RG-KA-90349 · RERA PRM/KA/RERA/1251/309/PR/171014/000565 · Last updated on RERA Karnataka portal: 29 Oct 2026

Source: official RERA Karnataka filing

Red flags

  • 11 complaints at RERA Karnataka
  • Completion date moved by 72 months
  • 3 extensions taken

Clear

  • No litigation declared
  • Separate project account declared
Jun 2027Possession promisedmoved 72 months from the original
7 of 17Construction stages donefurthest along: Masonry construction: Bricks, 96%
98 of 368Units unsoldnot recorded sold or booked
11Complaints at RERA Karnatakaon this registration
Jump to the 86 documents Report an error

The Presidential Tower is a Residential/Group Housing project by Best Golden Developers Pvt Ltd in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/309/PR/171014/000565 on 14 Oct 2017. Possession is promised by 30 Jun 2027. The completion date has moved by 72 months from the original filing. 270 of the 368 units on this registration are recorded sold or booked, and 7 of 17 construction stages are filed complete. 11 complaints are on record with the regulator.

At a glance

Project

  • NameThe Presidential Tower
  • TypeResidential/Group Housing
  • Location
    • Bengaluru North
    • Bengaluru Urban
  • PincodeNot stated
  • RERA no.PRM/KA/RERA/1251/309/PR/171014/000565
  • ReraGenie IDRG-KA-90349

Builder

  • NameBest Golden Developers Pvt Ltd
  • Entity typeCompany
  • CINU70100KA2011PTC061674
  • Authorized SignatorySanjay raj C D
  • DirectorSanjay raj C D

Key dates

this monthRegisteredOct 2017First promiseJun 2021Revised toJun 2027

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on14 Oct 2017
  • Promised completion30 Jun 2027
  • Revised completionRevised to 30 Jun 2027 (originally 30 Jun 2021)
  • Buildings1 building record
  • Documents filed86 files

Current status

73%270 of 368 units booked
67.8%Of the estimated cost spent so far

Figures as on 29 Oct 2026, this project's latest RERA Karnataka filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
The Presidential Tower---3680368

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 29 Oct 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

7 of 17 construction stages are filed complete. The stage furthest along is Masonry construction: Bricks, at 96%.

Building: 85% average across the applicable activities

ActivityProgress
Earth work and other leveling preparation work100%
Foundation footing work100%
Retaining wall (All types)100%
Plinth level Beam100%
Sub-structure flooring (Parking Floor, more than one floor below general ground level)100%
RCC or MS Framed structure100%
Masonry construction: Bricks, Concrete blocks etc96%
Plastering inside , outside & Ceiling95%
Joinery: Doors, Windows, Ventilators etc68%
Basic work of Water supply, Sanitary and Electrification68%
Dadoing, Skirting, Flooring, Tiles work (All types)70%
Railing and Grill fixing80%
Electrification, Water supply and Sanitary Finishing50%
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Fire prevention and fire fighting fitting and fixture with network100%
Weather Proof work(tile,concrete)80%
Painting85%
Elevation workNot applicable
Internal and External work including landscapes as per santioned drawings50%

Progress on shared amenities41

As on 29 Oct 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes35%
Internal Roads & FootpathsYes65%
Sewage and Drainage SystemYes55%
Parks & Tree plantingYes35%
Street LightingYes75%
Provision for community buildings and for treatment and disposal of sewage and sullage waterYes60%
Solid waste management and disposalYes55%
Water conservationYes20%
Energy managementYes0%
Fire protection and fire safety requirementsYes100%
Education/Health/Other public amenitiesYes-
Electricity supply transformer and substationYes80%
Emergency Evacuation servicesYes100%
Storm water drainsYes60%
Use of renewable energyYes50%
Water conservation/rain water harvesting/recharge of ground waterYes55%
ElectricityYes50%
Smart Home AutomationYes0%
CCTV SurveillanceYes50%
Club HouseYes75%
Community HallYes50%
Outdoor Sports facilityYes20%
Indoor Sports facilityYes55%
Swimming PoolYes82%
GymYes60%
ParksYes75%
Power BackupYes0%
GasYes0%
Water and SanitationYes20%
Air Conditioning And incerntionYes0%
StaircasesYes100%
LiftsYes84%
Staircases and Lift lobbies, corridor,lobbies, corridorYes85%
Fire escapesYes100%
Common entrance and exit for the building / common portico/foyer/verandahYes65%
BasementYes98%
TerraceYes80%
Outer WallYes100%
Open parking areas and common storage spacesYes75%
Provision for lodging of management staff and security staffNoNot applicable
Water conservation and renewable energyYes20%

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area20,234 sq m
Named landownersNone

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 574.83 cr
Cost incurredRs 389.60 cr
Spent of the estimate67.78%
Cost lineEstimatedIncurred
Estimated Cost of Construction as certified by EngineerRs 318.35 crRs 288.18 cr
On-site expenditure-Salaries of workersRs 82.97 crRs 51.34 cr
Principal sum and interest payable to financial institutions-Non Banking financial institution (NBFC)Rs 70.50 cr-
Principal sum and interest payable to financial institutions-Scheduled BanksRs 30.15 cr-
Principal sum and interest payable to financial institutions-Money Lenders on construction funding or money borrowed for constructionRs 25.56 cr-
Payment of feesRs 14.46 crRs 9.04 cr
Payment of taxesRs 13.46 crRs 5.89 cr
On-site expenditure-Site OverheadRs 9.96 crRs 22.58 cr
Payment of chargesRs 6.60 crRs 8.38 cr
On-site expenditure-Cost Of Services(Water, Electricity, Sewage)Rs 2.82 crRs 4.18 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectRajiv Hanumantaiah
EngineerGH basavaraj

Extensions applied for3

A revised date filed with the regulator does not change the possession date in your agreement for sale.

ExtensionJun 2021 → Mar 2022

No reason recorded in the filing

EX/PRM/KA/RERA/1251/309/PR/230223/000565Mar 2022 → Mar 2023

Reason as filed by the promoterothers

ExtensionMar 2023 → Jun 2027

No reason recorded in the filing

Complaints filed with RERA Karnataka11

Case no.ComplainantRespondentFiled
CMP/190515/0003030-Best Golden Developers Pvt Ltd15/05/2019
CMP/190520/0003099-Best Golden Developers Pvt Ltd20/05/2019
CMP/220608/0009606-Best Golden Developers Pvt Ltd08/06/2022
01871/2023-Best Golden Developers Pvt Ltd26/12/2023
00202/2024-Best Golden Developers Pvt Ltd19/02/2024
01156/2025-Best Golden Developers Pvt Ltd11/09/2025
01447/2025-Best Golden Developers Pvt Ltd08/12/2025
01448/2025-Best Golden Developers Pvt Ltd08/12/2025
00456/2026-Best Golden Developers Pvt Ltd02/05/2026
00950/2026-Best Golden Developers Pvt Ltd04/08/2026
01033/2026-Best Golden Developers Pvt Ltd20/08/2026

Documents filed86

As listed on the registration, under the names the promoter filed them with; the newest 80 of 86 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/309/PR/171014/000565 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Q1 2026-27 Form-4 Certificate issued by Chartered AccountantFile: CA Certificate Q1 26-27.pdf29 Oct 2026
Q1 2026-27 Form-5 Certificate issued by ArchitectFile: Architect's Certificate - The Presidential Tower.pdf29 Oct 2026
Q1 2026-27 Form-6 Certificate issued by Structural EngineerFile: Engineer certificate-Q1-26-27.pdf29 Oct 2026
Q1 2026-27 Water supply and sewage board29 Oct 2026
Q1 2026-27 KSPCB- PCB (10 Acres to 125 Acres)29 Oct 2026
Q1 2026-27 KPTCL- BESCOM29 Oct 2026
Q1 2026-27 Fire and Safety29 Oct 2026
Q1 2026-27 Airport Authority of India29 Oct 2026
Q1 2026-27 BSNL/Telecommunication Department29 Oct 2026
Q4 2025-26 Form-4 Certificate issued by Chartered AccountantFile: CA Certificate - Q4.pdf11 Jul 2026
Q4 2025-26 Form-5 Certificate issued by ArchitectFile: Architect Certificate Q4.pdf11 Jul 2026
Q4 2025-26 Form-6 Certificate issued by Structural EngineerFile: Engineer certificate-Q4-25-26.pdf11 Jul 2026
Q4 2025-26 Water supply and sewage board11 Jul 2026
Q4 2025-26 KSPCB- PCB (10 Acres to 125 Acres)11 Jul 2026
Q4 2025-26 KPTCL- BESCOM11 Jul 2026
Q4 2025-26 Fire and Safety11 Jul 2026
Q4 2025-26 Airport Authority of India11 Jul 2026
Q4 2025-26 BSNL/Telecommunication Department11 Jul 2026
Q3 2025-26 Form-4 Certificate issued by Chartered AccountantFile: CA Certificate Q3 Dec 25 Signed Copy.pdf6 Mar 2026
Q3 2025-26 Form-5 Certificate issued by ArchitectFile: Architect Certificate Q3.pdf6 Mar 2026
Q3 2025-26 Form-6 Certificate issued by Structural EngineerFile: TPT-Engg Certificate-Q3(25-26).pdf6 Mar 2026
Q3 2025-26 Water supply and sewage board6 Mar 2026
Q3 2025-26 KSPCB- PCB (10 Acres to 125 Acres)6 Mar 2026
Q3 2025-26 KPTCL- BESCOM6 Mar 2026
Q3 2025-26 Fire and Safety6 Mar 2026
Q3 2025-26 Airport Authority of India6 Mar 2026
Q3 2025-26 BSNL/Telecommunication Department6 Mar 2026
CertificateFile: incorporation certificate.pdf-
Project Details-
Certificate form Architect,Engineer,CA etc.File: Real_Estate_Act.pdf-
Architect Certificate for Work Completion Schedule till DateFile: Arc Certificate work completed.pdf-
Engineer Certificate for Work Completion Schedule till DateFile: Eng Certificate Status of work.pdf-
CA Certificate for Funds UtilizationFile: CA certificate for funds utilisation.pdf-
Architect Certificate for Pending Work Completion Schedule.File: Arc Certificate work completed.pdf-
Engineer Certificate for Pending Work Completion Schedule.File: Arc Certificate work completed.pdf-
CA Certificate for Funds required for Project CompletionFile: CA certificate for funds required.pdf-
AffidavitFile: Affidavit.pdf-
Details Of Sold/ Un-sold UnitsFile: SoldUnsoldDetails for Extension of project_R1.xlsx-
Document 2File: Reason for Delay Letter.pdf-
Document 3File: Affidavit - Form B.pdf-
BBMP - Submitted-
BBMP-
BDA-
Deed of absolutte sale-
AFS_PT_revised by Ramu9 8 17_Defect liabikity 5 years_19Aug 2017-
BDA- Submitted modify -
Approved section of building- Compressed-
RTC & MUTATION-
secation file(1)-
CDP-
Allotment Letter-
Presidential_Tower Brochure- Comp-
all noc(1)-
TPT specification (1)-
ec-
Khata-
JDA- 07102017-
Conversion order-
PT FIRE NOC-
AAI revised NOC-
PT BESCOM NOC-
BWSSB NOC-
PT KSPCB NOC-
BSNL NOC-
Advocates search report-
Balance Sheet 2015 - 2016File: 2016-Balance sheet.pdf-
Balance Sheet 2014 - 2015File: 2015-balance sheet.pdf-
Balance Sheet 2013 - 2014File: 2014-balance sheet.pdf-
Audited Profit and Loss Statement 2015 - 2016File: 2016-Profit and loss.pdf-
Audited Profit and Loss Statement 2014 - 2015File: 2015-Profit loss statament.pdf-
Audited Profit and Loss Statement 2013 - 2014File: 2014-Profit and loss report.pdf-
Director's Report 2015 - 2016File: 2016-Directors report.pdf-
Director's Report 2014 - 2015File: 2015-director report.pdf-
Director's Report 2013 - 2014File: 2014-director report.pdf-
Cash Flow Statement 2015 - 2016File: Doc1- Blank.pdf-
Cash Flow Statement 2014 - 2015File: Doc1- Blank.pdf-
Auditor's Report 2015 - 2016File: 2016-auditorreport compresed.pdf-
Auditor's Report 2014 - 2015File: 2015-independent auditor report.pdf-
Auditor's Report 2013 - 2014File: 2014-auditor report.pdf-
Income Tax Return Acknowledgement 2015 - 2016File: 2016-it returns.pdf-

How this compares with Bengaluru Urban

73%of this project is bookeddistrict median 51%
34%of Bengaluru Urban projects moved their completion datethis one moved by 72 months
1%of Bengaluru Urban registrations are shown as withdrawn or revokedthis one is not

Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.

Keep The Presidential Tower on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bengaluru Urban4,100+ in Bengaluru Urban

Builder: Best Golden Developers Pvt Ltd

Best Golden Developers Pvt Ltd has 1 registration on RERA Karnataka, including The Presidential Tower. Its filings disclose no earlier RERA Karnataka projects. Read the full track record. See more projects on the Bengaluru Urban district page.

Frequently asked questions

What are my rights if The Presidential Tower is delayed beyond 30 Jun 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of The Presidential Tower?

The registered promoter entity is Best Golden Developers Pvt Ltd, a company as per the filing. Its CIN U70100KA2011PTC061674 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in The Presidential Tower?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against The Presidential Tower?

Each case number above is a complaint filed with RERA Karnataka. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

Who certifies construction progress at The Presidential Tower?

The professionals named in the filing: Architect: Rajiv Hanumantaiah; Engineer: GH basavaraj. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in The Presidential Tower?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About The Presidential Tower. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save The Presidential Tower to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.