East Park Residences

By Ramsons Trendsquares Realty LLP

RG-KA-19049 · RERA PRM/KA/RERA/1251/310/PR/280224/006657 · Last updated on RERA Karnataka portal: 15 Oct 2026

Source: official RERA Karnataka filing

Red flags

  • 2 complaints at RERA Karnataka

Clear

  • No litigation declared
  • Completion date never moved
  • Separate project account declared
Mar 2028Possession promisedno revision filed
4 of 18Construction stages donefurthest along: RCC or MS Framed structure, 90%
36 of 497Units unsoldnot recorded sold or booked
2Complaints at RERA Karnatakaon this registration
Jump to the 237 documents Report an error

East Park Residences is a Residential/Group Housing project by Ramsons Trendsquares Realty LLP in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/310/PR/280224/006657 on 28 Feb 2024. Possession is promised by 31 Mar 2028. 461 of the 497 units on this registration are recorded sold or booked, and 4 of 18 construction stages are filed complete. 2 complaints are on record with the regulator.

At a glance

Project

  • NameEast Park Residences
  • TypeResidential/Group Housing
  • Location
    • Bengaluru South
    • Bengaluru Urban
    • 560035
  • Pincode560035
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PRM/KA/RERA/1251/310/PR/280224/006657
  • ReraGenie IDRG-KA-19049

Builder

  • NameRamsons Trendsquares Realty LLP
  • Entity typePartnership Firm
  • LLPINABZ-0288
  • GSTIN29ABGFR0106B1ZQ
  • Authorized SignatoryKARTHIK SHEKAR

Key dates

this monthRegisteredFeb 2024PromisedMar 2028

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on28 Feb 2024
  • Promised completion31 Mar 2028
  • Revised completionNone
  • Buildings6 building records
  • Documents filed237 files

Current status

93%461 of 497 units booked
79.6%Of the estimated cost spent so far

Figures as on 15 Oct 2026, this project's latest RERA Karnataka filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
A---1230123
B---1000100
C---1000100
D---1220122
E---1000100
F---1150115

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 15 Oct 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

4 of 18 construction stages are filed complete. The stage furthest along is RCC or MS Framed structure, at 90%.

Building: 48% average across the applicable activities

ActivityProgress
Earth work and other leveling preparation work100%
Foundation footing work100%
Retaining wall (All types)100%
Plinth level Beam100%
Sub-structure flooring (Parking Floor, more than one floor below general ground level)50%
RCC or MS Framed structure90%
Masonry construction: Bricks, Concrete blocks etc50%
Plastering inside , outside & Ceiling45%
Joinery: Doors, Windows, Ventilators etc15%
Basic work of Water supply, Sanitary and Electrification25%
Dadoing, Skirting, Flooring, Tiles work (All types)55%
Railing and Grill fixing25%
Electrification, Water supply and Sanitary Finishing5%
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Fire prevention and fire fighting fitting and fixture with network50%
Weather Proof work(tile,concrete)0%
Painting20%
Elevation work30%
Internal and External work including landscapes as per santioned drawings0%

Progress on shared amenities41

As on 15 Oct 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes50%
Internal Roads & FootpathsYes10%
Sewage and Drainage SystemYes20%
Parks & Tree plantingYes0%
Street LightingYes0%
Provision for community buildings and for treatment and disposal of sewage and sullage waterYes0%
Solid waste management and disposalYes0%
Water conservationYes0%
Energy managementYes0%
Fire protection and fire safety requirementsYes50%
Education/Health/Other public amenitiesNoNot applicable
Electricity supply transformer and substationYes0%
Emergency Evacuation servicesYes0%
Storm water drainsYes0%
Use of renewable energyYes0%
Water conservation/rain water harvesting/recharge of ground waterYes0%
ElectricityYes20%
Smart Home AutomationNoNot applicable
CCTV SurveillanceYes20%
Club HouseYes50%
Community HallYes0%
Outdoor Sports facilityYes0%
Indoor Sports facilityYes0%
Swimming PoolYes20%
GymYes0%
ParksYes0%
Power BackupYes0%
GasNoNot applicable
Water and SanitationYes20%
Air Conditioning And incerntionNoNot applicable
StaircasesYes60%
LiftsYes30%
Staircases and Lift lobbies, corridor,lobbies, corridorYes50%
Fire escapesYes40%
Common entrance and exit for the building / common portico/foyer/verandahYes30%
BasementYes20%
TerraceYes60%
Outer WallYes0%
Open parking areas and common storage spacesYes0%
Provision for lodging of management staff and security staffYes0%
Water conservation and renewable energyNoNot applicable

Land and ownership1

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area26,557 sq m
Named landowners1
LandownerVillageDistrict
Ramsons Trensquares Realty LLP--

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 566.25 cr
Cost incurredRs 450.99 cr
Spent of the estimate79.64%
Cost lineEstimatedIncurred
Estimated Cost of Construction as certified by EngineerRs 448.25 crRs 351.80 cr
Administrative CostsRs 118.00 crRs 99.19 cr

Certifying professionals and partners3

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectINDRAJITH S KEMBHAVI
EngineerYASHAVANTH ANANTHARAJ
Chartered AccountantDEEPAK BUBNA

Complaints filed with RERA Karnataka2

Case no.ComplainantRespondentFiled
01156/2024-Ramsons Trendsquares Realty LLP13/11/2024
00084/2026-Ramsons Trendsquares Realty LLP05/02/2026

Documents filed237

As listed on the registration, under the names the promoter filed them with; the newest 80 of 237 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/310/PR/280224/006657 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Q2 2026-27 Form-4 Certificate issued by Chartered AccountantFile: Ramsons Trendsquares Realty LLP-RERA Certificate-FY 2026-27-Q2.pdf15 Oct 2026
Q2 2026-27 Form-5 Certificate issued by ArchitectFile: 02 Form-5, Architect - Sept-signed.pdf15 Oct 2026
Q2 2026-27 Form-6 Certificate issued by Structural EngineerFile: 01 Form-6, Engineer Certificate - September.pdf15 Oct 2026
Q2 2026-27 Water supply and sewage board15 Oct 2026
Q2 2026-27 Engineering Department (PWD) for completion of development works15 Oct 2026
Q2 2026-27 KPTCL- BESCOM15 Oct 2026
Q2 2026-27 Fire and Safety15 Oct 2026
Q2 2026-27 Airport Authority of India15 Oct 2026
Q2 2026-27 BSNL/Telecommunication Department15 Oct 2026
Q1 2026-27 Form-4 Certificate issued by Chartered AccountantFile: 02 RTL CA Certificate - Q1 FY 26-26 with Annex_compressed.pdf15 Jul 2026
Q1 2026-27 Form-5 Certificate issued by ArchitectFile: 01 Form-5, Architect - June- Signed.pdf15 Jul 2026
Q1 2026-27 Form-6 Certificate issued by Structural EngineerFile: 01 Form-6, Engineer Certificate - June.pdf15 Jul 2026
Q1 2026-27 Water supply and sewage board15 Jul 2026
Q1 2026-27 Engineering Department (PWD) for completion of development works15 Jul 2026
Q1 2026-27 KPTCL- BESCOM15 Jul 2026
Q1 2026-27 Fire and Safety15 Jul 2026
Q1 2026-27 Airport Authority of India15 Jul 2026
Q1 2026-27 BSNL/Telecommunication Department15 Jul 2026
Q4 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Ramsons Trendquare-RERA Certificate-FY 2025-26-Q4.pdf15 Apr 2026
Q4 2025-26 Form-5 Certificate issued by ArchitectFile: 01 Form-5, Architect - March 2026-Signed.pdf15 Apr 2026
Q4 2025-26 Form-6 Certificate issued by Structural EngineerFile: Form 6.pdf15 Apr 2026
Q4 2025-26 Water supply and sewage board15 Apr 2026
Q4 2025-26 Engineering Department (PWD) for completion of development works15 Apr 2026
Q4 2025-26 KPTCL- BESCOM15 Apr 2026
Q4 2025-26 Fire and Safety15 Apr 2026
Q4 2025-26 Airport Authority of India15 Apr 2026
Q4 2025-26 BSNL/Telecommunication Department15 Apr 2026
Q3 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Ramsons-RERA Certificate-FY 2025-26-Q3.pdf15 Jan 2026
Q3 2025-26 Form-5 Certificate issued by ArchitectFile: 01 Form-5, Architect - December-Signed.pdf15 Jan 2026
Q3 2025-26 Form-6 Certificate issued by Structural EngineerFile: DocScanner Jan 14, 2026 5-27 PM.pdf15 Jan 2026
Q3 2025-26 Water supply and sewage board15 Jan 2026
Q3 2025-26 Engineering Department (PWD) for completion of development works15 Jan 2026
Q3 2025-26 KPTCL- BESCOM15 Jan 2026
Q3 2025-26 Fire and Safety15 Jan 2026
Q3 2025-26 Airport Authority of India15 Jan 2026
Q3 2025-26 BSNL/Telecommunication Department15 Jan 2026
RAMSON KSPCB NOCFile: RAMSON KSPCB NOC.pdf18 Jun 2025
Ramsons Trendsquare - Stability CertificateFile: Ramsons Trendsquare - Stability Certificate - Preliminary.pdf18 Jun 2025
Engineer CertificateFile: Eng Cerificatecompressed.pdf18 Jun 2025
CA certificateFile: CA Revised RamsonsRERA CertificateMay 2025.pdf18 Jun 2025
BDA LetterFile: BDA Sanction letter -RTRL_compressed.pdf14 Jun 2025
Airport Authority of India NOCFile: Airport Authority of India NOC.pdf26 Feb 2024
Source of FundFile: Source of Fund.pdf26 Feb 2024
STPFile: STP.pdf26 Feb 2024
Affidavit_ HALFile: Affidavit_ HAL.pdf26 Feb 2024
Airport Authority NOCFile: Airport Authority NOC.pdf23 Feb 2024
BDA Approval letterFile: BDA Approval letter.pdf23 Feb 2024
External InfrastructureFile: External Infrastructure.pdf23 Feb 2024
Plot Details & Inventories DetailsFile: Plot Details & Inventories Details.pdf23 Feb 2024
STPFile: STP.pdf23 Feb 2024
Water NOCFile: Water NOC.pdf23 Feb 2024
NOC from Air Force AAI BSNLFile: NOC from Air Force AAI BSNL.pdf23 Feb 2024
Airport and HAL Authorities NOCFile: HAL NOC_compressed.pdf1 Feb 2024
Source of WaterFile: Source of Water.pdf1 Feb 2024
STPFile: STP.pdf1 Feb 2024
Water NOCFile: Water NOC (1).pdf1 Feb 2024
proforma of the Allotment letterFile: Allotment Letter.pdf1 Feb 2024
Amenities and common area details ertified by the EngineerFile: amenities and common area.pdf1 Feb 2024
Abstract EstimationFile: Abstract Estimation.pdf23 Jan 2024
Agreement For SaleFile: Agreement For Sale.pdf23 Jan 2024
Bescom NOCFile: Bescom NOC.pdf23 Jan 2024
Balance Sheet and Profit and LossFile: BS and PL.pdf23 Jan 2024
Confederation of Engineering LicenceFile: Confederation of Engineering Licence.pdf23 Jan 2024
Conversion OrderFile: Conversion Order.pdf23 Jan 2024
DEED OF FAMILY PARTITIONFile: DEED OF FAMILY PARTITION.pdf23 Jan 2024
LLP Agreement 2023_24File: LLP Agreement 2023_24.pdf23 Jan 2024
Conversion Order DCFile: Conversion Order 2.pdf23 Jan 2024
RERA Estimates Source of FundsFile: RERA Estimates Source of Funds.pdf23 Jan 2024
RTC 2023_24File: RTC Latest.pdf23 Jan 2024
RTC 2016File: RTC.pdf23 Jan 2024
Panchayath KathaFile: Panchayath Katha.pdf23 Jan 2024
Sale Deed dated 03_12_1959File: Sale Deed dated03121959.pdf23 Jan 2024
Sale Deed dated12_01_1961File: Sale Deed dated12011961.pdf23 Jan 2024
Sale Deed dated12_04_1961File: Sale Deed dated12041961.pdf23 Jan 2024
Sale Deed 03_12_1959File: SD03121959.pdf23 Jan 2024
Sale Deed No 946162File: SD9946162.pdf23 Jan 2024
Source of WaterFile: Source of Water.pdf23 Jan 2024
STP DrawingFile: STP.pdf23 Jan 2024
Tax paid receiptFile: Tax paid receipt.jpeg23 Jan 2024
Title DeedFile: Titble Deed.pdf23 Jan 2024

How this compares with Bengaluru Urban

93%of this project is bookeddistrict median 51%
34%of Bengaluru Urban projects moved their completion datethis one has not
1%of Bengaluru Urban registrations are shown as withdrawn or revokedthis one is not

Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.

Keep East Park Residences on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bengaluru Urban4,100+ in Bengaluru Urban

2 kmEast Park ResidencesOther 56Dot size: filed unitsN

Filed coordinates, straight-line distance. 56 registered projects within 2 km.

Builder: Ramsons Trendsquares Realty LLP

Ramsons Trendsquares Realty LLP has 1 registration on RERA Karnataka, including East Park Residences. Its filings disclose no earlier RERA Karnataka projects. Read the full track record. See more projects on the Bengaluru Urban district page.

Frequently asked questions

What are my rights if East Park Residences is delayed beyond 31 Mar 2028?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of East Park Residences?

The registered promoter entity is Ramsons Trendsquares Realty LLP, a partnership firm as per the filing. Its LLPIN ABZ-0288 and GSTIN 29ABGFR0106B1ZQ can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in East Park Residences?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against East Park Residences?

Each case number above is a complaint filed with RERA Karnataka. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

Who certifies construction progress at East Park Residences?

The professionals named in the filing: Architect: INDRAJITH S KEMBHAVI; Engineer: YASHAVANTH ANANTHARAJ; Chartered Accountant: DEEPAK BUBNA. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in East Park Residences?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About East Park Residences. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save East Park Residences to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.