Sold or Unsold Inventory.pdf16 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM1 ARCHITECT CER 30-09.pdf16 Oct 2024
Details of encumbrances concerned to FinanceFile: Annexure K-Non-Encumbrance Concerned to Finance.pdf16 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM1 ARCHITECT CER 30-09.pdf16 Oct 2024
Disclosure of sold/ booked inventoryFile: Annexure B-Disclosure of Sold or Unsold Inventory.pdf16 Oct 2024
CERSAI detailsFile: Annexure G-Asset Based Declaration.pdf16 Oct 2024
CERSAI detailsFile: Annexure L- Debtor Based Declaration.pdf16 Oct 2024
Details of encumbrances concerned to LegalFile: Annexure K-Non-Encumbrance Concerned to Finance.pdf16 Oct 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Final_FORM 5 FY 23-24_compressed.pdf7 Oct 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Final_FORM 5 FY 23-24_compressed.pdf7 Oct 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Final_FORM 5 FY 23-24_compressed.pdf7 Oct 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A_FY 23-24.pdf25 Jul 2024
Details of encumbrances concerned to FinanceFile: Annexure K-Non-Encumbrance Concerned to Finance.pdf22 Jul 2024
Details of encumbrances concerned to LegalFile: Annexure K-Non-Encumbrance Concerned to Finance.pdf22 Jul 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1_Q1.pdf19 Jul 2024

How this compares with Thane

59%of this project is bookeddistrict median 26%
24%of Thane projects moved their completion datethis one has not
23%of Thane registrations have lapsed or been cancelledthis one is on the register

Computed across the 7,600+ Thane projects on ReraGenie, from their own filings.

Free monthly report: Thane on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep TOWER INDUSTRIAL PARK on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near WAGLE ESTATE MIDC7,600+ in Thane

2 kmTOWER INDUSTRIAL PARKCompleted 17Lapsed / revoked 8Other 35Dot size: filed unitsN

Filed coordinates, straight-line distance. 60 registered projects within 2 km.

Builder: TOWER ENGINEERING PRIVATE LIMITED

TOWER ENGINEERING PRIVATE LIMITED has 1 registration on MahaRERA, including TOWER INDUSTRIAL PARK. Its filings disclose no earlier MahaRERA projects. Litigation is declared on 1 of its registrations. Read the full track record. See more projects on the Thane district page.

Frequently asked questions

What are my rights if TOWER INDUSTRIAL PARK is delayed beyond 30 Sep 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of TOWER INDUSTRIAL PARK?

The registered promoter entity is TOWER ENGINEERING PRIVATE LIMITED, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in TOWER INDUSTRIAL PARK?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for TOWER INDUSTRIAL PARK?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at TOWER INDUSTRIAL PARK?

The professionals named in the filing: Architect: APICES STUDIO PRIVATE LIMITED; Engineer: AJAY MAHALE; Engineer: Jagdish Rauthan; Chartered Accountant: ROSHAN GAWDE & CO; Chartered Accountant: A K O R D & CO. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in TOWER INDUSTRIAL PARK?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; how the declared litigation on this registration affects your risk; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About TOWER INDUSTRIAL PARK. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save TOWER INDUSTRIAL PARK to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.