  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
Dec 2028Possession promisedno revision filed
0 of 17Construction stages donefurthest along: Earth work and other leveling..., 55%
272 of 391Units unsoldnot recorded sold or booked
0Complaints at RERA Karnatakaon this registration
Jump to the 115 documents Report an error

The Urban Forest is a Residential/Group Housing project by Keya Homes in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/310/PR/200525/007759 on 20 May 2025. Possession is promised by 31 Dec 2028. 119 of the 391 units on this registration are recorded sold or booked, and 0 of 17 construction stages are filed complete.

At a glance

Project

  • NameThe Urban Forest
  • TypeResidential/Group Housing
  • Location
    • Bengaluru South
    • Bengaluru Urban
    • 560035
  • Pincode560035
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PRM/KA/RERA/1251/310/PR/200525/007759
  • ReraGenie IDRG-KA-28244

Builder

  • NameKeya Homes
  • Entity typeCompany
  • CINU70109KA2013PTC068958
  • GSTIN29AAFCK1456Q1ZW
  • Authorized SignatoryDinesh Kejriwal
  • DirectorsDinesh Kejriwal, Dinesh Kejriwal, Bipin Ram Agarwal
  • Project HeadNayan Kumar Mookim
  • Declared earlier projects2 →

Key dates

this monthRegisteredMay 2025PromisedDec 2028

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on20 May 2025
  • Promised completion31 Dec 2028
  • Revised completionNone
  • Buildings2 building records
  • Documents filed115 files

Current status

30%119 of 391 units booked
8.5%Of the estimated cost spent so far

Figures as on 10 Aug 2026, this project's latest RERA Karnataka filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Tower A---1980198
Tower B---1930193

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 10 Aug 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

0 of 17 construction stages are filed complete. The stage furthest along is Earth work and other leveling preparation work, at 55%.

Building: 15% average across the applicable activities

ActivityProgress
Earth work and other leveling preparation work55%
Foundation footing work50%
Upto Plinth Level45%
Sub-structure flooring (Parking Floor, more than one floor below general ground level)40%
Retaining wall (All types)35%
RCC or MS Framed structure30%
Masonry Construction0%
Plastering inside , outside & Ceiling0%
Joinery: Doors, Windows, Ventilators etc0%
Basic work of Water supply, Sanitary and Electrification0%
Dadoing, Skirting, Flooring, Tiles work (All types)0%
Railing and Grill fixing0%
Electrification, Water supply and Sanitary Finishing0%
Painting0%
Fire prevention and fire fighting fitting and fixture with network0%
Weather Proof work(tile,concrete)0%
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Elevation workNot applicable
Internal and External work including landscapes as per sanctioned drawings0%

Progress on shared amenities40

As on 10 Aug 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes0%
Sewage and Drainage SystemYes0%
Water conservation/rain water harvesting/recharge of ground waterYes0%
Energy managementYes0%
Fire protection and fire safety requirementsYes0%
Solid waste management and disposalYes0%
Emergency Evacuation servicesYes0%
Internal Roads & FootpathsYes0%
Electricity supply transformer and substationYes0%
Storm water drainsYes0%
Use of renewable energyYes0%
Sewage Treatment Plant (STP)Yes0%
Parks & Tree plantingYes0%
Street LightingYes0%
ElectricityYes0%
Smart Home AutomationNoNot applicable
CCTV SurveillanceYes0%
Club HouseNoNot applicable
Community HallNoNot applicable
Outdoor Sports facilityYes0%
Indoor Sports facilityNoNot applicable
Swimming PoolNoNot applicable
GymNoNot applicable
ParksYes0%
Power BackupYes0%
Piped GasYes0%
Water and SanitationYes0%
Air ConditioningNoNot applicable
StaircasesYes0%
LiftsYes0%
Corridor/LobbiesYes0%
Fire escapesYes0%
Common entrance and exit for the building/common portico/foyer/verandahYes0%
BasementYes0%
TerraceNoNot applicable
Outer WallNoNot applicable
Open parking areasNoNot applicable
Provision for lodging of management staff and security staffYes0%
Water conservation and renewable energyYes0%
Common storage spacesNoNot applicable

Land and ownership3

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area29,001 sq m
Named landowners3
LandownerVillageDistrict
M/s Golden Gate Projects--
M/s Golden Gate Projects--
M/s Golden Gate Projects--

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 248.43 cr
Cost incurredRs 21.07 cr
Spent of the estimate8.48%
Cost lineEstimatedIncurred
Estimated Cost of Construction as certified by EngineerRs 248.43 crRs 21.07 cr

Certifying professionals and partners3

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectAnup Naik
EngineerPradeep G Kedlaya
Chartered AccountantNikshith K V

Complaints filed with RERA Karnataka

No complaints on record against this registration.

Documents filed115

As listed on the registration, under the names the promoter filed them with; the newest 80 of 115 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/310/PR/200525/007759 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Q1 2026-27 Form-4 Certificate issued by Chartered AccountantFile: 202608071649.pdf10 Aug 2026
Q1 2026-27 Form-5 Certificate issued by ArchitectFile: RERA 01- 22-02-2026.pdf10 Aug 2026
Q1 2026-27 Form-6 Certificate issued by Structural EngineerFile: KEYA URBAN FOREST AS ON 30-06-2026.pdf10 Aug 2026
Q1 2026-27 Water supply and sewage board10 Aug 2026
Q1 2026-27 KPTCL- BESCOM10 Aug 2026
Q1 2026-27 Fire and Safety10 Aug 2026
Q1 2026-27 Airport Authority of India10 Aug 2026
Q1 2026-27 BSNL/Telecommunication Department10 Aug 2026
Q4 2025-26 Form-4 Certificate issued by Chartered AccountantFile: TUF-25-36-Q4.pdf20 May 2026
Q4 2025-26 Form-5 Certificate issued by ArchitectFile: TUF Q4 - Signed.pdf20 May 2026
Q4 2025-26 Form-6 Certificate issued by Structural EngineerFile: MISC 260307 KEYA URBAN FOREST.pdf20 May 2026
Q4 2025-26 Water supply and sewage board20 May 2026
Q4 2025-26 KPTCL- BESCOM20 May 2026
Q4 2025-26 Fire and Safety20 May 2026
Q4 2025-26 Airport Authority of India20 May 2026
Q4 2025-26 BSNL/Telecommunication Department20 May 2026
Q3 2025-26 Form-4 Certificate issued by Chartered AccountantFile: TUF-25-26-Q3.pdf23 Apr 2026
Q3 2025-26 Form-5 Certificate issued by ArchitectFile: Q3 25-26 Signed.pdf23 Apr 2026
Q3 2025-26 Form-6 Certificate issued by Structural EngineerFile: MISC 251210 KEYA URBAN FOREST.pdf23 Apr 2026
Q3 2025-26 Water supply and sewage board23 Apr 2026
Q3 2025-26 KPTCL- BESCOM23 Apr 2026
Q3 2025-26 Fire and Safety23 Apr 2026
Q3 2025-26 Airport Authority of India23 Apr 2026
Q3 2025-26 BSNL/Telecommunication Department23 Apr 2026
Bank affidavitFile: A-1 Bank Affidavit.pdf17 May 2025
CA CertificateFile: A-2 CA Form1.pdf17 May 2025
EC 29/6File: A-4 EC 29_6.pdf17 May 2025
Title ClarificationFile: A-5 TITLE DEED CLARIFICATION.pdf17 May 2025
EC 30/2A and 30/2BFile: A-6 EC 30_2A 30_2B.pdf17 May 2025
Katha Extract 30/2A and 30/2BFile: A-7 KATHA 30_2A 30_2B.pdf17 May 2025
Non Litigation AffidavitFile: Non Litigation Affidavit.pdf17 May 2025
Form B AffidavitFile: A-9 FORM B.pdf17 May 2025
JDA AffidavitFile: A-10 JD AFFIDAVIT.pdf17 May 2025
Single Layout approval planFile: A-11 SINGLE LAYOUT PLAN.pdf17 May 2025
Single Layout approval plan OrderFile: A-12 SINGLE LAYOUT PLAN ORDER.pdf17 May 2025
Building PlanFile: A-13 BUILDING PLAN.pdf17 May 2025
Master PlanFile: CDP Master Plan.jpeg17 May 2025
Village MapFile: A-15 VILLAGE MAP.pdf17 May 2025
ADLR Survey SketchFile: A-16 ADLR SURVEY SKETCH.pdf17 May 2025
Floor PlansFile: A-17 FLOOR PLANS.pdf17 May 2025
KSPCB NOCFile: A-18 KSPCB NOC.pdf17 May 2025
SEIAA NOCFile: A-19 SEIAA NOC.pdf17 May 2025
Engineer licenseFile: A-22 ENGINEER LICENCE.pdf17 May 2025
Engineer Certificate and Brief EstimationFile: A-23 ENGINEER CERTIFICATE.pdf17 May 2025
BWSSB NOCFile: A-26 BWSSB NOC.pdf17 May 2025
HAL NOCFile: A-27 HAL NOC.pdf17 May 2025
STP DesignFile: A-28 STP.pdf17 May 2025
Land Cost CalculationFile: A-29 LAND CALCULATION.pdf17 May 2025
Source of WaterFile: Water Source.pdf17 May 2025
RTC, survey 29/6-
Mutation, survey 29/6-
Encumbrance Certificate, survey 29/6-
Conversion/Alienation Order, survey 29/6-
Sale/Title/Gift Deed, survey 29/6-
JDA, survey 29/6-
Khatha, survey 29/6-
RTC, survey 30/2A-
Mutation, survey 30/2A-
Encumbrance Certificate, survey 30/2A-
Conversion/Alienation Order, survey 30/2A-
Sale/Title/Gift Deed, survey 30/2A-
JDA, survey 30/2A-
Khatha, survey 30/2A-
RTC, survey 30/2B-
Mutation, survey 30/2B-
Encumbrance Certificate, survey 30/2B-
Conversion/Alienation Order, survey 30/2B-
Sale/Title/Gift Deed, survey 30/2B-
JDA, survey 30/2B-
Khatha, survey 30/2B-
Registration CertificateFile: A-1.pdf-
Memorandum of AssociationFile: A-15.pdf-
Article of AssociationFile: A-16.pdf-
GST CertificateFile: A-3.pdf-
Organization StructureFile: A-14.pdf-
Certificate issued by CA Form 1File: A-2 CA Form1.pdf-
Certificate issued by Architect Form 2File: A-61.pdf-
Certificate issued by Engineer Form 3File: A-23 ENGINEER CERTIFICATE.pdf-
Project Chartered Accountant-
Project Engineer-

Promoter's earlier projects2

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

2 declared completed, no finish date filed
ProjectLocationStatusPromisedDelivered
Life By The LakeNear Jakkur Lake Road, Nehru Nagar, Yelahanka Yelahanka, Agrahara, Bengaluru, Karnataka 560064Completed-No date filed
Around The Life2Q47+FG4, Chaitanya Ananya, Krishnarajapuram, Bengaluru, Karnataka 560067Completed-No date filed

How this compares with Bengaluru Urban

30%of this project is bookeddistrict median 51%
34%of Bengaluru Urban projects moved their completion datethis one has not
1%of Bengaluru Urban registrations are shown as withdrawn or revokedthis one is not

Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.

Keep The Urban Forest on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bengaluru Urban4,100+ in Bengaluru Urban

2 kmThe Urban ForestOther 37Dot size: filed unitsN

Filed coordinates, straight-line distance. 37 registered projects within 2 km.

Builder: Keya Homes

Keya Homes has 1 registration on RERA Karnataka, including The Urban Forest. Its filings declare 2 earlier projects, 2 of them declared completed. Read the full track record. See more projects on the Bengaluru Urban district page.

Frequently asked questions

What are my rights if The Urban Forest is delayed beyond 31 Dec 2028?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of The Urban Forest?

The registered promoter entity is Keya Homes, a company as per the filing. Its CIN U70109KA2013PTC068958 and GSTIN 29AAFCK1456Q1ZW can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in The Urban Forest?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at The Urban Forest?

The professionals named in the filing: Architect: Anup Naik; Engineer: Pradeep G Kedlaya; Chartered Accountant: Nikshith K V. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in The Urban Forest?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About The Urban Forest. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save The Urban Forest to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.