The Virtuoso Club and Serviced Residences

By Columbia Pacific Communities Private Limited

RG-KA-88041 · RERA PRM/KA/RERA/1251/446/PR/190809/002770 · Last updated on RERA Karnataka portal: 9 Aug 2022

Source: official RERA Karnataka filing

Red flags

  • 1 complaint at RERA Karnataka
  • Completion date moved by 9 months
  • 1 extension taken

Clear

  • Separate project account declared
Sep 2024Possession promisedmoved 9 months from the original
1Complaints at RERA Karnatakaon this registration
Jump to the 110 documents Report an error

The Virtuoso Club and Serviced Residences is a Residential/Group Housing project by Columbia Pacific Communities Private Limited in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/446/PR/190809/002770 on 9 Aug 2019. Possession is promised by 30 Sep 2024. The completion date has moved by 9 months from the original filing. 1 complaint is on record with the regulator.

At a glance

Project

  • NameThe Virtuoso Club and Serviced Residences
  • TypeResidential/Group Housing
  • Location
    • Bengaluru East
    • Bengaluru Urban
  • PincodeNot stated
  • RERA no.PRM/KA/RERA/1251/446/PR/190809/002770
  • ReraGenie IDRG-KA-88041

Builder

  • NameColumbia Pacific Communities Private Limited
  • Entity typeCompany
  • CINU85190TN2009PTC073344
  • Authorized SignatorySIVAKUMAR V

Key dates

this monthRegisteredAug 2019First promiseDec 2023Revised toSep 2024

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on9 Aug 2019
  • Promised completion30 Sep 2024
  • Revised completionRevised to 30 Sep 2024 (originally 31 Dec 2023)
  • Buildings2 building records
  • Documents filed110 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Tower A---80080
Tower B---71071

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 9 Aug 2022, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

Building:

ActivityProgress
Earth work and other leveling preparation work-
Foundation footing work-
Retaining wall (All types)-
Plinth level Beam-
Sub-structure flooring (Parking Floor, more than one floor below general ground level)-
RCC or MS Framed structure-
Masonry construction: Bricks, Concrete blocks etc-
Plastering inside , outside & Ceiling-
Joinery: Doors, Windows, Ventilators etc-
Basic work of Water supply, Sanitary and Electrification-
Dadoing, Skirting, Flooring, Tiles work (All types)-
Railing and Grill fixing-
Electrification, Water supply and Sanitary Finishing-
Wardrobe, Showcase, Kitchen cabinet, Puja work-
Fire prevention and fire fighting fitting and fixture with network-
Weather Proof work(tile,concrete)-
Painting-
Elevation work-
Internal and External work including landscapes as per santioned drawings-

Progress on shared amenities41

As on 9 Aug 2022, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes-
Internal Roads & FootpathsYes-
Sewage and Drainage SystemYes-
Parks & Tree plantingYes-
Street LightingYes-
Provision for community buildings and for treatment and disposal of sewage and sullage waterYes-
Solid waste management and disposalYes-
Water conservationYes-
Energy managementYes-
Fire protection and fire safety requirementsYes-
Education/Health/Other public amenitiesYes-
Electricity supply transformer and substationYes-
Emergency Evacuation servicesYes-
Storm water drainsYes-
Use of renewable energyYes-
Water conservation/rain water harvesting/recharge of ground waterYes-
ElectricityYes-
Smart Home AutomationNoNot applicable
CCTV SurveillanceYes-
Club HouseYes-
Community HallYes-
Outdoor Sports facilityYes-
Indoor Sports facilityYes-
Swimming PoolYes-
GymYes-
ParksYes-
Power BackupYes-
GasNoNot applicable
Water and SanitationYes-
Air Conditioning And incerntionYes-
StaircasesYes-
LiftsYes-
Staircases and Lift lobbies, corridor,lobbies, corridorYes-
Fire escapesYes-
Common entrance and exit for the building / common portico/foyer/verandahYes-
BasementYes-
TerraceYes-
Outer WallYes-
Open parking areas and common storage spacesYes-
Provision for lodging of management staff and security staffYes-
Water conservation and renewable energyYes-

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area8,195 sq m
Named landownersNone

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 61.00 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectM/s Venkataramanan Associates
EngineerA N Prakash Construction Project Management Consultants Pvt Ltd

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

ExtensionDec 2023 → not stated

No reason recorded in the filing

Complaints filed with RERA Karnataka1

Case no.ComplainantRespondentFiled
CMP/220517/0009476-Columbia Pacific Communities Private Limited17/05/2022

Documents filed110

As listed on the registration, under the names the promoter filed them with; the newest 80 of 110 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/446/PR/190809/002770 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Agreement of SaleFile: Agreement of Sale.pdf9 Aug 2022
Panchayat water NOCFile: Water NOC from Panchayat.pdf9 Aug 2022
Panchayat OrderFile: Panchayat Order.pdf5 Mar 2022
Consent LetterFile: consent letter reply.pdf5 Mar 2022
Basement PlanFile: Basement Plan.pdf8 Feb 2022
Site PlanFile: Site Plan.pdf8 Feb 2022
Elevation AFile: Elevation A.pdf8 Feb 2022
Section X PlanFile: Section X plan.pdf8 Feb 2022
Ground floor planFile: Ground floor plan.pdf8 Feb 2022
First floor planFile: First floor plan.pdf8 Feb 2022
Terrace planFile: Terrace Plan.pdf8 Feb 2022
Typical floor planFile: Typical floor plan.pdf8 Feb 2022
Borewell ReceiptFile: Borewell Application Acknowledgements.pdf8 Feb 2022
Commencement CertificateFile: Commencement Certificat.pdf8 Feb 2022
Panchayat OrderFile: Panchayat Order.pdf8 Feb 2022
Old Plan area breakupFile: Old plan area breakup.pdf8 Feb 2022
List of Directors/ MembersFile: List of Directors or Members.pdf8 Feb 2022
Consent LettersFile: CONSENT LETTERS.pdf8 Feb 2022
QU ScreenshotFile: COLUMBIA QU2 2021.png11 Jan 2022
Bank StatementFile: RERA bank statement.pdf11 Jan 2022
Modification PlanFile: Modified plan.pdf11 Jan 2022
AffidavitFile: Affidavit.pdf11 Jan 2022
Sold unsold unitsFile: Sold Unsold Units.xlsx11 Jan 2022
BESCOM NOCFile: Bescom NOC - Revised.pdf11 Jan 2022
Architect CertificateFile: Revised Architect Certificate for Modified Plan.pdf11 Jan 2022
CertificateFile: Registration certificate.pdf-
Modified plan details site plan, floor plans, Plan Licence LetterFile: SITE PLAN.pdf-
Elevation, Sections, Specifications ( If changes are there )File: ELEVATION PLAN.pdf-
List Of AllotteesFile: LIST OF ALLOTTEES.pdf-
List Of ComplaintsFile: NO PENDING COMPLAINTS.pdf-
Consent LetterFile: CONSENT LETTERS.pdf-
List Of Pending LitigationsFile: NO PENDING LITIGATIONS.pdf-
Chartered Accountant CertificateFile: CHARTERED ACCOUNTANT CERTIFICATE MODIFICATION.pdf-
Notarized AffidavitFile: NOTARIZED AFFIDAVIT FOR MODIFICATION.pdf-
Engineer CertificateFile: ENGINEER CERTIFICATE MODIFICATION COLUMBIA.pdf-
Architect CertificateFile: ARCHITECT CERTIFICATE MODIFICATION COLUMBIA.pdf-
Structural Engineer Certificate for stability of structureFile: STRUCTURAL PRE STABILITY CERTIFICATE.PDF-
Modification of Plan DetailsFile: Site Plan.pdf-
Modification of Plan DetailsFile: SITE PLAN.pdf-
Modification of Plan DetailsFile: REGISTER PLAN COMMENCEMENT CERTIFICATE.pdf-
Modification of Plan DetailsFile: MODIFIED PLAN COMMENCEMENT CERTIFICATE.pdf-
Modification of Plan DetailsFile: LIST OF SOLD AND UNSOLD DETAILS.pdf-
Modification of Plan DetailsFile: LIST OF SOLD AND UNSOLD DETAILS.pdf-
SECTION X PLANFile: SECTION X PLAN.pdf-
ELEVATION PLANFile: ELEVATION PLAN.pdf-
TERRACE PLANFile: TERRACE PLAN.pdf-
SECOND AND 10TH FLOOR PLANFile: SECOND AND TENTH FLOOR PLAN.pdf-
TYPICAL FLOOR PLAN 3RD TO 9THFile: TYPICAL FLOOR PLAN 3RD TO 9TH.pdf-
FIRST FLOOR PLANFile: FIRST FLOOR PLAN.pdf-
GROUND FLOOR PLANFile: GROUND FLOOR PLAN.pdf-
BASEMENT PLANFile: BASEMENT PLAN.pdf-
SITE PLANFile: SITE PLAN.pdf-
RERA DESIGNATED BANK ACCOUNT STATEMENTFile: RERA DESIGNATED BANK ACCOUNT STATEMENT.pdf-
REASON FOR MODIFICATIONFile: REASON FOR MODIFICATION UNDERTAKING LETTER.pdf-
Commencement certificate-
All Plans-
Allotment Letter-
Allotment Letter-
Sale_Deed_and_RTC-
Section_Elevation-
Ground Floor-
Allotment Letter-
Note - Consents-
Project Specification-
RERA_EC-
Affidavit-
Khata-
Conversion OM-
Relinquishment Deed-
Fire Authority-
Airport authority NOC-
BESCOM NOC-
Water Supply-
KSPBCB_CFE-
Section_Elevation-
Balance Sheet 2017 - 2018File: BS 17-18.pdf-
Balance Sheet 2016 - 2017File: BS 16-17.pdf-
Balance Sheet 2015 - 2016File: BS 15-16.pdf-
Audited Profit and Loss Statement 2017 - 2018File: P&L 17-18.pdf-
Audited Profit and Loss Statement 2016 - 2017File: P&L 16-17.pdf-

How this compares with Bengaluru Urban

34%of Bengaluru Urban projects moved their completion datethis one moved by 9 months
1%of Bengaluru Urban registrations are shown as withdrawn or revokedthis one is not

Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.

Keep The Virtuoso Club and Serviced Residences on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bengaluru Urban4,100+ in Bengaluru Urban

Builder: Columbia Pacific Communities Private Limited

Columbia Pacific Communities Private Limited has 1 registration on RERA Karnataka, including The Virtuoso Club and Serviced Residences. Its filings disclose no earlier RERA Karnataka projects. Read the full track record. See more projects on the Bengaluru Urban district page.

Frequently asked questions

What are my rights if The Virtuoso Club and Serviced Residences is delayed beyond 30 Sep 2024?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of The Virtuoso Club and Serviced Residences?

The registered promoter entity is Columbia Pacific Communities Private Limited, a company as per the filing. Its CIN U85190TN2009PTC073344 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in The Virtuoso Club and Serviced Residences?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against The Virtuoso Club and Serviced Residences?

Each case number above is a complaint filed with RERA Karnataka. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

Who certifies construction progress at The Virtuoso Club and Serviced Residences?

The professionals named in the filing: Architect: M/s Venkataramanan Associates; Engineer: A N Prakash Construction Project Management Consultants Pvt Ltd. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in The Virtuoso Club and Serviced Residences?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About The Virtuoso Club and Serviced Residences. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save The Virtuoso Club and Serviced Residences to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.